A ground-oriented multiplex under construction at the framing stage beside a completed identical unit, showing building progress that unlocks each construction loan draw
Financing

Multiplex Construction Loan Draws: How They Work

7 min read

A construction loan doesn't hand you the money up front. You get paid in draws as you build, after an inspector confirms the work. And BC's Builders Lien Act holds back 10% of every payment. Here's the draw schedule, the stages, and the 45-day holdback that catches first-time multiplex builders off guard.

Key takeaway

A builder-focused explainer of how construction loan draws work for a BC multiplex.

Covers the draw schedule concept (money released in stages as work is completed and inspected rather than as a lump sum), the typical stages (land advance, lock-up at about 40% complete, drywall at about 70% complete, final occupancy at 100%), and the BC Builders Lien Act 10% holdback on every progress payment, calculated on the greater of the value of work and materials or the payment made, and released after a minimum 45-day holding period. Explains why lenders monitor lien filings before draws (a registered mortgage has priority for funds advanced before a lien is filed) and how to plan cash flow around draw milestones.

What this covers

  • construction loan draws vs lump sum
  • typical BC draw stages: land, lock-up 40%, drywall 70%, final 100%
  • the 10% Builders Lien Act holdback and 45-day release
  • why lenders check for liens before each draw
  • planning cash flow around draw milestones
multiplex construction-loan draw-schedule builders-lien-act holdback financing

A construction loan does not hand you the money up front. You get paid as you build, in stages, after an inspector confirms the work is actually done. First-time multiplex builders often plan their budget as if the full loan lands on day one, then hit a cash squeeze when the first draw does not cover the early bills. Understanding the draw schedule fixes that before it happens.

There is a second surprise waiting at the end: the 10% builders lien holdback that sits there for weeks after the work is finished. Here is how draws work in BC, when the money actually moves, and what the holdback does to your final numbers.

Draws, not a lump sum

The first thing to unlearn is the idea that a construction loan works like a regular mortgage. It does not. The draw schedule is the heart of a construction loan. It sets out when funds are released to the builder or contractor as work is completed and inspected. The lender is not being difficult. It is protecting itself, and protecting you, from paying for work that has not happened.

That means your early costs, the ones before the first big draw, often come out of your own pocket or a separate facility. If you plan as though the loan covers everything from the start, you can run short exactly when momentum matters. Map your cash needs against the draw schedule, not against the total loan amount.

The typical stages

BC construction draws usually follow a recognizable sequence, tied to how complete the building is. A land advance covers the property purchase. Lock-up comes at roughly 40% complete, once the foundation, framing, and exterior sheathing are in place and the building can be closed up. Drywall follows at about 70% complete, after the plumbing, electrical, and mechanical systems are roughed in. The final draw comes at 100%, on completion and receipt of the occupancy permit.

Each of these is a milestone the lender can verify. An inspector or appraiser confirms the stage before the money moves. So the pace of your draws follows the pace of your build. Fall behind schedule and your draws come later, which means you carry more cost on your own for longer. Keeping the build on pace is not just about the finish date. It is about your cash flow the whole way through.

Horizontal step diagram of construction draw stages: land advance, lock-up at 40 percent complete, drywall at 70 percent complete, and final occupancy at 100 percent

The 10% holdback that catches people out

Now the part that surprises first-timers. BC’s Builders Lien Act requires a minimum holdback of 10% of the value of work done and materials supplied under each payment. This applies to every progress payment under any construction contract in BC. The 10% is calculated on the greater of the actual value of the work and materials provided during the period, or the amount of the payment made on account of the contract price.

So on each draw, 10% is held back. A construction holdback withholds 10% from payments to the general contractor. Two separate clocks then run. Anyone who worked on the project has 45 days to file a claim of lien, counted from the day the certificate of completion is issued (section 20). The holdback period itself expires 55 days after that same certificate (section 8). Those ten extra days let the owner search title for liens filed on day 45 before releasing the money. Plan for it. The last 10% of your money is not available the day the building is done, and it is not available on day 45 either. It sits for 55 days.

Stacked bar of a single construction payment showing 90 percent released to the contractor and a 10 percent holdback, released 55 days after the certificate of completion if no liens are filed

Why lenders check for liens before every draw

There is a legal reason your lender watches for lien filings, and it affects how draws are handled. A registered mortgage has priority over a lien for all funds advanced before the claim of lien is filed. Once a lien is registered, that priority picture changes. So construction lenders typically monitor lien filings before advancing draws, because advancing money after a lien is filed can weaken their security.

For you, the practical effect is that unpaid subtrades are not just an ethical problem, they are a financing problem. If a subtrade files a lien because they were not paid, it can hold up your next draw and complicate your loan. Paying trades properly and keeping clean records is part of keeping your money flowing, not just good manners.

How to plan your cash around the draws

Build a simple cash flow that lines up your expenses with your draw milestones. Know what you have to spend before lock-up, before drywall, and before completion, and know when each draw actually lands after inspection. Then add the holdback: assume you will not see the final 10% for 55 days after the certificate of completion is issued.

The builders who never get squeezed are the ones who treat the draw schedule as a cash flow plan, not a formality. They keep a cushion for the gaps between spending and draws, they keep the build on pace so draws come on time, and they pay their trades so no lien freezes the pipeline. None of that is complicated. It just has to be planned before the first shovel, not discovered mid-build.

Common questions about construction draws

Do I get the whole construction loan up front? No. It comes in draws as the build hits milestones and passes inspection. Typical stages are land advance, lock-up at about 40%, drywall at about 70%, and final at 100% with the occupancy permit. Plan your early cash needs accordingly.

What is the builders lien holdback? BC’s Builders Lien Act requires a 10% holdback on every progress payment (section 4). It gives unpaid workers and suppliers time to file a lien, which they must do within 45 days of the certificate of completion (section 20). The holdback period expires 55 days after that certificate (section 8), which is when the money can be paid out.

When do I get the final 10%? The holdback period expires 55 days after the certificate of completion is issued, and the money can be released then if no lien has been filed. Do not count on that money the day the building finishes, and do not count on it at day 45 when the filing window closes.

Why does my lender care about liens? Because priority depends on timing. A registered mortgage has priority for funds advanced before a lien is filed. Lenders monitor lien filings before releasing draws to protect their security, which is why unpaid trades can stall your funding.

Money follows milestones, and the last slice waits at the end. Plan your cash around the draw schedule and the 55-day holdback period, and you build without the squeeze. Test your project’s numbers in about two minutes before you sit down with a lender.

David Babakaiff, Co-Founder, VanPlex | PlexRank™ | Profit with Multiplex

Frequently asked questions

Do I get my whole construction loan up front for a multiplex build?

No. A construction loan pays out in draws as the build hits milestones and passes inspection, not as a lump sum on day one. The typical BC stages are a land advance, lock-up at roughly 40 percent complete, drywall at roughly 70 percent complete, and a final draw at 100 percent once the occupancy permit is issued. First-time builders who plan their budget as if the full loan arrives up front often hit a cash squeeze when the first draw does not cover early bills.

What is a construction loan lock-up draw?

The lock-up draw is released at roughly 40 percent complete, once the foundation, framing, and exterior sheathing are in place and the building can be closed up. An inspector or appraiser confirms the stage is finished before the lender releases the funds. This is the second milestone in the typical BC sequence, after the land advance and before the drywall draw.

What is the builders lien holdback in BC and how much is it?

BC's Builders Lien Act requires a minimum holdback of 10 percent of the value of work done and materials supplied on every progress payment under any construction contract in BC. The 10 percent is calculated on the greater of the actual value of work and materials provided during the period, or the amount of the payment made on account of the contract price. This holdback applies to every draw, not just the final one.

When is the final 10 percent holdback released after a multiplex build?

Two separate timelines apply. Anyone who worked on the project has 45 days to file a claim of lien, counted from the day the certificate of completion is issued. The holdback period itself expires 55 days after that same certificate, ten days longer than the lien filing window, so the owner can search title for liens filed on day 45 before releasing the money. Builders should not expect the final 10 percent on the day the building is finished, and not at day 45 either.

Why do construction lenders check for liens before releasing a draw?

A registered mortgage has priority over a lien for all funds advanced before the claim of lien is filed, but once a lien is registered, that priority picture changes. Because of this, construction lenders typically monitor lien filings before advancing draws, since paying out money after a lien is filed can weaken their security. For the builder, this means an unpaid subtrade who files a lien is not only an ethical problem but a financing problem that can hold up the next draw.

What are the typical stages of a BC construction loan draw schedule?

The typical sequence is a land advance to cover the property purchase, a lock-up draw at roughly 40 percent complete once the building can be closed up, a drywall draw at roughly 70 percent complete after plumbing, electrical, and mechanical systems are roughed in, and a final draw at 100 percent complete once the occupancy permit is received. Each stage is a milestone the lender verifies through inspection before releasing money.

How should I plan my cash flow around a multiplex construction loan?

Build a simple cash flow that lines up expenses with the draw milestones: know what you need to spend before lock-up, before drywall, and before completion, and know that each draw only lands after inspection confirms the stage is done. Add a cushion for the gap between spending and draws, keep the build on pace so draws come on time, and add the 55-day holdback delay on the final 10 percent to your planning rather than counting on that money the day the building finishes.

What happens if my multiplex build falls behind schedule?

Falling behind schedule means draws come later, since each draw is tied to a verified construction milestone rather than a calendar date. That means the builder carries more cost out of pocket for longer while waiting for the next draw. Keeping the build on pace affects cash flow throughout the project, not just the final completion date.

Free 12-page guide for Vancouver-area homeowners. Build, sell, hold, or partner — side-by-side comparison of the numbers, timeline, and risk on each path.

Verified phone required. We'll text you the link in 60 seconds.

David Babakaiff

David Babakaiff

Co-Founder, VanPlex | 25+ Years BC Construction

David Babakaiff is Co-Founder of VanPlex with 25+ years scaling BC construction. He led Alair Homes Vancouver to the 2024 HAVAN Award for Best Multiplex Unit in the GVRD. VanPlex’s PlexRank™ algorithm scores residential parcels across BC for multiplex conversion potential under Bill 44.

Want insights like this delivered weekly?

Join 2,500+ property owners getting ROI case studies, market data, and exclusive opportunities.

No spam. Unsubscribe anytime.