Written by David Babakaiff · Co-Founder, VanPlex | 25+ Years BC Construction Last reviewed: October 2026

Vallejo | Permits and Fees

Vallejo Permits and Fees: Review Authorities, Appeals, Planning Fees and Impact Fees

A Vallejo housing project passes through three kinds of approval. Planning approvals under Part VI of the Zoning Code decide whether the project fits the zoning. Subdivision maps under Title 15 create lots. Building permits approve the construction itself. Each step has a decision maker, a notice rule, an appeal period and a fee. The City Council sets the fees by resolution in a Master Fee Schedule, and the code adds per-home charges called impact fees, which pay for roads, parks and other public facilities that new homes use. This page lists them from the FY 2026-2027 schedule. The Vallejo overview has the summary.

Vallejo permits and fees in six facts

Who Decides What

Approval Decided by Appeal to
Zoning compliance review Director Planning Commission
Minor use permit Director Planning Commission
Major use permit Planning Commission City Council
Variance Planning Commission City Council
Development review, Downtown/Waterfront Minor: Director; major: Design Review Board City Council
Development review, other areas Minor: Director; major: Planning Commission Planning Commission (minor), City Council (major)
Certificate of appropriateness Minor: Director; major: AHLC AHLC (minor), City Council (major)
Rezoning, specific plan, Planned Development City Council, after a Planning Commission recommendation None

Source: Vallejo Municipal Code Section 16.601.07, Table 16.601-A. AHLC is the Architectural Heritage and Landmarks Commission.

Under the table's note, "Director Decisions: No Public Hearing Required; PC, DRB, AHLC, CC Decisions: Public Hearing is Required," and "All new construction shall be subject to Development Review pursuant to Chapter 16.605." The Director here is the Planning and Development Services Director. For housing, Note 1 to the use table sets the level by project size: 2 to 10 homes are a Director decision, 11 to 49 homes a Director decision with a Design Review Board recommendation, and 50 or more a Planning Commission decision after a Board recommendation.

Zoning compliance review under Chapter 16.603 is the staff check for uses "allowed as a matter of right." If the plans conform, "a zoning compliance certificate will be issued"; if not, the applicant is told how to fix them. No public notice is needed unless the Director decides otherwise. Its fee is $123 over the counter and $420 when it needs a full plan check.

Development review under Chapter 16.605 is required for "all permits for new construction, reconstruction, rehabilitation alteration, or other improvements to the exterior of a structure." The chapter lists 13 exemptions. They include ADUs that comply with state standards, residential additions under 500 square feet and 14 feet tall that add no story (one every 24 months), and accessory structures under 500 square feet and 14 feet.

Notice, Effective Dates and Appeals

  • Mailed notice. Under Section 16.602.08, notice goes out at least 14 calendar days ahead for projects exempt from CEQA, the state environmental review law, and 21 days ahead for projects subject to it. It reaches owners within 300 feet for a Director action and 500 feet for a hearing, or 1,000 feet for "a large-scale, complex, or controversial project." The Vallejo City Unified School District and the agencies that will serve the project are notified too.
  • Effective date. A discretionary decision "shall become effective after the expiration of ten calendar days following the date of action, unless an appeal is filed," and no building permit is issued "until the 11th day."
  • Appeals. Any person aggrieved may appeal "within ten calendar days of the date of the action," or seven days for a temporary use permit. An appeal of a ministerial decision must rest on facts showing whether the project meets specific standards. Appealing one permit for a project automatically appeals all permits granted with it.
  • Appeal fees. $2,733 to a Commission or Board and $905 to the City Council, each "plus noticing fee," in the FY 2026-2027 schedule.

How Long Approvals Last

Section 16.602.12 sets the life of a planning approval when the decision does not set one. Permits for affordable housing or mixed-use projects where housing is at least 75 percent of the floor area, and that have public funding or meet set affordability levels, last three years from the effective date. "All Other Permits" last two years. For new construction, issuing the building permit counts as using the approval, but the approval still lapses if the building permit expires.

The Director may grant a first one-year extension and "a further extension of an additional one year," "for a total of two twelve-month extensions per entitlement," if the written request and fee arrive at least 15 calendar days before the permit expires. Subdivision maps run on their own clock: 36 months for a tentative map under Section 15.08.110, with Planning Commission extensions of up to 36 months more, as the lot size and subdivisions page explains.

State Deadlines for ADUs and SB 9

Two kinds of housing follow state deadlines. Under the ADU chapter in force since October 8, 2026, the Building Division has 15 business days to say whether an ADU application is complete and must approve or deny a complete one within 60 days, or "the application shall be deemed approved." For SB 9 two-unit projects, Government Code 65852.21 sets the same rule: a complete application "shall be considered and approved or denied within 60 days," or it is deemed approved. Vallejo's code has no SB 9 section, so the statute's process applies directly.

Planning Fees

Application FY 2026-2027 fee
Accessory dwelling unit $968
SB 9 lot split, or SB 9 two-unit development $1,737 each
SB 9 lot split and two-unit development together $3,081
Zoning compliance review, minor / major $123 / $420
Development review, minor $1,226
Development review, major, staff level / Planning Commission $6,164 / $6,660
Development review, SB 35 and/or density bonus $5,861
Design review (Design Review Board) $8,911
Minor use permit / major use permit $2,449 / $6,838
Exception / variance $5,144 / $9,649
Parcel map $4,858
Tentative map, 5 to 20 lots / 20 or more lots $15,995 / $17,766
Appeal to a Commission or Board / to the City Council $2,733 / $905
Preliminary review $256 per hour

Source: City of Vallejo Master Fee Schedule FY 2026-2027, Planning Division fee pages, "Fees include a 12% surcharge when applicable."

Section 16.101.04 says the City Council "shall by resolution establish, and from time to time, amend the Master Fee Schedule," and that "Applications processed concurrently shall be subject to separate fees for each application filed unless specifically exempted by the city council." So a duplex that needs development review and a minor use permit pays both fees. Hourly items, such as preliminary review at $256 an hour, need a deposit of half the estimated total under Resolution No. 26-128 N.C., and work stops if a further deposit is not paid within ten days of notice.

The schedule adds three surcharges to Building and Planning fees: technology at 4 percent, permit streamlining at 3 percent and General Plan update at 5 percent. "Surcharges are applied to all fees, except those fees prohibited by state law, or as otherwise excluded."

The 2026 Fee Change

The City Council adopted Resolution No. 26-128 N.C. on July 14, 2026, after a fee study by MGT of America Consulting dated August 2025. It revised Building, Planning and Water Department fees "effective 60 days after the adoption of this Resolution," which is September 12, 2026 (VanPlex arithmetic). The City's Planning Division page gives a different date: "Applications submitted on or after September 14, 2026, will be subject to the new fee schedule in effect at the time of submittal." The resolution sets the legal effective date; ask the Permit Center which date it applies to your filing. Starting July 1, 2027, the fees rise each year by "the net change" in the two departments' "salary and benefit costs."

Impact Fees and Taxes per New Home

Charge FY 2026-2027 amount Note
City excise tax $6,689 per home ADUs exempt (Sec. 3.05.040)
Transportation impact mitigation fee $8,580 per single-family home; $4,824 per multi-family home Ch. 3.07
Greater Vallejo Recreation District park fee $16,977 detached; $15,308 attached; $13,860 duplex; $11,632 three or more ADUs excepted (Sec. 3.18.210)
Solano County public facilities fee $9,263 single-family; $6,662 multi-family; $4,536 second or accessory unit County Resolution No. 2024-915
Vallejo City Unified School District $2.24 per sq ft Residential
Fire facilities fee, Northgate area only $134 per home Attachment 1 map

Source: City of Vallejo Master Fee Schedule FY 2026-2027, Development Impact Fees and Excise Tax; Vallejo Municipal Code Ch. 3.05, Ch. 3.07 and Sec. 3.18.170.

  • Excise tax. Chapter 3.05, the "property development excise tax," set $3,000 per home in 1989 and adjusts it every July 1 by consumer price indexes. It is "paid before approval and issuance of a building permit." Accessory dwelling units are exempt.
  • Transportation fee. Chapter 3.07 charges single-family homes and multi-family homes differently. It defines multifamily residential as "all residential units developed in the city other than single-family dwellings, hotels, or motels," so each duplex or fourplex home pays the multi-family rate. Its single-family definition "includes any accessory dwelling units."
  • Park fee. Section 3.18.170 printed 2007 amounts, from $9,983 for a detached house down to $5,990 for a mobile home, adjusted each January 1 by a Bay Area construction cost index. It is paid "at or prior to the issuance of any building permit." ADUs are excepted. Subdivisions also owe park land or an in-lieu fee under Article I of Chapter 3.18.
  • County and school. Solano County's fee and the school district's fee are set by those agencies; the City's Building Division collects them.

For a fourplex, those rates add up per home to $6,689 excise tax, $4,824 transportation fee, $11,632 park fee and, if the County classes it as multi-family, $6,662: $29,807 per home, or $119,228 for four homes before school fees (VanPlex arithmetic). For an ADU, state law bars impact fees on a unit of 750 square feet or less under Government Code 66311.5, and larger ADUs pay in proportion to the house.

Water and sewer service add their own charges. The schedule lists a water tap and meter set of up to 1 inch at $3,397, and the Vallejo Flood and Wastewater District's annual sanitary sewer service charge at $1,240.56 per dwelling unit.

Where the Code and the Fee Schedule Differ

  • Old dollar amounts. Section 3.05.030 prints $3,000 and Section 3.18.170 prints $9,983; the fee schedule's adjusted amounts, $6,689 and $16,977, are the ones charged.
  • Old references. Chapters 3.05, 3.06 and 3.18 define their terms through sections of the zoning ordinance repealed in 2021, such as "Section 16.04.011." Section 3.05.030 calls the City Charter "the city's Chapter."
  • Public facilities fee. Chapter 3.06 lets the Council set a public facilities impact mitigation fee by resolution, but the FY 2026-2027 fee schedule lists no such City fee; the only public facilities fee it lists is Solano County's.
  • Effective date of new fees. Resolution No. 26-128 N.C. points to September 12, 2026 and the Planning Division page to September 14, 2026.

Best For

  • ✓ Projects of 10 or fewer homes, decided by the Director without a hearing.
  • ✓ ADUs, which skip the excise tax and park fees.
  • ✓ Owners who budget the full per-home charges before buying.

Usually Fails When

  • ✕ An appeal is filed more than ten calendar days after the decision.
  • ✕ The approval lapses after two years with no extension requested.
  • ✕ The budget uses the old amounts printed in the code.

What To Verify Before Spending Money

  • → The fee schedule in force on the day you file.
  • → How Solano County classes the homes for its facilities fee.
  • → School fees per square foot with the school district.

Where to Go Next

Related on VanPlex: the Vallejo overview, the California impact fees page and the CEQA and permit streamlining page.

Frequently Asked Questions

How long do I have to appeal a planning decision in Vallejo? +
Ten calendar days. Vallejo Section 16.602.14 requires appeals to be filed in writing within ten calendar days of the decision, or seven days for a temporary use permit. Director decisions are appealed to the Planning Commission, Design Review Board or AHLC through the Planning Division, and their decisions to the City Council through the City Clerk. An appeal to the Council costs $905.
How long is a Vallejo planning approval good for? +
Two years from the effective date, under Vallejo Section 16.602.12, unless the approval sets another time. Qualifying affordable and mixed-use projects get three years. The Director may grant a one-year extension and then one more, two in all, if the request and fee arrive at least 15 calendar days before the permit expires. A building permit counts as using the approval.
What is the excise tax on a new home in Vallejo? +
Vallejo's FY 2026-2027 Master Fee Schedule lists the City excise tax at $6,689 per residential unit. Chapter 3.05 set it at $3,000 per unit in 1989 and adjusts it each July 1 by consumer price indexes. It is paid before the building permit is issued. Accessory dwelling units are exempt under Section 3.05.040.C.
How much is the park fee for a new home in Vallejo? +
Vallejo's FY 2026-2027 Master Fee Schedule lists the Greater Vallejo Recreation District park fee at $16,977 for a single-family detached home, $15,308 for an attached home, $13,860 per duplex home and $11,632 per home in a building of three or more. The fee is authorized by Section 3.18.170, adjusted each January 1, and does not apply to ADUs.
What does it cost in impact fees to build a fourplex in Vallejo? +
In Vallejo, a fourplex pays per home the $6,689 excise tax, the $4,824 multi-family transportation fee, the $11,632 park fee and, if Solano County classes it as multi-family, a $6,662 county fee: $29,807 per home and $119,228 for four homes, by VanPlex arithmetic from the FY 2026-2027 schedule. School fees of $2.24 per square foot come on top.
When did Vallejo last raise its planning fees? +
Vallejo's City Council adopted Resolution No. 26-128 N.C. on July 14, 2026, revising Building and Planning fees, effective 60 days after adoption. The Planning Division page says the new fees apply to applications submitted on or after September 14, 2026. From July 1, 2027 the fees rise each year with the departments' salary and benefit costs.
Does a duplex need a public hearing in Vallejo? +
Usually no. Vallejo Note 1 to Table 16.301-A sends projects of 2 to 10 homes to a Director decision, and Table 16.601-A says Director decisions need no public hearing. Notice is still mailed to owners within 300 feet at least 14 days before a Director action under Section 16.602.08. A decision becomes effective after the ten-day appeal period.
What surcharges does Vallejo add to permit fees? +
Vallejo adds a 4 percent technology surcharge, a 3 percent permit streamlining surcharge and a 5 percent General Plan update surcharge to Planning and Building fees, 12 percent in all, under its FY 2026-2027 Master Fee Schedule and Resolution No. 26-128 N.C. The surcharges do not apply to fees state law protects from them.
Who sets Vallejo's permit fees? +
The Vallejo City Council sets permit fees by resolution in a Master Fee Schedule, under Section 16.101.04 of the Zoning Code, which also says applications processed together pay separate fees for each application unless the Council exempts them. The FY 2026-2027 schedule is a 390-page document that also lists water, sewer, county and school district charges.
Is there a deadline for Vallejo to decide an SB 9 project? +
Yes, from state law. Government Code 65852.21 requires a city to approve or deny a complete SB 9 two-unit application within 60 days, or it is deemed approved, and Vallejo's code has no SB 9 section that sets a different process. Vallejo's ADU chapter sets the same 60-day deadline for ADUs, with a 15 business day completeness check.

Official sources (checked October 2026)

City of Vallejo, Master Fee Schedule FY 2026-2027 (PDF)
https://www.cityofvallejo.net/business/business_information/fee_schedule
City of Vallejo, Planning Division page
https://www.cityofvallejo.net/cms/One.aspx?portalId=16925451&pageId=17560677
Vallejo Municipal Code, Section 16.601.07 and Table 16.601-A, permit review authority
https://library.municode.com/ca/vallejo/codes/municipal_code?nodeId=TIT16ZO_PTVIPRPE_CH16.601PLAU_16.601.07SUREAUDEAP
Vallejo Municipal Code, Section 16.602.08, noticing
https://library.municode.com/ca/vallejo/codes/municipal_code?nodeId=TIT16ZO_PTVIPRPE_CH16.602COPR_16.602.08NO
Vallejo Municipal Code, Section 16.602.11, effective dates
https://library.municode.com/ca/vallejo/codes/municipal_code?nodeId=TIT16ZO_PTVIPRPE_CH16.602COPR_16.602.11EFDA
Vallejo Municipal Code, Section 16.602.12, expiration and extension
https://library.municode.com/ca/vallejo/codes/municipal_code?nodeId=TIT16ZO_PTVIPRPE_CH16.602COPR_16.602.12EXEX
Vallejo Municipal Code, Section 16.602.14, appeals
https://library.municode.com/ca/vallejo/codes/municipal_code?nodeId=TIT16ZO_PTVIPRPE_CH16.602COPR_16.602.14AP
Vallejo Municipal Code, Chapter 16.603, zoning compliance review
https://library.municode.com/ca/vallejo/codes/municipal_code?nodeId=TIT16ZO_PTVIPRPE_CH16.603ZOCORE
Vallejo Municipal Code, Chapter 16.605, development review
https://library.municode.com/ca/vallejo/codes/municipal_code?nodeId=TIT16ZO_PTVIPRPE_CH16.605DERE
Vallejo Municipal Code, Chapter 3.05, property development excise tax
https://library.municode.com/ca/vallejo/codes/municipal_code?nodeId=TIT3REFI_CH3.05PRDEEXTA
Vallejo Municipal Code, Chapter 3.07, transportation impact mitigation fee
https://library.municode.com/ca/vallejo/codes/municipal_code?nodeId=TIT3REFI_CH3.07TRIMMIFE
Vallejo Municipal Code, Section 3.18.170, park impact fees
https://library.municode.com/ca/vallejo/codes/municipal_code?nodeId=TIT3REFI_CH3.18LADEFEPAREPU_ARTIIPAIMFE_3.18.170PAIMFEMP
City of Vallejo, Ordinance No. 1890 N.C.(2d), accessory dwelling units (PDF)
https://www.cityofvallejo.net/common/pages/GetFile.ashx?key=anxGAdOC
Government Code 65852.21 (SB 9 two-unit projects)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=65852.21
Government Code 66311.5 (ADU fees)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66311.5
General information, not legal advice. California housing law changes every year, and each city adds its own rules on top of state law. Confirm current requirements with the city or county planning department, and with a California-licensed attorney or architect, before you buy land or file plans.