Corpus Christi | Plats, Permits and Fees

Corpus Christi Plats, Permits and Fees: Plat Types, Deadlines and What the City Charges

A Corpus Christi project passes two City reviews before construction. The first is the plat, the recorded map that divides land into lots, under Article 3 of the Unified Development Code (UDC). The second is the building permit. Fees for both are set in Chapter 14 of the Code of Ordinances, and new lots also pay trust fund fees for water and sewer mains and a park fee. This page gives the steps, deadlines and FY 2026 amounts. The Corpus Christi overview gives the short version.

Corpus Christi plats and fees in six facts

When a Plat Is Needed

Section 3.8.1 requires a plat before "the subdivision, re-subdivision or development of any land within the City or of the ETJ," the extraterritorial jurisdiction outside the city limits. A division counts whether it is made by deed, contract or "any other method." No building permit may be issued until the land "has received final plat approval" and "the plat has been recorded." The City's platting page says a plat is needed "when land is divided into two or more tracts for purpose of sale, transfer of ownership or in creating a new building site prior to issuance of a building permit or connecting to City utilities," within the city or five miles of it.

Section 3.8.2 lists the exceptions, among them divisions into parts greater than 5 acres with street access and no public improvement, additions to an existing building that need no new utilities, street access or drainage, and a change in ownership by inheritance or probate.

Plat Types and Who Decides

Plat type When it is used Who decides Expiration
Preliminary plat Any division that is not a minor, amending or vacating plat or a replat Planning Commission, within 30 days of completeness 24 months unless final plats are approved
Final plat Follows an approved preliminary plat and must be consistent with it Planning Commission, within 30 days of completeness 12 months if improvements are not in place or started, unless secured
Minor plat Combines existing platted lots into 4 or fewer lots on an existing street, with no added lots and no new street or utilities Technical Review Committee (staff); cannot deny 6 months if not filed with the county
Amending plat A plat meeting Local Government Code 212.016 (corrections and small changes) Technical Review Committee (staff) 6 months if not filed
Vacating plat Cancels a final plat before lots are sold, or with all owners' consent Technical Review Committee (staff) 6 months if not filed
Replat without vacation Redraws recorded lots, signed only by their owners, without removing covenants Planning Commission, within 30 days of completeness 6 months if improvements are not started

Source: Corpus Christi UDC, Section 3.8, Section 3.10 and Section 3.11.

Corpus Christi's minor plat is narrower than many cities' version. Section 3.10.1 defines it as "a replat for the combining or consolidating of any number of existing, platted lots, if the replat results in four or fewer lots fronting on an existing street, does not increase the number of lots." Splitting one lot into two adds a lot, so it does not qualify, and it goes to the Planning Commission as a replat or final plat. "Any plat that requires a waiver from subdivision design and improvement standards of this UDC shall not be processed as a minor plat."

The Technical Review Committee, a panel of City staff and utility providers, reviews every plat. Section 3.10.2 says it "may not deny a minor, amending or vacating plat"; one that fails the rules goes to the Planning Commission. Section 3.8.3.B adds that a committee member who does not comment during review may not ask for more material later.

Deadlines

Section 3.1.6.E starts the clock. Staff decide within five business days of submittal whether an application is complete. If it is not, they send a written list of missing items within ten business days and allow at least ten business days to resubmit; an application not resubmitted is rejected and needs a new fee. Ordinance No. 033317 of March 19, 2024 added the submittal checklist for each plat type; Local Government Code 212.0081 requires each city to adopt and publish such a list, and an application with every listed item "is considered complete."

  • The Planning Commission acts on a preliminary plat within 30 days of completeness; "in the event the Planning Commission shall fail to act within 30 days, the preliminary plat shall be considered approved."
  • It approves or denies a final plat or a replat without vacation within 30 days of completeness, with written reasons for a denial.
  • Local Government Code 212.009 sets the same 30 days and extends it by periods of up to 30 days each when the applicant asks in writing and the City approves.
  • For a building permit, Local Government Code 214.904 gives the City 45 days to grant or deny, explain in writing, or agree on a deadline; if it misses the deadline it may not collect the permit fees and must refund any it took.

The City's platting page says "Plat review cycles 30-Days and can be extended in 30-Day increments. We recommend 60-Days for Public-Notice Plats," and that "as a general rule, the time period involved from the date of a completed application to the filing of the plat for record is two months."

Replats in Older Neighborhoods

Under Section 3.11, a replat without vacation may redraw recorded lots if signed only by their owners and if it does not "amend or remove any covenants or restrictions previously incorporated in the recorded plat." Section 3.1.7.B requires notice "as mandated by Section 212.015 of the Texas Local Government Code."

Section 212.015 covers a replat of land that, in the past five years, was limited by zoning or deed restriction to no more than two homes per lot. When such a replat "requires a variance or exception," a public hearing is held, owners within 200 feet in the original subdivision get notice before the 15th day, and a protest by owners of 20 percent of that area requires a three-fourths vote. The City's platting page describes notice for every replat that meets the five-year test, without the variance condition. The statute sets the trigger for the hearing, and it controls where the two differ.

FY 2026 Plat and Permit Fees

Fees are set in Chapter 14, Article XIII of the Code of Ordinances: Section 14-1313 for building permits and Section 14-1341 for UDC fees. The City's FY 2026 Development Fee Schedule prints the same amounts and says they are "effective fees from October 1, 2025 to September 30, 2026."

Fee FY 2026 amount
Preliminary plat, under 1 acre / 1 to 5 acres / over 5 acres $1,863.40 / $2,395.80 / $2,928.20
Final plat, under 1 acre / 1 to 5 acres / over 5 acres $1,197.90 / $1,730.30 / $2,262.70
Minor plat (4 lots or less) $911.74
Amending or vacating plat $1,002.91
Planning Commission appeal or waiver $1,064.80
Plat time extension $399.30
Public notice surcharge $250.00
Recording fee Actual cost plus $66.55
Public improvement plan review, under 1 acre $2,168.19
Residential building permit (new, additions, remodels) $0.461 per sq ft, $146.41 minimum
Residential plan review $0.146 per sq ft
Residential electrical, plumbing, mechanical permits $0.075 per sq ft each
Residential demolition $266.20
Development Services administration surcharge 4.5% on listed permits and fees

Source: Corpus Christi Code of Ordinances, Sections 14-1313, 14-1341 and 14-1351, Supplement 44; City of Corpus Christi, FY 2026 Development Fee Schedule, Rev. October 1, 2025.

Each fee section ends: "After Fiscal Year 24-25, all fees in this section shall be indexed to the August Construction Index published in the Engineering News-Record and shall automatically increase on October 1 of each fiscal year." The schedule says "all fees will be reassessed in August 2026 for Fiscal Year 2027," and on October 8, 2026 the City's fee schedules page still listed FY 2026 as the newest schedule. Ask for the FY 2027 amounts before you budget.

Two small differences between the code and the schedule: the code's "Plat Revision Fee" row has no amount, while the schedule prints "15% of application fee after 2nd review"; and the schedule prints the Board of Adjustment fee as "$1,4902.72," where Section 14-1361 sets $1,490.72. The adopted code controls, so the Board fee is $1,490.72.

Water and Wastewater Trust Fund Fees

Corpus Christi pays for water and sewer mains through trust funds. Section 8.5 requires the developer to pay lot or acreage fees "before any unit of a subdivision or single lot is completed and the final plat recorded," and a surcharge applies when a service tap is requested. The money reimburses developers who build mains that follow the City's master plans. The FY 2026 amounts:

Trust fund fee FY 2026 amount
Water lot fee $525.61
Water lot fee, single-family or duplex $266.47
Water acreage fee $2,106.84
Water acreage fee, single-family or duplex $1,052.69
Water surcharge, single-family or duplex $355.78
Water distribution line pro rata $15.42 per front foot
Wastewater lot fee $575.39
Wastewater acreage fee $2,300.10
Wastewater surcharge $405.56
Wastewater collection line pro rata $17.83 per front foot

Source: Corpus Christi Code of Ordinances, Section 14-1341; FY 2026 Development Fee Schedule, page 9. Each fee carries the 4.5 percent surcharge.

The rules changed in 2026. Ordinance No. 033894, passed on second reading on March 24, 2026, struck "whichever is greater" from the lot or acreage fee rule and added: "Acreage fees shall be assessed on multifamily, commercial, and industrial properties. Lot fees shall be assessed on single-family and two-family residential properties." It also says the front-foot pro rata fee will not be collected when "the developer must install infrastructure (above and beyond a tap) to access the utility." The enCodePlus copy of the UDC still prints the older text, so the ordinance controls until the online code is updated.

Corpus Christi has no impact fee in its fee sections. An ordinance to adopt water, wastewater, stormwater and roadway impact fees and "sunset trust fund fees" is listed in the City Council records as a held item from June 2024, and a resolution to set a May 12, 2026 hearing on impact fees was withdrawn on March 17, 2026, its title noting that "no action is needed on this item if Council direction is to remain on Trust Funds."

Park Fee, Guarantees and Proportionality

Section 8.3 requires parkland of 1 acre per 100 single-family homes or per 200 multifamily units, or a park development fee in lieu of land. Section 8.3.6 sets the fee at "$462.50 per dwelling unit," adjusted "each January 1, with the first adjustment January 1, 2024," by the consumer price index, and payable "at or prior to the time of filing the final plat or prior to the issuance of a building permit where a plat is not required." The fee schedule does not list the adjusted amount, so ask the City for the 2026 figure. Plats of single-family lots of 5 acres or more, and replats that already met the rule, are exempt.

A plat may be recorded before its streets and utilities are done. Section 8.1.10 allows it when the developer posts a guarantee of "110% of the cost of the delayed public improvements," water and sewer service are available, and the work is finished within five years. Under Section 3.9, infrastructure costs must be "roughly proportionate to the proposed development"; on request the City retains a licensed engineer to decide, with appeals to the City Council and then to a county court at law or district court in Nueces County within 30 days.

Best For

  • ✓ A combination of existing platted lots into four or fewer, which staff can approve as a minor plat.
  • ✓ A single-family or duplex lot, which pays the lower water lot fee of $266.47.
  • ✓ A project where streets are not finished but a 110 percent guarantee can be posted.

Usually Fails When

  • ✕ The plan splits one lot into two and expects a staff-level minor plat.
  • ✕ The budget uses FY 2026 amounts after the October 1, 2026 index increase.
  • ✕ The replat needs a variance and 20 percent of nearby owners protest.

What To Verify Before Spending Money

  • → The FY 2027 fee amounts, and the 2026 park development fee.
  • → Which trust fund fee applies under Ordinance No. 033894 to your lot.
  • → Whether the land was limited to two homes per lot in the past five years.

Where to Go Next

Related on VanPlex: the Corpus Christi overview, how Texas zoning works and Texas property tax.

Frequently Asked Questions

How long does a plat take in Corpus Christi? +
Corpus Christi UDC Section 3.8 gives the Planning Commission 30 days from the determination of completeness to act on a preliminary or final plat, and a preliminary plat not acted on in that time is considered approved. The City's platting page says review cycles run 30 days and can be extended in 30-day increments, and that a completed application usually takes two months to reach recording.
What is a minor plat in Corpus Christi? +
A minor plat in Corpus Christi, under UDC Section 3.10.1, is a replat that combines existing platted lots into four or fewer lots on an existing street, does not increase the number of lots, and needs no new street or utility extension. Staff on the Technical Review Committee approve it and cannot deny it. A plat needing a waiver cannot be a minor plat. The FY 2026 fee is $911.74.
How much does a plat cost in Corpus Christi? +
Corpus Christi Code Section 14-1341 and the FY 2026 fee schedule list a final plat of under 1 acre at $1,197.90, a preliminary plat of under 1 acre at $1,863.40, and a minor plat at $911.74. A plat needing public notice adds a $250 surcharge, recording costs the actual county charge plus $66.55, and a 4.5 percent administration surcharge applies to these fees.
Does Corpus Christi charge impact fees? +
Not as of October 8, 2026, by VanPlex review of City records. An ordinance to adopt water, wastewater, stormwater and roadway impact fees is listed as a held item from June 2024, and a resolution to set a May 12, 2026 hearing on them was withdrawn on March 17, 2026. Its water and wastewater charge is the trust fund lot and acreage fee under UDC Section 8.5.
What are trust fund fees in Corpus Christi? +
Trust fund fees are Corpus Christi charges, set in UDC Section 8.5 and Code Section 14-1341, that pay for water and wastewater mains and reimburse developers who build them. They are paid before a final plat is recorded. The FY 2026 water lot fee for a single-family or duplex lot is $266.47 and the wastewater lot fee is $575.39, each with a 4.5 percent surcharge.
What changed in the Corpus Christi trust fund rules in 2026? +
Corpus Christi Ordinance No. 033894, passed on second reading March 24, 2026, amended UDC Section 8.5. It struck the rule that a developer pays the lot fee or acreage fee, whichever is greater, and provided that acreage fees apply to multifamily, commercial and industrial property and lot fees to single-family and two-family property. The online UDC copy still shows the older text.
How long does Corpus Christi have to issue a building permit? +
Local Government Code 214.904 gives a Texas city, including Corpus Christi, 45 days after a permit application is submitted to grant or deny it, explain in writing why it cannot yet decide, or agree on a deadline. After a written notice it has 30 more days. If it misses the deadline it may not collect the permit fees and must refund any it collected.
What does the building permit for a new house cost in Corpus Christi? +
Corpus Christi Code Section 14-1313 sets residential fees by floor area: a building permit of $0.461 per square foot with a $146.41 minimum, plan review of $0.146 per square foot, and electrical, plumbing and mechanical permits of $0.075 per square foot each, plus a 4.5 percent surcharge. For a 2,000 square foot duplex that is $1,738.88, by VanPlex arithmetic, before other fees.
Can I record a plat in Corpus Christi before the streets and utilities are finished? +
Yes, in some cases. Corpus Christi UDC Section 8.1.10 lets the Assistant City Manager approve recording before improvements are complete if the developer posts a guarantee of 110 percent of the cost of the delayed work, water and sewer service are available, and a standard agreement is signed. The improvements must be finished within five years or a shorter time the City sets.
Do neighbors get notice of a replat in Corpus Christi? +
Sometimes. Local Government Code 212.015 requires a hearing and notice to owners within 200 feet in the original subdivision when a replat of land limited in the past five years to two homes per lot needs a variance or exception. The Corpus Christi platting page describes notice for every such replat. A protest by owners of 20 percent of that area then requires a three-fourths vote.
What if Corpus Christi asks me to build more infrastructure than my project needs? +
Corpus Christi UDC Section 3.9 says infrastructure costs placed on a developer must be "roughly proportionate" to the development. On request, the City retains a licensed professional engineer to make that determination. The applicant may appeal to the Assistant City Manager and then the City Council, and then to a county court at law or district court in Nueces County within 30 days.

Official sources (checked October 2026)

Corpus Christi UDC Section 3.1 (common review procedures, completeness and notice)
https://online.encodeplus.com/regs/corpuschristi-tx/doc-viewer.aspx#secid-342
Corpus Christi UDC Section 3.8 (subdivision plat review)
https://online.encodeplus.com/regs/corpuschristi-tx/doc-viewer.aspx#secid-408
Corpus Christi UDC Section 3.10 (minor, amending or vacating plats)
https://online.encodeplus.com/regs/corpuschristi-tx/doc-viewer.aspx#secid-432
Corpus Christi UDC Section 3.11 (replat without vacation)
https://online.encodeplus.com/regs/corpuschristi-tx/doc-viewer.aspx#secid-437
Corpus Christi UDC Section 3.18 (building permit)
https://online.encodeplus.com/regs/corpuschristi-tx/doc-viewer.aspx#secid-486
Corpus Christi UDC Section 8.2 and 8.1 (design standards and plat recording)
https://online.encodeplus.com/regs/corpuschristi-tx/doc-viewer.aspx#secid-1528
Corpus Christi UDC Section 8.3 (public open space and park fee)
https://online.encodeplus.com/regs/corpuschristi-tx/doc-viewer.aspx#secid-1551
Corpus Christi UDC Section 8.5 (trust fund policy, online copy)
https://online.encodeplus.com/regs/corpuschristi-tx/doc-viewer.aspx#secid-1566
City of Corpus Christi, Ordinance No. 033894 as attached to the Council item (PDF)
https://legistar.granicus.com/CorpusChristi/attachments/ec7f128b-acbb-4b78-a404-ca8ec10fb9de.pdf
Corpus Christi Code of Ordinances, Chapter 14, Article XIII (development service fees)
https://library.municode.com/tx/corpus_christi/codes/code_of_ordinances?nodeId=PTIIITHCOOR_CH14DESE_ARTXIIIDESEFE
City of Corpus Christi, FY 2026 Development Fee Schedule (PDF)
https://www.corpuschristitx.gov/media/c5dka34k/fy-2026-development-fee-schedule.pdf
City of Corpus Christi, Fee Schedules page
https://www.corpuschristitx.gov/department-directory/development-services/fee-schedules/
City of Corpus Christi, Platting (Land Development) page
https://www.corpuschristitx.gov/department-directory/development-services/platting-land-development/
City of Corpus Christi, Informational Bulletin 001, UDC amendment process, 2026 cycle (PDF)
https://www.corpuschristitx.gov/media/c22f4552/ibs-001-udc-text-amendments-code-cycle-2026.pdf
Local Government Code 212.009 (plat approval deadlines)
https://statutes.capitol.texas.gov/Docs/LG/htm/LG.212.htm#212.009
Local Government Code 212.015 (residential replats)
https://statutes.capitol.texas.gov/Docs/LG/htm/LG.212.htm#212.015
Local Government Code 214.904 (building permit deadlines)
https://statutes.capitol.texas.gov/Docs/LG/htm/LG.214.htm#214.904
General information, not legal advice. Texas has no statewide zoning code. Each city writes its own rules, and deed restrictions recorded on a lot can forbid what the city allows. Confirm current requirements with the city planning department, read the deed restrictions for your lot, and talk to a Texas-licensed attorney or architect before you buy land or file plans.