Daly City | Coastal zone and bluffs

Daly City, California Coastal Zone and Bluffs: The Local Coastal Program, the Resource Protection District, Geotechnical Reports, Coastal Permits and Grading

The western edge of Daly City is a line of sea cliffs with houses on the flat land above them. State law puts that strip in the coastal zone, where building needs a second review under the California Coastal Act. Daly City carries out that law through a Local Coastal Program approved in 1984 and through three chapters of its zoning code. The main one, the -RP Resource Protection combining district, keeps buildings 50 feet back from the bluff edge and asks for a geologist's report before most construction. This page explains where the zone is, what needs a permit, who decides, and the citywide rules on grading, slopes and fire hazard. The Daly City overview has the summary.

Daly City coastal rules in six facts

Where the Coastal Zone Is

The City's Coastal Element, which is also its Local Coastal Program or LCP, draws the area: "The Daly City coastal zone consists of all lands within the city limits" that "are west of Skyline Boulevard, as well as two areas which are east of" it. West of the boulevard the zone runs from the northern limits of Thornton State Beach south to the Mussel Rock headlands. The two eastern areas are the land bounded by the Olympic Club, John Daly Boulevard and Eastgate Drive, and a part of Westlake near Lake Merced Boulevard at the San Francisco line.

The City's ADU guide gives owners a short version: "Properties west of Skyline Boulevard and west of Eastgate Drive (north of John Daly Boulevard) are located within the Coastal Zone." The Element describes the ground. "Between these extends about 2.6 miles of beach which is mostly inaccessible" because of the bluffs, whose tops are "300 to over 650 feet in elevation and the slopes are exceedingly steep." In 1984 it counted "about 2288 housing units on the coastal" terrace above the beach. The Housing Element of 2024 says "Much of the area encompassed by the Coastal Zone in Daly City is developed with single-family detached homes built in the 1950s and 1960s as part of the Westlake neighborhood."

The Local Coastal Program of 1984

An LCP is a city's own plan and rules for its coastal zone. Once the California Coastal Commission certifies it, the city issues coastal permits in place of the state. The Element's adoption page records two dates: "November 14, 1983: City Council approved Local Coastal Plan for" submission, and "March 14, 1984: Approved by the California Coastal Commission." The copy on the City's General Plan page is a scan of the 1984 document.

  • House lots. The Element's summary of the R-1 land says "All of the parcels designated R1 are existing conforming uses," and that its policies protect them.
  • Little land left. "Buildout of developable land has almost been completed inside the coastal" zone, the Element said in 1984.
  • Hazards. "The entire 2+ mile stretch of sea cliffs in the coastal zone presents major" physical hazards, mainly erosion and landslides. Landsliding "caused removal of 12 homes along Westline Drive above Mussel Rock and four homes" on Lynvale Court.
  • The appeal area. Of the -RP district the Element says "This zone is also the effective appeals area." It adds that the residential land east of that zone falls under a categorical exclusion, an order that exempts a class of projects from coastal permits. The exclusion order itself was not read for this guide.
  • Today. The 2024 Housing Element says that since 1984 "new private development has been sporadic," that landslides "caused a number of single-family homes in the Coastal Zone to be removed," and that "there are presently no homes that are known to be threatened by landslide activity."

Zoning Districts in the Coastal Zone

District Land Main rule Code
R-1 with -RP Houses on the coastal terrace New structures and additions of ten percent or more need a use permit and a geotechnical report; 50-foot bluff setback DCMC 17.27
OS Open Space Parks, beaches, school grounds and land unsuited to building New structures and commercial uses need a use permit; no homes DCMC 17.23
OSR Open Space Residential Private land shown as open space on the General Plan Homes at up to two per gross acre with a use permit DCMC 17.25
C-1 in the coastal zone Small commercial sites Dwellings and commercial development need a use permit DCMC 17.18.010

Sources: Daly City Municipal Code 17.18.010, 17.23.050, 17.25.040, 17.27.030 and 17.27.050 (Supplement 38); Coastal Element, section II.

The three open space and resource chapters were adopted in 1981 and amended in 1983, as the LCP was being written. A fourth, Chapter 15.36, "Coastal Zone Conservation," is an empty heading in the building title; an editor's note says its one section was repealed in 2010. The code text read for this guide never uses the words "coastal development permit." The City uses that name in its fee schedule and staff reports for the use permit these chapters require.

The -RP Resource Protection District

A combining district adds rules to those of the main district of a lot. Section 17.27.010 says the -RP district exists "to ensure that the character and intensity of allowable development is compatible with, and does not create or contribute to adverse impacts on sensitive resources or geotechnically hazardous areas." Where the -RP rules and the underlying district differ, "the regulations of the -RP zone shall prevail."

  • What needs a use permit. Section 17.27.030: "New structures, including buildings, fences, walls and swimming pools," and "Additions to existing conforming structures which will result in an increase of ten percent or more in the internal floor area, the construction of an additional story, or cause further encroachment towards the edge of a bluff or other sensitive physical feature."
  • Bluff setback. Section 17.27.050: "No building or structure shall be placed closer than fifty feet from the edge of the bluff, the setback line to be determined by the city engineer."
  • No grading on the blufftop. "No grading or filling operations shall be permitted except for required drainage or erosion control."
  • View corridor. New structures must leave "a permanent vista corridor with an unobstructed width of at least five feet or fifteen percent of the lot width of each lot, whichever is greater." On a lot 50 feet wide that is 7.5 feet (VanPlex arithmetic: 15 percent of 50).
  • Steep faces. "No development shall be allowed on a bluff or other such surface with a slope of thirty degrees or greater and a vertical relief of ten feet or more, except an approved stairway, ramp or developed trail."
  • Underlying rules still apply. The yards, height and coverage of the main district apply too, along with any conditions of the use permit.

The Element's glossary defines the blufftop more widely than the 50-foot line. Bluff and cliff areas are "the base, face and top of all bluffs and cliffs of ten" feet or more in height, and the top extends inland to a line set by a 20-degree plane from the toe of the bluff or to 50 feet from "the edge of the cliff or bluff, whichever is greater."

The Geotechnical Report

A geotechnical report is a study of the soil, rock, water and slope of a site by a licensed professional. Section 17.27.040 requires one "prepared and signed by a licensed geologist" with every application in the -RP district. The same list applies in the OS and OSR districts. It must cover:

  • "Site topography" and "Soils and geologic composition."
  • "Past and possible future landslide and/or erosion conditions, both natural and artificially induced."
  • "Ground and surface water conditions."
  • "Stability of the site, potential impact of the proposed project, and any mitigation measures or potential alternatives necessary to insure structural integrity of the site and structures for the economic life of the project."
  • "Certification that the development will have no adverse effect on the site or adjacent areas, will not endanger life or property, and will not require protective structures at any time during the economic life of the project."

The application also needs added site plan details, among them "Existing topography and any proposed changes due to grading or filling operations" and the "Existing and proposed drainage pattern on the site and surrounding area," plus an "Environmental evaluation pursuant to CEQA," the state environmental review law. The last item on the list of report contents matters most on the coast. A protective structure is a seawall or similar work at the base of a bluff, and the Coastal Act policy the Element copies says new development may not "in any way require the construction of protective devices that would substantially alter natural landforms along bluffs and cliffs."

How a Coastal Permit Is Decided

Step What happens Source
Application Use permit materials plus topography, trees, roads, drainage, a geotechnical report by a licensed geologist and an environmental evaluation DCMC 17.27.040
Planning Commission Public hearing; notice also goes to the Coastal Commission; the Commission makes a recommendation DCMC 17.27.060
City Council Final determination, with findings that the project conforms to the local coastal plan DCMC 17.27.060 and 17.44.050
Appeal To the State Coastal Commission for projects in the appeal area DCMC 17.27.060; Public Resources Code 30603

Sources: Daly City Municipal Code 17.27.040, 17.27.060 and 17.44.050 (Supplement 38); Public Resources Code 30603.

  • Hearing and notice. Section 17.27.060: "A public hearing shall be held by the planning commission," with notice "to all persons who have filed request for notice and to the coastal commission." Then "The planning commission shall make a recommendation concerning the application for development to the city council for final determination."
  • Findings. Section 17.44.050 adds that "In the coastal zone, specific findings of conformance with access, recreation and other relevant policies of the local coastal plan shall be made."
  • Appeal to the state. Public Resources Code 30603 lets a City decision be appealed to the Coastal Commission for projects "between the sea and the first public road paralleling the sea" and for those "within 300 feet of the top of the seaward face of any coastal bluff."
  • Time. The Housing Element lists "Coastal Development Permit (coastal zone only)" at "8 to 10 weeks," decided by the City Council, with the note "May be appealed to Coastal Commission."
  • Fee. The FY 2027 Master Fee Schedule lists the Coastal Development Permit at $5,681 for "Minor" and $22,725 for "Major."
  • Variances. A variance in the coastal zone needs a third finding under Section 17.46.050: that it "is consistent with the policies, maps and public access component of the local coastal plan."
  • Zoning changes. Section 17.48.060: "All amendments concerning lands within the coastal zone, after approval by the city council, shall become effective only upon certification approval by the California Coastal Commission."

A 2025 Example: a Bedroom at 60 Roslyn Court

The City Council file of June 23, 2025 shows the process on a small project. The owner asked to remove a 246 square foot sunroom and build a 216 square foot bedroom in its place, behind a house in the Westlake Palisades neighborhood. The staff report says "The project is in the -Resource Protection (-RP) overlay zone and therefore requires a Coastal Development Permit," and explains that the overlay "essentially requires public hearings for most new construction and allows for appeals to the California Coastal Commission."

  • Two hearings. "On December 3, 2024, the Planning Commission voted 4-0" to recommend approval. The City Council adopted Resolution 25-104 on June 23, 2025, by unanimous roll call vote. That is more than six months between the two hearings.
  • Time horizon. Asked about the geotechnical review, "Staff answered that a structure such as this is evaluated for a 50-year time frame."
  • Geotechnical finding. The City received "a report from a California Licensed Civil Engineer concluding that the placement of the addition is feasible from a geotechnical engineering perspective," and made the report's recommendations conditions of approval.
  • Appeal. "Because the proposed development is located within 300 feet of the seaward face of a coastal bluff, the project may be appealed to the Coastal Commission."
  • Notice. Notice went by newspaper, by posting and by "first class mailing to property owners within 300 feet and occupants within 100 feet of the site."
  • Conditions. The applicant must file "a Declaration of Acceptance of all conditions" within thirty days of Council approval.

ADUs, SB 9 and Other Added Homes in the Coastal Zone

  • ADUs. The City's ADU guide says that in the coastal zone, ADUs inside or attached to the main house "are typically exempt from Coastal Development Permit (CDP) requirements," junior ADUs "are also exempt because they are located entirely within the walls of the primary dwelling," and "Detached ADUs are not exempt and a CDP may be required."
  • No hearing for an ADU coastal permit. Government Code 66329 keeps the Coastal Act in force for ADUs, "except that the local government shall" decide the coastal permit "within 60 days of receiving a completed application, and shall not be required to hold public hearings."
  • SB 9. Government Code 65852.21 says the two-unit law does not "supersede or in any way alter or lessen the effect or application of the California Coastal Act," again with no public hearing required for the coastal permit. The City's SB 9 forms also ask whether the parcel is in a high or very high fire hazard severity zone, an earthquake fault zone or a flood hazard area, and if so whether the project meets the required safety measures.
  • Commercial sites. In C-1, the code makes "dwellings or any commercial developments in the coastal zone" a use that needs a use permit.
  • Open space land. Chapter 17.23 allows no homes in the OS district. Rezoning OS land takes an extra step: if the Council chooses to seek to keep the land open, "all further proceedings for the reclassification of the property shall be halted for a minimum period of ninety days." The OSR district allows "Residential uses at a density not to exceed two units per gross acre."

See the ADUs and SB 9 page for the unit rules.

Grading and Slopes Across the City

Steep ground is found across the city. The Citywide Objective Design Standards say "Daly City is notable for its steep and varied topography," and the City's rules on earth moving apply on every lot.

  • Grading permit. Section 15.62.070: "No person may grade, fill, excavate, store or dispose of soil and earth materials or perform any other land-disturbing or land-filling activity which may cause erosion without first obtaining a city permit."
  • Small jobs. Section 15.62.080 exempts work that meets five tests at once, including "The site upon which land area is disturbed or filled is three thousand square feet or less," "Natural and finished slopes are less than ten percent" and "Volume of soil or earth materials stored is fifty cubic yards or less."
  • Building excavation. Section 15.62.090 exempts "An excavation below finished grade for basements and footings of a building, retaining wall or other structure authorized by a valid building permit," but not a cut left with "an unsupported height greater than five feet."
  • Reports. The City Engineer may require a soil engineering report and an engineering geology report, each "based on adequate and necessary test borings."
  • Decision time. The City Engineer "shall notify applicant of its decision on the permit within twenty working days."
  • Wet season. The code defines it as "the winter period generally between October 15th through April 15th." Work that continues in that season needs special permission "every five working days." The fee schedule lists a Wet Season Work Authorization at $667 per week.
  • Large jobs. "All grading in excess of five thousand cubic yards" is "engineered grading" under a civil engineer. Cut slopes "shall be no steeper than two horizontal to one vertical" unless an engineer specifies otherwise.
  • Fees. Grading of 1,000 cubic yards or less has a plan review base fee of $334 and a permit and inspection base fee of $653, and the grading security deposit is 25 percent of the grading cost.
  • Zoning rule. Section 17.40.010 requires a use permit to remove or import "in excess of five hundred cubic yards" of natural materials, with exceptions for foundations, basements and approved subdivisions.
  • Maps. Section 16.20.120 requires unstable land to be marked on a final map, with a signed certificate naming the engineering geologist or soils engineer.

The design standards add rules for hillside houses. Tall support structures under a house, "of a height of 10 feet or greater," must be enclosed with a finished surface when they are wood-framed, and visible retaining walls may not be "Exposed concrete block walls" with no plaster finish. On the four-lot Crocker Avenue project of 2026, on a 25 percent slope, the staff report describes "deep foundations (piers/piles), retaining walls, and terracing for stability" and a geotechnical study reviewed by outside consultants.

Fire Hazard

Ordinance No. 1482, adopted June 23, 2025, designated the fire hazard severity zones "as recommended by the State Fire Marshal" and found that the official map, dated February 25, 2025, "confirms that all areas within the City of Daly City have been designated" Moderate. The City also adopted the 2025 California Wildland-Urban Interface Code, which under Section 15.33.010 controls "for all areas designated as wildland-urban interface fire areas." Section 15.32.260 sets up a vegetation management program for the Southern Hills, aimed at "the accumulation of gorse plants near residential areas." On Crocker Avenue the applicant told the Planning Commission that the Fire Department asked for large trees to be removed from the site.

Where the Code and City Documents Differ

  • The name of the permit. Title 17 requires a use permit in the -RP, OS and OSR districts. The fee schedule, the Housing Element and staff reports call it a Coastal Development Permit.
  • How long it takes. The Housing Element gives 8 to 10 weeks. The Roslyn Court permit went to the Planning Commission in December 2024 and to the City Council in June 2025.
  • Fire hazard section. Ordinance No. 1482 added a Section 15.32.280 in June 2025. Ordinance No. 1484 replaced Chapter 15.32 in November 2025, and the Supplement 38 text of that chapter ends at Section 15.32.260.
  • Ordinance title. The Council agenda and minutes of June 23, 2025 describe Ordinance No. 1482 as adding a chapter "of Title 5." The ordinance itself says Title 15.
  • The 1980s districts list. Section 17.06.010, which names the City's zoning districts, does not list OS, OSR or -RP.
  • District list in the staff report. The Roslyn Court findings say the R-1 district "requires a Coastal Development Permit." The requirement comes from the -RP combining district.
  • Who signs the report. Section 17.27.040 asks for a geotechnical report "prepared and signed by a licensed geologist." The Roslyn Court findings rely on a report from "a California Licensed Civil Engineer."

Limits of This Page

The Coastal Element is a scanned document of 89 pages, read by optical character recognition; quotes here are short and were checked against the recognized text. Its maps, including the map of the -RP district and the appeal area, could not be read, so this page cannot say whether a given lot is inside either. The categorical exclusion order of 1980, the Coastal Commission's certification record, any LCP amendment after 1984, the fire hazard map and the federal flood maps were not read. The City's coastal permit application form was not found. Ask the Planning Division, 650-991-8033, whether a lot is in the coastal zone, the -RP district and the appeal area, and ask the Engineering Division, 650-991-8064, about grading permits.

Best For

  • ✓ ADUs built inside or attached to an existing house in the coastal zone, which the City guide says are typically exempt from a coastal permit.
  • ✓ Interior work and additions under ten percent of floor area that add no story and move no closer to the bluff.
  • ✓ Sites east of the -RP district, after the Planning Division confirms the lot is outside it.

Usually Fails When

  • ✕ A new building or detached ADU is planned within 50 feet of the bluff edge.
  • ✕ A project budget leaves out the geotechnical report and the two public hearings.
  • ✕ A rezoning for more homes in the coastal zone is planned with no time for Coastal Commission certification.

What To Verify Before Spending Money

  • → Whether the lot is in the coastal zone, the -RP district and the Coastal Commission appeal area.
  • → Whether the City treats the project as a minor or a major Coastal Development Permit.
  • → The bluff setback line as set by the City Engineer.

Where to Go Next

Related on VanPlex: the Daly City overview, the parking, setbacks and height page and the property tax, fire zones and insurance page.

Frequently Asked Questions

Where is the coastal zone in Daly City? +
The Daly City Coastal Element says the coastal zone "consists of all lands within the city limits" west of Skyline Boulevard, plus two areas east of it. The City ADU guide describes the same area for owners: properties west of Skyline Boulevard and west of Eastgate Drive, north of John Daly Boulevard. The Planning Division confirms the status of a given lot.
How far from the bluff edge must a building be in Daly City? +
Fifty feet. Section 17.27.050 of the Daly City code says that on a blufftop in the -RP Resource Protection district "No building or structure shall be placed closer than fifty feet from the edge of the bluff, the setback line to be determined by the city engineer." Grading and filling there are barred except for drainage or erosion control.
Do I need a coastal permit to add a room to a Daly City house near the bluffs? +
In the -RP district of Daly City, an addition needs a use permit, handled as a Coastal Development Permit, when it adds ten percent or more floor area, adds a story or moves closer to the bluff edge. In June 2025 the City Council approved one for a 216 square foot bedroom at 60 Roslyn Court after a geotechnical report and two hearings.
Who decides a coastal permit in Daly City? +
The Daly City Council. Section 17.27.060 requires a public hearing by the Planning Commission, which then makes "a recommendation concerning the application for development to the city council for final determination." Notice goes to the Coastal Commission, and a Council decision in the appeal area may be appealed to that state agency.
What does a Daly City Coastal Development Permit cost? +
The Daly City Master Fee Schedule for fiscal year 2027 lists a Coastal Development Permit at $5,681 for a minor project and $22,725 for a major one. The schedule does not define the two classes, so ask the Planning Division which applies. The geotechnical report, environmental review and building permit fees are separate costs.
What must a geotechnical report cover in the Daly City coastal zone? +
Section 17.27.040 of the Daly City code lists six items, signed by a licensed geologist: topography, soils and geology, past and possible landslides and erosion, ground and surface water, site stability, and a certification that the project "will not require protective structures at any time during the economic life of the project." City staff said in 2025 that a house addition is evaluated over 50 years.
Can I build on a steep slope in the Daly City coastal zone? +
Section 17.27.050 of the Daly City code bars development in the -RP district "on a bluff or other such surface with a slope of thirty degrees or greater and a vertical relief of ten feet or more, except an approved stairway, ramp or developed trail." Flatter sites still need a use permit and a geotechnical report.
Is Daly City in a fire hazard severity zone? +
Daly City Ordinance No. 1482, adopted June 23, 2025, designated the fire hazard severity zones that the State Fire Marshal recommended. It finds that the official map "confirms that all areas within the City of Daly City have been designated Moderate." The current Municode text of the fire chapter does not show the section that ordinance added.
When do I need a grading permit in Daly City? +
Under Chapter 15.62 of the Daly City code, grading needs a City permit unless the site disturbed is 3,000 square feet or less, slopes are under ten percent, stored soil is 50 cubic yards or less and no drainage way is blocked. Excavation for a basement or footing under a valid building permit is exempt. The wet season runs from October 15 to April 15.
Can the Daly City Council change zoning in the coastal zone by itself? +
No. Section 17.48.060 of the Daly City code says amendments concerning land in the coastal zone, after City Council approval, "shall become effective only upon certification approval by the California Coastal Commission." That adds a state step to any rezoning or zoning text change that would allow more homes west of Skyline Boulevard.

Official sources (checked October 2026)

City of Daly City, General Plan Coastal Element (Local Coastal Program), March 1984 (PDF)
https://www.dalycity.org/DocumentCenter/View/898/Coastal-Element-PDF
City of Daly City, General Plan page
https://www.dalycity.org/363/General-Plan
Daly City Municipal Code, Chapter 17.27, -RP Resource Protection Combining District
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.27-RREPRCODI
Daly City Municipal Code, Section 17.27.010, -RP general provisions
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.27-RREPRCODI_17.27.010GEPR
Daly City Municipal Code, Section 17.27.030, -RP conditional uses
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.27-RREPRCODI_17.27.030COUS
Daly City Municipal Code, Section 17.27.040, -RP application requirements
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.27-RREPRCODI_17.27.040APRE
Daly City Municipal Code, Section 17.27.050, -RP development regulations
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.27-RREPRCODI_17.27.050DERE
Daly City Municipal Code, Section 17.27.060, -RP hearing and notice
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.27-RREPRCODI_17.27.060HENORE
Daly City Municipal Code, Chapter 17.23, OS Open Space District
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.23OSOPSPDI
Daly City Municipal Code, Section 17.23.050, OS conditional uses
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.23OSOPSPDI_17.23.050COUS
Daly City Municipal Code, Section 17.25.040, OSR conditional uses
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.25OSOPSPREDI_17.25.040COUS
Daly City Municipal Code, Section 17.18.010, C-1 table of uses
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.18LICODI_17.18.010TAUS
Daly City Municipal Code, Section 17.40.010, removal or importation of natural materials
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.40MIUSRE_17.40.010REIMNAMA
Daly City Municipal Code, Section 17.44.050, use permit findings
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.44USPE_17.44.050FI
Daly City Municipal Code, Section 17.46.050, variance findings
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.46VA_17.46.050FIPLCO
Daly City Municipal Code, Section 17.48.060, amendments in the coastal zone
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.48AM_17.48.060ACCO
Daly City Municipal Code, Chapter 15.36, Coastal Zone Conservation (repealed 2010)
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT15BUCO_CH15.36COZOCO
Daly City Municipal Code, Section 15.62.070, grading permit
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT15BUCO_CH15.62GRERSECO_15.62.070PE
Daly City Municipal Code, Section 15.62.080, grading exemptions
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT15BUCO_CH15.62GRERSECO_15.62.080GEEX
Daly City Municipal Code, Section 15.33.010, Wildland-Urban Interface Code
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT15BUCO_CH15.33CAWIBAINCO_15.33.010CAWIBAINCODOHEFI
Daly City Municipal Code, Section 15.32.260, vegetation management in the Southern Hills
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT15BUCO_CH15.32FICO_15.32.260VEMAPRSOHIAR
Daly City Municipal Code, Section 16.20.120, flood and unstable areas on maps
https://library.municode.com/ca/daly_city/codes/code_of_ordinances?nodeId=TIT16SU_CH16.20FIMA_16.20.120DEFLARUNAR
Daly City Ordinance No. 1482, fire hazard severity zones, adopted June 23, 2025 (Municode ordinance bank)
https://library.municode.com/ca/daly_city/ordinances/code_of_ordinances?nodeId=1366359
City of Daly City, City Council meeting of June 23, 2025, agenda files (CivicClerk portal)
https://dalycityca.portal.civicclerk.com/event/2125/files
City of Daly City, City Council meeting of February 23, 2026, agenda files (CivicClerk portal)
https://dalycityca.portal.civicclerk.com/event/2176/files
City of Daly City, Accessory Dwelling Unit Guide (PDF)
https://www.dalycity.org/DocumentCenter/View/12311/Accessory-Dwelling-Unit-Guide
City of Daly City, Citywide Objective Design Standards, September 2024 (PDF)
https://www.dalycity.org/DocumentCenter/View/11195/Citywide-Objective-Design-Standards
City of Daly City, Master Fee Schedule, FY 2027 (PDF)
https://www.dalycity.org/DocumentCenter/View/13336/FY-2027-Master-Fee-Schedule-Final-with-Police-Fines-PDF
City of Daly City, 2023-2031 Housing Element, adopted November 12, 2024 (PDF)
https://www.dalycity.org/DocumentCenter/View/11553/Daly-City-2023-2031-Housing-Element---Adopted-111224
City of Daly City, Engineering permits, fees and insurance requirements page
https://www.dalycity.org/508/Permits-Fees-Insurance-Requirements
Public Resources Code 30603 (appeals to the Coastal Commission)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PRC&sectionNum=30603
Government Code 66329 (ADUs and the Coastal Act)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66329
Government Code 65852.21 (SB 9 two-unit projects)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=65852.21
General information, not legal advice. California housing law changes every year, and each city adds its own rules on top of state law. Confirm current requirements with the city or county planning department, and with a California-licensed attorney or architect, before you buy land or file plans.

Planning a multiplex in Daly City?

VanPlex builds multiplexes in British Columbia, Canada. For a lot in Daly City, our team makes a custom proforma by hand and emails it to you in 24 to 48 hours.

Get a proforma for your address