An accessory dwelling unit (ADU) is a second, complete home on a lot that already has, or will have, a main home. A junior ADU is a unit of up to 500 square feet inside a single-family home. An SB 9 two-unit project puts two main homes on one house lot under state law. Lancaster sets its rules for all three in Chapter 17.41 of the Municipal Code, rewritten by Ordinance No. 1106 on October 10, 2023. Several City rules are stricter than state law and yield to it; this page names each one. See the Lancaster overview for the whole guide.

Lancaster ADUs and SB 9 in six facts

  • An ADU or junior ADU that meets the City standards needs only a ministerial building permit, decided within 60 days. Source: LMC 17.41.014
  • An attached ADU may be 850 square feet with one bedroom or less and 1,200 square feet with two or more. Source: LMC 17.41.016
  • A detached ADU may be 18 feet tall, or 20 feet to match the roof pitch of the house, with 4 foot side and rear setbacks. Source: LMC 17.41.016
  • Each new home in a Lancaster SB 9 two-unit project must be over 500 and at most 800 square feet, one story and 22 feet tall. Source: LMC 17.41.058
  • Only an individual property owner may apply for an SB 9 two-unit project. Source: LMC 17.41.054
  • State law bars an owner-occupancy rule for ADUs, so the City's owner rule in Section 17.41.018 yields to Government Code 66315. Source: Gov. Code 66315

ADU Approval

ADUs and junior ADUs are a P use, permitted, in every residential zone and in the MU-N, MU-C and MU-E mixed use zones. Section 17.41.014 says one that "complies with all of the applicable development standards of this article requires only a ministerial building permit." Ministerial means staff check the plans against fixed rules, with no hearing and no judgment calls. The City "shall approve or deny an application to create an ADU or JADU within 60 days from the date that the city receives a completed application," or the application "is deemed approved." A denial must come with a list of what is missing and how to fix it, within the same 60 days.

Two timing rules come from state law. When the ADU is filed together with a new house or apartment building, the City may wait to act on the ADU until it acts on the main building. And Government Code 66317 requires the City to say whether an ADU application is complete "not later than 15 business days after the permitting agency received the application," a step the City code does not repeat. A demolition permit for a detached garage that an ADU replaces is reviewed with the ADU and issued at the same time.

ADU Size, Height and Setbacks

Type Size Height Setbacks
Interior ADU (converted space) Existing space, plus up to 150 sq ft for entry and exit Existing building Enough for fire and safety
Attached ADU 850 sq ft (studio or 1 bedroom), 1,200 sq ft (2 or more bedrooms) 25 ft and 2 stories Front 25 ft, side 4 ft, rear 4 ft
Detached ADU, house lot No maximum printed in Section 17.41.016.A.4 18 ft, or 20 ft to match the roof pitch Front 25 ft, side 4 ft, rear 4 ft
Detached ADU, apartment lot (up to 2) 850 sq ft (studio or 1 bedroom), 1,200 sq ft (2 or more bedrooms) 18 ft, or 20 ft to match the roof pitch Front 25 ft, side 4 ft, rear 4 ft
Junior ADU Up to 500 sq ft inside the house Inside the house Inside the house

Sources: Lancaster Municipal Code 17.41.012 and 17.41.016, Supplement 10 - 2025.

A setback is the open distance a building must keep from a property line. Lancaster uses the same three numbers for every new ADU: "Front-yard setback: 25 feet," and 4 feet from the side and rear lines. An interior ADU, made from space inside the house or an existing accessory building, keeps only the side and rear distances "sufficient for fire and safety." Lot coverage, the share of the lot under roofs, may not pass 40 percent in RR-2.5, RR-1, SRR, R-15,000 and R-10,000, 50 percent in R-7,000, MDR and HDR, and 60 percent in the mixed use zones. For attached ADUs, the code adds that the front setback and lot coverage may not force the ADU below 850 square feet.

On a lot with apartments, Section 17.41.016.B allows interior ADUs in unused space such as storage rooms, garages and attics, up to 25 percent of the number of homes in the building and at least one, plus "No more than 2 detached ADUs per lot." Every ADU must be at least the size of an efficiency unit as defined in Section 17958.1 of the Health and Safety Code. A garage that serves an existing home may be converted into an ADU or junior ADU under Section 17.08.220.

Parking, Rentals and Other ADU Rules

  • Parking. "One off-street parking space is required for each ADU," 10 by 20 feet, in a garage, carport or driveway, and tandem parking (one car behind another) is allowed. None is needed for an interior ADU, an ADU "within one-half mile walking distance of public transit," or the small ADUs state law exempts.
  • Garage replaced by an ADU. Lost garage spaces do not have to be replaced. When a junior ADU is made from an attached garage, the lost spaces "shall be replaced in kind."
  • Rentals. "No ADU or JADU may be rented for a term that is shorter than 30 days."
  • No separate sale. An ADU may be rented, but may not be sold apart from the lot and main home, except under Government Code Section 65852.26. A deed restriction saying so is recorded before the building permit.
  • Fire sprinklers. Required in the ADU only if the main home needs them, and building an ADU "does not trigger a requirement for fire sprinklers to be installed in the existing primary dwelling."
  • Septic. An ADU on a septic system needs a percolation test (a soil drainage test) from the last 5 years, or 10 years if recertified.
  • Old problems on the lot. The City "will not deny an ADU or JADU application due to a nonconforming zoning condition, building code violation, or unpermitted structure" that is no threat to health and safety. An unpermitted ADU built before January 1, 2018 can be legalized, with health and safety exceptions.

Where State ADU Law Controls

A city ADU rule that is stricter than state ADU law has no effect to that extent. These Lancaster rules are in that group:

  • Number of ADUs. Section 17.41.016.A.1.a allows "No more than one JADU and one ADU" per parcel. Government Code 66323 requires approval of "any combination" of a converted ADU and junior ADU plus one "detached, new construction" ADU of up to 800 square feet. The statute controls.
  • Owner occupancy. Section 17.41.018.E requires an owner to live on site. Government Code 66315 bars any added standard for an ADU, "including an owner-occupant requirement." Government Code 66333 allows the rule only for a junior ADU that shares a bathroom with the house.
  • Front setback for a detached ADU. The 25 foot front setback comes with an 850 square foot guarantee only for attached ADUs. Government Code 66321 bars front setbacks and lot coverage limits that do not permit an ADU "with at least 800 square feet of interior livable space and with four-foot side and rear yard setbacks." The statute protects a detached ADU too.
  • Parking. Government Code 66322 also bars ADU parking within a historic district, where permit parking is not offered to the ADU, "When there is a car share vehicle located within one block," and when the ADU is filed with a new home. The City list is shorter; the statute controls.
  • Impact fees. Government Code 66311.5 bars impact fees on an ADU of 750 square feet or less and a junior ADU of 500 square feet or less. Lancaster's impact fee chapter has no ADU rule, so the statute sets the limit.
  • Old statute numbers. Section 17.41.010 cites Government Code 65852.2, 65852.22 and 65852.23. The first two are no longer in the Legislature's database of sections in force, and the state ADU rules now sit in Sections 66314 and following. Section 17.41.012 also points to "Section 21.78.050.D.1," a section that does not exist in Lancaster's code.

SB 9 Two-Unit Projects in Lancaster

Rule Lancaster standard
Zones RR-2.5, RR-1, SRR, R-15,000, R-10,000 and R-7,000
Units per lot 2: a duplex, two houses, a house and an ADU, or a house and a junior ADU
Size of each new home More than 500 and up to 800 sq ft; no basements
Total floor area on the lot 1,700 sq ft for both units
Height One story and 22 ft to the peak; no rooftop deck
Lot coverage 50 percent
Setbacks Front 25 ft; side and rear 4 ft; none for an existing building
Parking 1 space per home, none within one-half mile walking distance of qualifying transit or one block of a car share vehicle
Planted screen One 15-gallon plant per 5 ft of wall, one 24-inch box per 10 ft, or a 6 ft solid fence

Source: Lancaster Municipal Code 17.41.058, Supplement 10 - 2025.

Lancaster's two-unit rules are in Chapter 17.41, Article III. The applicant must be an "individual property owner," which leaves out companies but includes a community land trust and a qualified nonprofit, and must bring a certificate of compliance showing the lot was legally created. The Community Development Director decides "ministerially by the community development director without discretionary review," and the approval takes effect only once the deed restrictions and easements are recorded. Government Code 65852.21 adds the deadline the City code leaves out: a decision "within 60 days from the date the local agency receives a completed application," or the project is deemed approved.

The size limits come first. "The total floor area of each primary dwelling that is developed under this section must be less than or equal to 800 square feet and more than 500 square feet," the two units together may not pass 1,700 square feet, and "No new primary dwelling unit shall exceed a single story." An existing house over 800 square feet may stay but may not grow. State law allows such limits because it only guarantees that each unit can reach 800 square feet; the City code says any standard, other than side and rear setbacks, that would stop two homes of 800 square feet "shall be waived." By VanPlex arithmetic, 50 percent coverage on a 7,000 square foot lot is 3,500 square feet, so on most R-7,000 lots the 1,700 square foot total is the limit that binds.

Other conditions apply. Homes must not replace rent-restricted or rent-controlled housing, housing withdrawn under the Ellis Act in the last 15 years, or housing "occupied by a tenant in the last 3 years," and no more than 25 percent of the exterior walls may be torn down unless no tenant has lived there in 3 years. Each home needs its own utility connection and underground service. Rentals must be 30 days or longer, the lot may hold residential uses only, and the owner records a deed restriction that bars separate sale of a home and any further building beyond the two units. The objective design standards in Article IV apply, with Article III winning a conflict.

Duplex by Director's Review: the Other Route

SB 9 is one of two ways to get two main homes on a Lancaster house lot. The residential uses matrix in Section 17.08.050 lists a duplex as a director's review use in the RR, R, MDR and HDR zones. A duplex built that way follows the zone's ordinary height, lot coverage and setbacks (in the R zones, 35 feet and 40 to 50 percent coverage), with a corner duplex lot needing 10,000 square feet and 100 feet of width. Each duplex home also needs 2 garage spaces under Section 17.08.100, unless the lot is within one-half mile of a major transit stop. The SB 9 route caps each new home at 800 square feet and one story but asks for only 1 parking space per home. The parking, setbacks and height page compares the two sets of standards.

Best For

  • ✓ House lots with room for a detached ADU behind a 25 foot front setback.
  • ✓ Garage conversions, which need no replacement parking for an ADU.
  • ✓ Owners who want two small one-story homes under SB 9 on an R-7,000 lot.

Usually Fails When

  • ✕ The SB 9 plan needs homes over 800 square feet or a second story.
  • ✕ The applicant for an SB 9 project is a company or partnership.
  • ✕ A tenant has lived in the home in the last 3 years and the plan alters it.

What To Verify Before Spending Money

  • → Whether the lot is within one-half mile walking distance of public transit for parking.
  • → Whether the lot is on a septic system and needs a percolation test.
  • → How the City applies Government Code 66323 to a third unit on a house lot.

Where to Go Next

Related on VanPlex: the Lancaster overview, the California ADU law page and the SB 9 page.

Frequently Asked Questions

How big can an ADU be in Lancaster? +
A Lancaster attached ADU may be up to 850 square feet with a studio or one bedroom, and up to 1,200 square feet with two or more bedrooms, under Section 17.41.016. A detached ADU on a house lot has no maximum floor area printed in the code, and is limited instead by height, setbacks and lot coverage. A junior ADU is up to 500 square feet inside the house.
How tall can a detached ADU be in Lancaster? +
A Lancaster detached ADU may be 18 feet tall under Section 17.41.016, plus up to 2 more feet, for 20 feet, when needed to match the roof pitch of the main house. An attached ADU may be 25 feet tall and no more than 2 stories. These limits meet or exceed the 16 foot floor that Government Code 66321 guarantees for a detached ADU.
Does Lancaster require parking for an ADU? +
Lancaster Section 17.41.018 requires one off-street space of 10 by 20 feet for each ADU, with exceptions for a converted ADU, an ADU within one-half mile walking distance of public transit, and the small ADUs state law exempts. Government Code 66322 adds more exceptions, such as a car share vehicle within one block, and the statute controls where it is broader.
Must I live on the property to build an ADU in Lancaster? +
Not for an ADU. Lancaster Section 17.41.018.E still prints an owner-occupancy rule, but Government Code 66315 says no standard beyond Section 66314 may be imposed on an ADU, "including an owner-occupant requirement." For a junior ADU, Government Code 66333 lets a city require the owner to live on site when the junior ADU shares a bathroom with the house.
How many ADUs can I build on a Lancaster house lot? +
Lancaster Section 17.41.016.A.1.a says no more than one junior ADU and one ADU per legal parcel. Government Code 66323 requires a city to approve, in any combination, a converted ADU and a junior ADU plus one new detached ADU of up to 800 square feet with 4 foot side and rear setbacks. Where the City limit is lower, the statute controls.
Can I sell an ADU separately in Lancaster? +
Generally no. Lancaster Section 17.41.018 says an ADU or junior ADU may be rented, but may not be sold or conveyed separately from the lot and main home, except as Government Code Section 65852.26 allows. Before a building permit issues, the owner records a deed restriction that keeps the unit with the lot and limits it to its approved size. Rentals must be 30 days or longer.
How large can an SB 9 home be in Lancaster? +
Each new home built under Lancaster's SB 9 two-unit rules must be more than 500 and no more than 800 square feet, under Section 17.41.058.F.3, with a combined limit of 1,700 square feet for both units on the lot. Each new home must be one story and no more than 22 feet tall, and basements and rooftop decks are not permitted.
Do I have to live in one of the homes in a Lancaster SB 9 project? +
Lancaster Section 17.41.058.J.3 requires the owners of a two-unit project lot to live in one of the homes as their principal residence, and after an urban lot split to occupy one unit for at least 3 years. For a lot split, Government Code 66411.7 allows only an affidavit of intent to live there for 3 years and bars additional owner-occupancy standards.
Who approves an SB 9 two-unit project in Lancaster? +
The Lancaster Community Development Director approves or denies a two-unit project ministerially, with no discretionary review, under Section 17.41.056. The approval does not take effect until the required deed restrictions and easements are recorded. Government Code 65852.21 requires a decision within 60 days of a complete application, or the project is deemed approved; the City code sets no deadline of its own.
Must I tell the neighbors before building a Lancaster SB 9 project? +
Yes. Lancaster Section 17.41.058.K requires written notice to the owners of every adjacent residential lot at least 30 business days before construction starts. The notice gives the start and end dates, work hours, and contact details for the project manager and the building department. The code says the notice is for information only and gives neighbors no right to comment.

Official sources (checked October 2026)

Lancaster Municipal Code, Section 17.41.012, ADU and JADU definitions (Supplement 10 - 2025)
https://library.municode.com/ca/lancaster/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.41ADREUSRE_ARTIACDWUNADJUACDWUNJARE_17.41.012DEAPADJARE
Lancaster Municipal Code, Section 17.41.014, ADU and JADU approvals
https://library.municode.com/ca/lancaster/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.41ADREUSRE_ARTIACDWUNADJUACDWUNJARE_17.41.014ADJAAP
Lancaster Municipal Code, Section 17.41.016, ADU and JADU development standards
https://library.municode.com/ca/lancaster/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.41ADREUSRE_ARTIACDWUNADJUACDWUNJARE_17.41.016ADJADEST
Lancaster Municipal Code, Section 17.41.018, ADU and JADU requirements
https://library.municode.com/ca/lancaster/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.41ADREUSRE_ARTIACDWUNADJUACDWUNJARE_17.41.018ADJARE
Lancaster Municipal Code, Section 17.41.020, nonconforming conditions and unpermitted ADUs
https://library.municode.com/ca/lancaster/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.41ADREUSRE_ARTIACDWUNADJUACDWUNJARE_17.41.020ADJANOZOCOCOBUCOVIUNST
Lancaster Municipal Code, Section 17.08.220, garage conversions
https://library.municode.com/ca/lancaster/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.08REZO_ARTIVSTSPLAUS_17.08.220GACO
Lancaster Municipal Code, Section 17.41.054, two-unit project applications
https://library.municode.com/ca/lancaster/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.41ADREUSRE_ARTIIITITPR_17.41.054AP
Lancaster Municipal Code, Section 17.41.056, two-unit project approval
https://library.municode.com/ca/lancaster/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.41ADREUSRE_ARTIIITITPR_17.41.056AP
Lancaster Municipal Code, Section 17.41.058, two-unit project requirements
https://library.municode.com/ca/lancaster/codes/code_of_ordinances?nodeId=TIT17ZO_CH17.41ADREUSRE_ARTIIITITPR_17.41.058RE
Government Code 65852.21 (SB 9 two-unit projects)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=65852.21
Government Code 66311.5 (ADU fees)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66311.5
Government Code 66315 (no added ADU standards, no owner occupancy)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66315
Government Code 66317 (ADU application review)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66317
Government Code 66321 (ADU size, height and setbacks)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66321
Government Code 66322 (ADU parking)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66322
Government Code 66323 (ADUs a city must approve)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66323
Government Code 66333 (junior ADUs)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66333
General information, not legal advice. California housing law changes every year, and each city adds its own rules on top of state law. Confirm current requirements with the city or county planning department, and with a California-licensed attorney or architect, before you buy land or file plans.

Planning a multiplex in Lancaster?

VanPlex builds multiplexes in British Columbia, Canada. For a lot in Lancaster, our team makes a custom proforma by hand and emails it to you in 24 to 48 hours.

Get a proforma for your address