Construction financing paperwork and a calculator on a desk, illustrating the progress draw where a BC owner must retain the 10 percent builders lien holdback rather than rely on a no-lien clause
Legal & Compliance

That No-Lien Clause in Your Contract Is Void

7 min read

Section 42 of the BC Builders Lien Act voids any agreement purporting to waive the Act. The clause stops nobody from filing. The damage is what it persuades owners to skip: the 10% holdback that is the only thing creating a real fund.

builders-lien construction-contract legal bc section-42 holdback

A builder hands you a contract. Somewhere in the middle is a clause saying the contractor and its subcontractors waive their lien rights. It looks like protection. It is worth nothing.

Section 42 voids it

Section 42 of the BC Builders Lien Act makes void certain acts, agreements and assignments, and an agreement that purports to waive the operation of the Act is among them.

So the clause does not stop a subcontractor from registering a claim of lien against your title. It does not stop a supplier. It does not stop a worker.

The reason is structural. Most of the people who can file a lien on your project never signed your contract. A drywall sub engaged by your general contractor has no agreement with you at all. A clause in a document they were not party to was never going to bind them, and the Act closes the gap for the ones who did sign.

The failure this causes

The damage is rarely the clause itself. It is what the clause persuades an owner to skip.

An owner reads it, concludes lien risk is handled, and pays each draw in full without retaining the section 4 holdback. Months later a subcontractor who was never paid by the general contractor files against the title.

Now there is no fund. The 10% that was supposed to answer that claim went out with the draws. The owner can end up paying twice: once to the general who did not pass the money down, and again to clear the lien.

What actually works

Four things, none of which are a clause.

Retain the holdback. 10% of the greater of the value of work provided or the payment made, on every progress payment. This is the only measure that creates an actual fund, and section 42 means it cannot be contracted away.

Require a statutory declaration before each draw. A sworn statement from the general contractor that the trades paid to date have in fact been paid. It puts them on record and forces the question to be asked monthly rather than assumed.

Search title before significant payments. A search is cheap and converts an assumption into a fact.

Use joint cheques where the exposure is concentrated. A cheque payable to both the general and a specific subcontractor cannot be diverted on the way down. This works as a targeted tool on one or two large trades, not as a default across every contract.

Reading the clause as a signal

A contractor who leans on a no-lien clause during negotiation is telling you something about how they think about payment down the chain.

The clause is unenforceable, so it protects nobody. If it is being offered as a reason you do not need the holdback, that is the moment to be more careful about the holdback, not less.

See what your lot can build before you sign anything.

The full set of controls is in the contracts and prevention guide.

Frequently asked questions

Does a no-lien clause work in British Columbia?

No. Section 42 of the Builders Lien Act makes void any agreement that purports to waive the operation of the Act, so a no-lien clause does not prevent a subcontractor from registering a claim against your title. Owners who rely on such a clause instead of retaining the statutory holdback end up with no protection at all.

Why can a subcontractor file when they never signed my contract?

Because most people who can file a lien on your project have no agreement with you. A drywall subcontractor engaged by your general contractor never signed your contract, so a clause inside that document was never going to bind them. Section 42 then closes the gap for the parties who did sign it.

What is the real damage caused by relying on a no-lien clause?

The clause persuades owners to skip the holdback. An owner concludes lien risk is handled, pays each draw in full without retaining the section 4 holdback, and later faces a claim from a subcontractor the general never paid. The 10% that should have answered that claim already went out with the draws.

What is a statutory declaration in BC construction payments?

It is a sworn statement from the contractor confirming that subcontractors, workers and suppliers paid to date have in fact been paid. Requiring one before each progress draw puts the contractor on record and creates a monthly checkpoint where payment down the chain gets verified rather than assumed.

How much is the builders lien holdback in BC?

The holdback is 10% under section 4 of the Builders Lien Act, calculated on the greater of the value of work and material actually provided, or the amount paid on account of the contract price. If a trade performed $100,000 of work and you pay $60,000, the holdback is $10,000 rather than $6,000.

Are joint cheques a good idea on a multiplex build?

They work as a targeted tool where one or two subcontractors carry the largest exposure, because a cheque payable to both the general contractor and that subcontractor cannot be diverted on the way down. Applied across every trade they become unworkable and can interfere with the general contractor's own agreements.

Can a contractor be required to prove the trades were paid?

Yes, and it is standard practice before releasing a draw. A statutory declaration is the usual instrument. Section 10 of the Builders Lien Act also treats money received on account of the contract price as a trust fund for those the contractor engaged, which gives the request a statutory footing.

What is the single most effective step against builders liens?

Retaining the 10% holdback required by section 4 on every progress payment. It is the only measure that creates an actual fund to answer a claim from someone you have no contract with, and unlike a no-lien clause it cannot be contracted away because section 42 voids agreements purporting to waive the Act.

Free 12-page guide for Vancouver-area homeowners. Build, sell, hold, or partner — side-by-side comparison of the numbers, timeline, and risk on each path.

Verified phone required. We'll text you the link in 60 seconds.

David Babakaiff

David Babakaiff

Co-Founder, VanPlex | 25+ Years BC Construction

David Babakaiff is Co-Founder of VanPlex with 25+ years scaling BC construction. He led Alair Homes Vancouver to the 2024 HAVAN Award for Best Multiplex Unit in the GVRD. VanPlex’s PlexRank™ algorithm scores residential parcels across BC for multiplex conversion potential under Bill 44.

Want insights like this delivered weekly?

Join 2,500+ property owners getting ROI case studies, market data, and exclusive opportunities.

No spam. Unsubscribe anytime.