Mesquite | Plats, Permits and Fees

Mesquite Plats, Permits, Impact Fees and Development Fees

A plat is the recorded map that creates legal lots. In Mesquite, a building permit in a subdivision needs an approved plat first. This page covers the plat steps in the Subdivision Ordinance, the replat rules when lots get smaller, park land, impact fees, and the fee schedule the City Council updated through Ordinance No. 5274, in force since October 1, 2026. The Mesquite overview gives the short version.

Mesquite plats and fees in six facts

How a Plat Moves Through the City

Article III of the Subdivision Ordinance, rewritten by Ordinance No. 5082 in November 2023, follows the state plat rules in Local Government Code chapter 212. The steps:

  • Before filing. A self-survey and a pre-application meeting are recommended, and the meeting "does not constitute the filing of an application." The meeting costs $150, with no charge for an infill single-family lot.
  • Filing. An application must include everything on the City's Plat Checklist and the fee. It counts as submitted when entered on the City's Online Application Portal "before 3 p.m. on a business day."
  • Who decides. "The Director shall review and make a decision on all plats except for those requiring a public hearing," and the Planning and Zoning Commission decides those.
  • The 30-day rule. "The Director or Commission shall make a decision within 30 days after the date the application is considered officially filed," and "A plat is approved by the City unless it is disapproved within the 30-day time period."
  • Conditions and denials. Each condition or reason must cite the law behind it, and staff sends it in writing by the end of the next business day. The applicant may answer with a Response Review Application, which the City must decide within 15 days; a response that meets every condition or reason is deemed approved if the City does not disapprove it in time.
  • Extensions. The 30 days may be extended in periods of up to 30 days by written agreement, and "The City may not request or require an applicant to waive a deadline."

Art. III(J)(2) makes the plat a condition of the permit: "no building permit may be issued for any building, structure, or improvement located within a subdivision" until the plat is approved, required land is dedicated, and required improvements are provided for. The City "shall not extend or connect any street lighting, water service, or sanitary sewer service" to unplatted land. Residential accessory structures need no plat.

A plat may be approved with conditions such as building public improvements to the City's Engineering Design Manual, a flood study, engineering plans or a traffic impact analysis. Under Chapter 11, building in a floodplain needs a development permit, and the owner pays the review cost of any flood study, deposited before review starts (Sec. 11-148).

Replats and Amending Plats

A replat redraws lots on land already platted. Under Art. III(K), a replat is a residential replat "if any of the area proposed for replatting was limited to residential use for not more than two residential units per lot or any lot was deed restricted for same within the preceding five years." For residential replats, the City publishes notice before the 15th day before the hearing and mails notice to the owners in the original subdivision within 200 feet, postmarked at least 15 days before the meeting.

If the residential replat needs a variance and is protested by "the owners of at least 20 percent of the area of the lots or land immediately adjoining the area covered by the proposed replat and extending 200 feet from that area, but within the original subdivision," the Mesquite text requires "the affirmative vote of at least three-fourths of all members of the Commission." Local Government Code 212.015(c) sets the same 20 percent land test but requires three-fourths "of the members present." The two differ, and the statute controls. Both include streets and alleys in the land area. When a residential replat needs no variance, Section 212.015(f) has the City mail notice of the approval to owners within 200 feet in the original subdivision within 15 days after approval.

An amending plat is a simpler path for small fixes, decided by the Director with no notice. Under Art. III(M) it may, among other things, relocate lot lines between adjacent lots when all owners join and the number of lots does not rise, or "create six or fewer lots" in a residential improvement area if zoning is not affected and no covenants are removed. Every amending plat must carry the note "This plat does not increase the number of lots in the previously recorded subdivision nor attempt to alter or remove existing deed restrictions or covenants, if any, on this property." A subdivision variance goes to the Commission, which must find special conditions on the land, and the plat must follow within two years (Art. III(O)).

Park Land and Park Fees

Article VI applies to "all new residential or hotel/motel development." The land required is "one acre per 55 residential units, or portion thereof." The City Council decides whether the owner gives land, pays a fee in lieu, or both. The fee equals "the average value of land in the Park Service Area," taken from the certified tax roll of January 1 each year from "the applicable central appraisal district," applied to the land that would have been given. In Mesquite that is the Dallas or Kaufman County appraisal district, depending on the lot. So the fee changes each year and by area, and the code sets no single dollar figure.

  • A plat or replat that creates "four (4) or fewer new single-family or duplex residential lots" pays the fee, with no land option.
  • For houses and duplexes, "One-half of the required payment shall be made prior to the filing of the plat," and the rest is split evenly among the homes and paid with each building permit.
  • For apartments and hotels, the fee is due before building permits.
  • "A replat that does not increase the number of single-family or duplex residential lots" is exempt.
  • Fees not spent within 10 years after 95 percent of the certificates of occupancy are issued can be refunded on a written request made within one year.

Impact Fees

An impact fee is a one-time charge on new development to pay for the water, sewer and road capacity it uses. Mesquite sets them in Chapter 7.5 under Local Government Code chapter 395, based on its 2015 study as updated in 2022. Schedule 1 lists the maximum the City could charge, and Schedule 2 lists the lower "Collection Rates" it does charge:

Impact fee Unit Maximum (Schedule 1) Collected
Water Service unit (one 5/8-inch meter) $7,759.00 $3,879.50
Wastewater Service unit (one 5/8-inch meter) $5,809.00 $2,904.50
Roadway, single-family detached Dwelling unit $6,582 (north) to $5,346 (south) $3,108
Roadway, condominium or townhome Dwelling unit $3,423 to $2,780 $1,616
Roadway, apartment or multifamily Dwelling unit $4,081 to $3,315 $1,927

Source: Mesquite Code of Ordinances on municode, Supplement 71, Chapter 7.5, Schedules 1 and 2 and Tables 1 and 2 (2022 update).

A 5/8-inch meter is one service unit; a 1-inch meter is 2.5 units. Table 2 sets the roadway fee by land use, with a different maximum in each of three service areas but one collected rate for all of them. By VanPlex arithmetic, a new house with a 5/8-inch meter pays $3,879.50, $2,904.50 and $3,108, or $9,892 in all. Table 2 has no duplex row; ask the City which roadway category it applies to a duplex.

Timing follows Sec. 7.5-9. For land platted after the fees began, the maximum fee is fixed at final plat approval; for unplatted land, at the building permit or utility connection. "No impact fees shall be assessed for development on any lot governed by an approved final plat for single-family residential development filed prior to the initial adoption of impact fees on March 1, 1997." The City's Impact Fees page says "impact fees are assessed and invoiced with the Building Permit." In January 2026 the Council hired Kimley-Horn and Associates to prepare a Roadway Impact Fee Study Update for $164,000; no new roadway rates had been adopted by October 5, 2026.

Fees in Force Since October 1, 2026

The fee schedule is Appendix D of the City Code. The codified text on municode is older than the current fees: on September 21, 2026, the Council passed Ordinance No. 5274, with the fees in its Exhibit A in force from October 1, 2026, and it also reauthorized "any building permit fees and all other fees" under Local Government Code 214.908, which ends a building permit fee 10 years after adoption unless the Council holds a hearing and votes again. The signed ordinance shows each change with old amounts struck out; the figures below are the new ones.

Item Fee Sec.
Pre-application meeting $150; no charge for an infill single-family lot 12-162
Plat or replat $600 up to one acre, plus $25 per added acre 12-169
Single-family infill plat $300 12-169
Amending plat $500 for 5 acres or more; $300 under 5 acres 12-169
Subdivision variance $500 12-169
County recording $250 12-170
Site plan $1,000 staff approval; $1,250 Commission or Council approval; $500 revised 12-168
Building permit, house, duplex, townhouse or condominium $1,100 per unit 12-100
Building permit, single-family infill development $950 12-100
Building permit, apartment $450 per unit 12-100
Plan review 25% of the building permit fee (residential); 30% (commercial or multifamily) 12-111
Electrical, plumbing or mechanical permit, residential $75 each 12-104 to 12-106
Certificate of occupancy $150 12-112
Engineering plan review, first review $750 up to one acre, plus $50 per added acre; $300 for an owner-occupied or non-profit infill house 14-101
Engineering inspection $1,500 base fee, plus amounts by type of work 14-103
Utility availability letter $200 14-102

Source: City of Mesquite Ordinance No. 5274, Exhibit A, Appendix D, Articles XII and XIV, signed copy in the City Secretary's archive.

The building permit section also lists an emergency notification fee of $100, an emergency services fee of $1,000 and a technology fee of $200, without saying which permits they attach to; ask the Building Inspection Division before you budget. The schedule uses "infill" for a lower building permit ($950), plat fee ($300) and engineering review ($300) but does not define the word, so confirm in writing whether your lot qualifies. A new Sec. 12-173 lets the City charge the cost of an outside consultant's review in addition to any application fee.

Two monthly charges follow the homes once built. The drainage utility charge is $6.00 per month for each single-family home (Appendix D, Sec. 4-100, under Sec. 11-42). And where the land is in a public improvement district, or PID, owners pay yearly assessments for the improvements; under Sec. 11-913 a homebuilder there must disclose the PID on any MLS® listing and show the assessment in price brochures.

Best For

  • ✓ A replat that keeps the number of lots, which avoids park fees and fits the amending plat path.
  • ✓ A platted lot from before March 1, 1997, which owes no impact fees.
  • ✓ A builder who files a complete plat on the portal and holds the City to the 30-day decision.

Usually Fails When

  • ✕ The budget leaves out park fees, impact fees and the $1,100 per unit permit.
  • ✕ A replat that needs a variance meets a 20 percent protest and lacks the votes.
  • ✕ Work starts in a floodplain before the development permit issues.

What To Verify Before Spending Money

  • → The current park fee for your park service area, from the Planning Division.
  • → Which roadway impact fee category the City uses for your building type.
  • → Whether your lot counts as infill for the lower fees.

Where to Go Next

Related on VanPlex: the Mesquite overview, Texas property tax and financing 2 to 4 units.

Frequently Asked Questions

How long does Mesquite take to approve a plat? +
Mesquite must approve, approve with conditions, or disapprove a plat within 30 days after it is officially filed, under Subdivision Ordinance Art. III(H)(3) and Local Government Code 212.009. A plat not disapproved in that time is approved. A response to conditions or a disapproval must be decided within 15 days. The 30-day period may be extended only by written agreement or for a takings study.
Who approves plats in Mesquite? +
In Mesquite, the Director of Planning and Development Services decides plats that need no public hearing, and the Planning and Zoning Commission decides plats that need one, such as residential replats with a variance, under Subdivision Ordinance Art. III(H)(1). An appeal of the Director's decision on an amending plat goes to the City Council.
How much does a plat cost in Mesquite? +
Under Mesquite Ordinance No. 5274, in force since October 1, 2026, a plat or replat costs $600 up to one acre plus $25 per added acre, up from $500. A single-family infill plat costs $300, an amending plat $300 under five acres, and a resubmittal within five days of a Commission meeting $500. The county recording fee is $250.
Can neighbors protest a replat in Mesquite? +
Yes, when a residential replat needs a variance. Owners of 20 percent of the land within 200 feet in the original subdivision can protest. The Mesquite text then asks for three-fourths of all Commission members, while Local Government Code 212.015 says three-fourths of the members present. Where the two differ, the statute controls. Both count land area, streets and alleys included.
What park fees apply to new homes in Mesquite? +
Mesquite Subdivision Ordinance Article VI asks for park land at one acre per 55 homes, or a fee in lieu of land equal to the average land value in the park service area times the land that would be dedicated. A plat that creates four or fewer new house or duplex lots must pay the fee. A replat that adds no lots is exempt.
When are park fees paid in Mesquite? +
For houses and duplexes, Mesquite collects half of the park fee before the plat is filed, and splits the other half evenly among the homes, paid as each building permit is issued, under Subdivision Ordinance Art. VI(F)(2). For apartments, the whole fee is due before the building permits. Unspent fees can be refunded on written request after 10 years.
What impact fees does Mesquite charge for a new house? +
Mesquite Chapter 7.5 collects $3,879.50 for water and $2,904.50 for wastewater per service unit, and a 5/8-inch meter counts as one unit. The roadway impact fee collected is $3,108 per single-family home in every service area. By VanPlex arithmetic, a house with a 5/8-inch meter owes $9,892 in impact fees. Lots in single-family plats filed before March 1, 1997 owe none.
When does Mesquite collect impact fees? +
The Mesquite Impact Fees page says impact fees are assessed and invoiced with the building permit. Under Sec. 7.5-9, the amount is fixed at final plat approval for land platted after the fee rules began, or at the building permit or utility connection for unplatted land, using the maximum rate then in effect. The collection rates in Schedule 2 are what the City charges.
How much is a building permit for a new house in Mesquite? +
Since October 1, 2026, Mesquite Ordinance No. 5274 sets the building permit for single-family homes, duplexes, townhouses and condominiums at $1,100 per unit, with residential plan review at 25 percent of the permit fee. Electrical, plumbing and mechanical permits are $75 each for residential work, and a certificate of occupancy is $150.
Does a Mesquite building permit need a plat first? +
Yes, for most new buildings. Mesquite Subdivision Ordinance Art. III(J)(2) says no building permit may be issued in a subdivision until a plat is approved, required land is dedicated and required improvements are provided for. A residential accessory structure needs no plat, and the City will not connect water or sewer to land until its plat is approved and recorded.
What must a Mesquite homebuilder disclose in a public improvement district? +
A public improvement district, or PID, finances improvements through assessments on the land. Under Mesquite Sec. 11-913, a homebuilder in a PID must disclose the PID on any MLS® listing, show the current annual and total assessment in any brochure with model prices, and include assessments in any estimate of monthly ownership costs for buyers.

Official sources (checked October 2026)

Mesquite Subdivision Ordinance, Art. III, platting review procedures (municode, Supplement 71)
https://library.municode.com/tx/mesquite/codes/code_of_ordinances?nodeId=PTIICOOR_APXBSU_ARTIIIPLREPR
Mesquite Subdivision Ordinance, Art. III(K), replats
https://library.municode.com/tx/mesquite/codes/code_of_ordinances?nodeId=PTIICOOR_APXBSU_ARTIIIPLREPR_KSUADREAPRE
Mesquite Subdivision Ordinance, Art. VI, conveyance of land for parks
https://library.municode.com/tx/mesquite/codes/code_of_ordinances?nodeId=PTIICOOR_APXBSU_ARTVICOLAPA
Mesquite Code of Ordinances, Chapter 7.5, impact fees
https://library.municode.com/tx/mesquite/codes/code_of_ordinances?nodeId=PTIICOOR_CH7.5IMFE
Mesquite Code of Ordinances, Sec. 7.5-9, assessment of impact fees
https://library.municode.com/tx/mesquite/codes/code_of_ordinances?nodeId=PTIICOOR_CH7.5IMFE_ARTIGEPR_S7.5-9ASIMFE
City of Mesquite, Impact Fees page
https://www.cityofmesquite.com/1707/Impact-Fees
City of Mesquite Ordinance No. 5274, fee schedule update in force October 1, 2026 (PDF)
https://apps.cityofmesquite.com/city_secweb/ordinances/5274.pdf
Mesquite Zoning Ordinance, Sec. 5.107, site plans
https://library.municode.com/tx/mesquite/codes/code_of_ordinances?nodeId=PTIICOOR_APXCZOOR_PT5AD_5.100REENPR_5.107SIPL
Mesquite Code of Ordinances, Chapter 11, Art. V, drainage and flood hazard areas
https://library.municode.com/tx/mesquite/codes/code_of_ordinances?nodeId=PTIICOOR_CH11PLDE_ARTVDRFLHAARRE
Mesquite City Council meeting calendar and records (Legistar)
https://mesquite.legistar.com/Calendar.aspx
Local Government Code 212.009 (plat approval deadlines)
https://statutes.capitol.texas.gov/Docs/LG/htm/LG.212.htm#212.009
Local Government Code 212.015 (residential replats)
https://statutes.capitol.texas.gov/Docs/LG/htm/LG.212.htm#212.015
Local Government Code chapter 395 (impact fees)
https://statutes.capitol.texas.gov/Docs/LG/htm/LG.395.htm
General information, not legal advice. Texas has no statewide zoning code. Each city writes its own rules, and deed restrictions recorded on a lot can forbid what the city allows. Confirm current requirements with the city planning department, read the deed restrictions for your lot, and talk to a Texas-licensed attorney or architect before you buy land or file plans.