Brownsville | Plats, Permits and Fees

Brownsville Plats, Permits and Fees: Plat Types, Deadlines and the FY 2027 Fee Schedule

A Brownsville housing project passes through two City reviews. The first is the plat, the recorded map that divides land into lots, under Article 3 of the Unified Development Code (UDC). The second is the building permit under Section 4.2.8. This page explains which plat you need, who decides it and how fast, when a lot can skip platting, and what the City charges under the FY 2027 Master Fee Schedule. The Brownsville overview has the short version.

Plats, permits and fees in six facts

When a Plat Is Needed

Under Section 3.1.4, an owner inside the city or in its extraterritorial jurisdiction (ETJ), the area outside the city limits where the City reviews plats, "must prepare a plat and record the plat with the County Clerk" before dividing a tract "in two (2) or more parts." A division made "by using a metes and bounds description in a deed of conveyance," or by a contract for deed, still needs a plat.

Section 3.1.5 lists the exemptions. A tract divided into parts of five acres or more, each with access to an improved public road, is exempt under Local Government Code 212.004. A parcel whose boundaries were "fully described by one (1) or more title transfer instruments executed before March 30, 1971," and not changed since, is exempt under the "grandfather clause" if it can reach water and wastewater lines directly and has at least 12 feet of frontage. Both are confirmed by a determination certificate from the Planning Director.

Ordinance No. 2025-235.124, passed January 6, 2026, added a route for single-family lots. The Planning Director "may exempt a property from platting without the approval of a determination" certificate when the lot has been the site of a single-family home that is "being rebuilt or remodeled in its totality due to unforeseen circumstances or an act of God," or that is being expanded within the zoning rules; when it had a legal water and wastewater connection, or has direct access to the lines; when its boundary is shown by a deed or a survey sealed within 6 months; and when it has "a minimum frontage of 12 feet on a public" right-of-way or easement at least 30 feet wide. The scanned ordinance drops a few words, so confirm the exact text with the Planning Department.

A second January 2026 ordinance, No. 2025-235.122, made zoning a first step. Section 3.1.3.A now says "No plat type shall be accepted for final processing, approval or recording unless the proposed use that will be established on the resulting" lots is "permitted by right or permitted through a zoning atlas amendment," a rezoning.

Plat Types and Who Decides

Plat Used when Decision-maker
Preliminary plat A subdivision that needs new streets or utility lines, or is built in phases City staff
Final plat After public improvements are built and accepted City staff; City Commission if a development agreement is used
Minor plat Four or fewer lots on an existing street, with no new water or wastewater lines City staff
Amending plat Fixes errors or moves lot lines without adding lots City staff
Replat, nonresidential Re-divides a recorded plat Planning and Zoning Commission
Replat, residential Re-divides a recorded plat limited to two homes per lot Planning and Zoning Commission, with notice
Conveyance plat Divides land to sell it, with no approval to build Planning and Zoning Commission
Plat vacation Cancels a recorded plat Planning and Zoning Commission, after a hearing

Source: Table 2.1-1 as restated by Ordinance No. 2026-235.128 (June 16, 2026), and Brownsville UDC Section 3.2, Supplement 26.

Every plat must give lots that "conform to the minimum lot and area regulations of the governing zoning district." A preliminary plat is "the first stage of the platting process" and is never recorded; a final plat follows once streets, water and wastewater lines are built and accepted by the City Engineer, or with a development agreement and financial security if they are built later. Ordinance No. 2025-235.112 moved the preliminary, final and minor plat decisions to staff in March 2025, and Table 2.1-1 now lists City staff as the decision-maker for each.

Each new lot needs a sidewalk. Under Section 3.4.4 the owner "shall either construct a sidewalk or pay a fee in lieu" after plat approval, the fee amount "is determined by the City Engineer," and a lot in a multi-lot or master planned subdivision may not use the fee. Sidewalks are at least 5 feet wide.

Deadlines

  • Completeness. Under Section 2.3.4, the Planning Director decides whether an application is complete within fourteen business days; if not, "the application will be deemed complete." An incomplete application expires "on or after the 45th day" if its gaps are not fixed.
  • Decision. The decision-maker acts "within thirty (30) calendar days following the date the application has passed completeness check." If it does not, the plat "shall be deemed approved."
  • Waiver. An applicant may file one "Waiver of Right to 30-Day Action" for a plat, which delays action for up to thirty days.
  • Expiration. A preliminary plat expires after two years unless construction plans are approved or a final plat is filed, and staff may extend it once by one year. Minor plats, replats and amending plats expire two years after approval.

The state rule is close but counts from a different day. Local Government Code 212.009 says a city "shall approve, approve with conditions, or disapprove a plat within 30 days after the date the plat is filed," and a plat not disapproved in time is approved. Section 212.0081 says an application with every item on the city's published list "is considered complete," and Section 212.0097 says a city "may not request or require an applicant to waive a deadline." Where the City text and the statute differ, the statute controls. After a conditional approval or denial, the applicant may answer in writing, and under Section 212.0095 the City decides the answer within 15 days.

Replats and Protests

A replat re-divides land in a recorded plat. Under Section 3.2.4, the Planning and Zoning Commission decides replats, and staff may approve one that has "four (4) or fewer lots fronting on an existing street" with no new street, no extension of City lines and no required hearing. A replat counts as residential when, in the last five years, the land was zoned for no more than two homes per lot or deed restrictions limited it the same way.

A residential replat with a subdivision waiver, a request to depart from a subdivision rule, needs a hearing with newspaper notice and mailed notice to owners within 200 feet. If owners protest, Section 3.2.4.G requires "the affirmative vote of at least three-fourths of the voting members of the Planning and Zoning Commission present," and counts a protest from "at least twenty (20) percent of property owners who own property located within two hundred (200) feet." Local Government Code 212.015(c) measures the 20 percent by "area of the lots or land" next to the replat and "within the original subdivision," so the statute's test differs from the City's owner count; the statute controls. Without a waiver, the City mails notice of the approval within 15 days, with the new zoning and a phone number and email.

Building Permits

Under Section 4.2.8, the Building Official reports missing items "within ten (10) business days," and "will approve or deny the application within thirty (30) calendar days after the date the application is deemed complete." An applicant who does not send corrected plans "within ninety (90) days" after a list of deficiencies loses the application. A house or duplex needs a plot plan, and a residential building of more than three homes needs Site Plan approval first. No building may be used until the Building Official issues a Certificate of Occupancy under Section 4.2.9. Local Government Code 214.904 gives a Texas city 45 days to grant or deny a permit application, give written reasons, or agree on a deadline, and a city that misses its deadline may not collect the permit fees.

Fees

Section 2.3.3.D says every application comes with "the prescribed fees set forth in the adopted fee schedule," and that fees are not refunded unless paid in error. The City adopted its FY 2027 Master Fee Schedule by Ordinance No. 2026-1761-B, which takes effect on second reading; the draft minutes of September 22, 2026 record that reading passing 5 to 0.

Item FY 2027 fee
Minor subdivision, residential, 0 to 1 acre $350
Minor subdivision, residential, 1 to 5 acres $500
Major subdivision, residential, 0 to 1 acre $500
Major subdivision, residential, 1 to 10 acres $1,000
Major subdivision, residential, 10 acres and up $2,000
Amending plat $375
Determination certificate, 5-acre rule $500
Technology fee, subdivisions (new in FY 2027) $250
Subdivision park fee, residential, per dwelling unit $500
Building permit base fee $40
Residential new construction, 3,011 sq ft and up $0.30 per sq ft
Certificate of occupancy, residential or multifamily, per unit $50

Source: Exhibit A, FY 2027 Master Fee Schedule (Ordinance No. 2026-1761-B), Planning and Redevelopment Services rows, in the City Commission agenda packet of September 22, 2026. The plat fees are listed under "Zoning Permit."

A new house pays the $40 base building fee plus a rate per square foot. The schedule lists the residential tiers as "1-1,450," "1,451-3,010" and "3,011+" square feet, at $0.25, $0.27 and $0.30, and it does not say whether a house of 2,000 square feet pays $0.27 on every foot or $0.25 on the first 1,450 feet; ask the Building Division before you budget. Residential plan checking is $50, the technology fee on a new home permit is $100, and the certificate of occupancy is $50 per unit.

Two lines in the schedule do not match the code word for word. The schedule lists a "Commercial Park Fee" of $2,000 "Per Subdivided Acre," citing UDC 5.2.3.E, while Section 5.2.3.G of the UDC sets "six thousand dollars ($6,000) per acre" for nonresidential development. And it lists a "Determination Certificate - 1995 Rule" at $300, while Section 3.1.5 sets the grandfather date at March 30, 1971. Ask the Planning Department which figure it charges.

Park Fees and the Roadway Capital Recovery Fee

Parkland applies to property of two net acres or more. Section 5.2.3 requires "one (1) acre of parkland per one hundred (100) dwelling units" in RE, R-1, R-2, R-3 and TN, or a payment of "five hundred dollars ($500) per dwelling unit." The City sets the amount at preliminary plat approval, and the developer pays before the final plat is recorded. If the City has not spent the money on parks within eight years, the owner may ask in writing for a refund.

The roadway capital recovery fee is a charge for road capacity under Local Government Code chapter 395, the state impact fee law. Chapter 9 of the Code of Ordinances, adopted by Ordinance No. 2024-1739 with an effective date of May 7, 2024, says in Section 9-13: "Fees shall be $ 1,000.00 per residential dwelling unit and ten percent of the valuation for nonresidential development," and "Fees shall increase by 5 percent each year for the following four years." The fee "shall be collected at the time the City issues a building permit." Section 9-14 exempts qualifying low-income housing, development in the historic downtown area bounded by Fronton Street, Jackson Street, International Boulevard and Palm Boulevard, and "Properties that are exempt from platting." Chapter 314 of the code, titled Impact Fees, holds definitions and an advisory committee, and its land use, capital plan and fee articles are marked "Reserved." Water and wastewater connections run through the utility provider; ask it for its fees.

Best For

  • ✓ A minor plat of four or fewer lots on an existing street, decided by staff in 30 days.
  • ✓ Rebuilding a house on an unplatted lot that had a legal utility connection, under the January 2026 exemption.
  • ✓ A subdivision under two net acres, which owes no parkland.

Usually Fails When

  • ✕ The plat is filed before the land has the zoning its lots need.
  • ✕ The project relies on a sidewalk fee in lieu inside a master planned subdivision.
  • ✕ The budget leaves out the $1,000 per home roadway fee at building permit.

What To Verify Before Spending Money

  • → Whether the land is in the city or the ETJ, and whether a recorded plat exists.
  • → The current year rate of the roadway capital recovery fee.
  • → Water and wastewater service and its fees with the utility provider.

Where to Go Next

Related on VanPlex: the Brownsville overview, how Texas zoning works and financing 2 to 4 units.

Frequently Asked Questions

How long does Brownsville take to approve a plat? +
Brownsville staff check a plat application for completeness within 14 business days under UDC Section 2.3.4, and the decision-maker then has 30 calendar days to approve, approve with conditions or deny it. If no decision is made in that time, the UDC says the plat is deemed approved. Local Government Code 212.009 counts its 30 days from the date the plat is filed.
What is a minor plat in Brownsville? +
A minor plat in Brownsville creates four or fewer lots that front an existing street, need no new street, and need no extension of public water or wastewater lines, under UDC Section 3.2.3. The Planning Director decides it within 30 days of a complete filing. A residential minor subdivision of up to one acre costs $350 under the FY 2027 Master Fee Schedule.
Can I rebuild a house in Brownsville without platting the lot? +
Often, yes. Brownsville Ordinance No. 2025-235.124, passed January 6, 2026, lets the Planning Director exempt a lot from platting when it has been the site of a single-family home being rebuilt or remodeled, had a legal water and wastewater connection, has a boundary shown by deed or a recent survey, and has at least 12 feet of frontage on a street or easement.
What does the Brownsville roadway capital recovery fee cost? +
Brownsville Code Section 9-13 sets the roadway capital recovery fee at $1,000 per residential dwelling unit and ten percent of the valuation for nonresidential development, rising 5 percent a year for the four years after the article is implemented; its effective date is May 7, 2024. The fee is collected when the building permit is issued, and qualifying low-income housing is exempt.
Does Brownsville charge a park fee on a small subdivision? +
Brownsville UDC Section 5.2.2 exempts property of less than two net acres, property in the extraterritorial jurisdiction, AG land, and replats that add no homes. Larger residential subdivisions dedicate one acre of parkland per 100 homes or pay $500 per home. The fee is set at preliminary plat approval and paid before the final plat is recorded.
Do I need a public hearing to replat my Brownsville lot? +
A Brownsville residential replat needs a hearing when it asks for a subdivision waiver, under UDC Section 3.2.4. If the replat needs no waiver, the City mails notice to owners within 200 feet no later than 15 days after approval, with the new zoning and a phone number and email. Replats of four or fewer lots on an existing street may be approved by staff.
How long does a Brownsville building permit take? +
Under Brownsville UDC Section 4.2.8, the Building Official reports missing items within ten business days and decides within thirty calendar days after the application is complete. An applicant who does not answer a list of deficiencies within ninety days loses the application. Local Government Code 214.904 gives a Texas city 45 days to act on a permit application.
What are the Model Subdivision Rules in Brownsville? +
The Model Subdivision Rules are state rules that border counties, including Cameron County, must enforce so residential lots are not sold without water and sewer. Brownsville UDC Section 3.1.6 applies them to subdivisions creating two or more lots of five acres or less for homes. The plat needs proof of utility service and a note limiting each lot to one single family detached dwelling.
Can Brownsville ask me to waive the 30-day plat deadline? +
Local Government Code 212.0097 says a city may not request or require an applicant to waive a plat deadline. Brownsville UDC Section 2.3.4.H lets the applicant file one Waiver of Right to 30-Day Action for a plat, which delays action for up to 30 more days. Section 212.009(b-2) of the statute allows an extension when the applicant asks and the city agrees.
How long is a Brownsville plat approval good for? +
A Brownsville preliminary plat expires two years after approval unless construction plans are approved or a final plat is filed, under UDC Section 3.2.1.I, and staff may extend it once by one year. Minor plats, replats and amending plats also expire two years after approval. Recording requires payment of parkland, impact and sidewalk fees first.

Official sources (checked October 2026)

Brownsville UDC Section 3.2, subdivision plats
https://library.municode.com/tx/brownsville/codes/code_of_ordinances?nodeId=PTIICOOR_ART3SURE_3.2SUPL
Brownsville UDC Section 3.2.4, replats
https://library.municode.com/tx/brownsville/codes/code_of_ordinances?nodeId=PTIICOOR_ART3SURE_3.2SUPL_3.2.4RE
Brownsville UDC Section 3.1.5, exemptions to platting
https://library.municode.com/tx/brownsville/codes/code_of_ordinances?nodeId=PTIICOOR_ART3SURE_3.1GEPR_3.1.5EXPL
Brownsville UDC Section 3.1.6, Model Subdivision Rules
https://library.municode.com/tx/brownsville/codes/code_of_ordinances?nodeId=PTIICOOR_ART3SURE_3.1GEPR_3.1.6MOSURU
Brownsville UDC Section 2.3.4, application completeness
https://library.municode.com/tx/brownsville/codes/code_of_ordinances?nodeId=PTIICOOR_ART2ADREPR_2.3APSUPR_2.3.4DEAPCO
Brownsville UDC Section 4.2.8, building permits
https://library.municode.com/tx/brownsville/codes/code_of_ordinances?nodeId=PTIICOOR_ART4ZORE_4.2ZOPR_4.2.8BUPE
Brownsville UDC Section 3.4.4, sidewalks
https://library.municode.com/tx/brownsville/codes/code_of_ordinances?nodeId=PTIICOOR_ART3SURE_3.4SUDEST_3.4.4SI
Brownsville UDC Section 5.2, parkland dedication
https://library.municode.com/tx/brownsville/codes/code_of_ordinances?nodeId=PTIICOOR_ART5SURE_5.2OPSPTRST
Brownsville Ordinance No. 2025-235.122, zoning before platting (January 6, 2026)
https://library.municode.com/tx/brownsville/ordinances/code_of_ordinances?nodeId=1401705
Brownsville Ordinance No. 2025-235.124, plat exemption for single-family lots (January 6, 2026)
https://library.municode.com/tx/brownsville/ordinances/code_of_ordinances?nodeId=1401709
Brownsville Ordinance No. 2026-235.128, approval authorities (June 16, 2026)
https://library.municode.com/tx/brownsville/ordinances/code_of_ordinances?nodeId=1434138
Brownsville Code of Ordinances, Chapter 9, roadway capital recovery fees
https://library.municode.com/tx/brownsville/codes/code_of_ordinances?nodeId=PTIICOOR_CH9CAREFE
City of Brownsville, agenda packet of September 22, 2026, with the FY 2027 Master Fee Schedule (PDF)
https://brownsvilletx.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=6287,plainText=false)
Local Government Code 212.009 (plat approval deadlines)
https://statutes.capitol.texas.gov/Docs/LG/htm/LG.212.htm#212.009
Local Government Code chapter 212 (plats and replats)
https://statutes.capitol.texas.gov/Docs/LG/htm/LG.212.htm
Local Government Code 214.904 (building permit deadlines)
https://statutes.capitol.texas.gov/Docs/LG/htm/LG.214.htm#214.904
General information, not legal advice. Texas has no statewide zoning code. Each city writes its own rules, and deed restrictions recorded on a lot can forbid what the city allows. Confirm current requirements with the city planning department, read the deed restrictions for your lot, and talk to a Texas-licensed attorney or architect before you buy land or file plans.