David Babakaiff
Written by David Babakaiff · Co-Founder, VanPlex | 25+ Years BC Construction Last reviewed: October 2026

San Jose | Permits and Fees

San Jose Permits and Fees: Decision Makers, Deadlines, Construction Taxes and Park Fees

Before you build more homes in San Jose, you need the right approval and you pay a set of taxes and fees. This page reads who decides each permit and how fast, the review deadlines set by state law, the four construction taxes whose rates are written into the Municipal Code, and the park and inclusionary rules. Most other fee amounts, such as planning and map fees, are set by City Council resolution and are not printed in the code; this page names where each one is set. The California impact fees page covers the state rules.

San Jose permits and fees in six facts

  • San Jose does not treat a planning application as received until all fees are paid, and the Director has thirty calendar days to say whether it is complete. Source: SJMC 20.100.120, 20.100.150
  • An appeal of a San Jose permit decision must be filed within ten calendar days after the written decision is mailed; otherwise it is final on the eleventh day. Source: SJMC 20.100.240
  • The Residential Construction Tax is $122.10 per home and the Construction Tax $101.75 per home in a building of three or four homes, both due when the building permit is issued. Source: SJMC 4.54.050, 4.64.050
  • The Building and Structure Construction Tax on residential work is 1.75 percent of 88 percent of the valuation the building official sets. Source: SJMC 4.46.050
  • The Commercial-Residential-Mobilehome Park Building Tax on residential work is 2.75 percent of 88 percent of that same valuation. Source: SJMC 4.47.040
  • No impact fee may be charged on an ADU of 750 sq ft or less of interior livable space, or a junior ADU of 500 sq ft or less. Source: Gov. Code 66311.5(c)

Who Decides Each Permit

Chapter 20.100 says that, as a general rule, "any use which involves new construction" needs a development permit unless exempt. Table 20-260 in Section 20.100.220 names the first decision maker for each permit and the body that hears an appeal.

Permit First decision Appeal heard by
Administrative permit Director of Planning No appeal
Single-family house permit Director of Planning Planning Commission (Section 20.100.1080)
Site development permit Director of Planning Planning Commission
Planned development permit Director of Planning Planning Commission
Special use permit Director of Planning Planning Commission
Conditional use permit Planning Commission City Council
Variance or exception Director of Planning Planning Commission
Zoning code verification certificate Director of Planning No appeal

Source: San Jose Municipal Code Section 20.100.220, Table 20-260, and Section 20.100.1080, Supplement 5 Update 3.

Two notes under Table 20-260 move decisions to the City Council. The Council is the first decision maker "for a project that requires certification of an environmental impact report," unless the project includes every mitigation measure the draft report found necessary. It also hears appeals filed against both a permit and its environmental clearance.

Several housing approvals skip this table because they are ministerial, meaning staff check the plans against written rules with no hearing. These include ADUs under Part 2.75, SB 9 projects under Part 8, R-2 two-unit projects under Part 9, inventory properties under Part 9.5, and the approvals in Chapter 20.195. A State Streamlined Ministerial Approval expires after three years if construction has not begun, unless state law requires otherwise, and a Local Streamlined Ministerial Approval after four years, with "a one-time, one-year extension" available.

Filing, Completeness and Appeals

  • Filing. "No application shall be deemed received until" all fees in the Council's fee resolution are paid and all required documents are filed (Section 20.100.120). A check counts as paid only once it has cleared.
  • Completeness. "Not later than thirty calendar days after an application has been received, the director shall notify the applicant if the application is not complete," with a list of what is missing. The same thirty days runs after each resubmittal. If the Director misses it, the application "will be deemed complete."
  • Appeals. "A notice of appeal must be filed with the director of planning within ten calendar days" after the written decision is mailed. If none is filed "by 5:00 p.m. on the tenth day," the decision is final on the eleventh day. The notice must state the specific grounds.
  • House permits. An appeal of a single-family house permit goes to the Planning Commission within ten calendar days and may be filed by the applicant or an owner or tenant within three hundred feet.

Section 20.10.100 lets the Director charge a fee for each permit "as set forth in and in the manner described in a resolution adopted by the city council," and says the fee "shall not exceed the costs incurred by the city" in processing it. Map fees work the same way: Section 19.11.040 for ministerial tentative maps, and Sections 19.32.180 and 19.32.190 for parcel map checking and review, all refer to the Council's schedule of fees.

State Deadlines for Housing Approvals

State law sets the clock for the approvals most small projects use. Each runs from a complete application.

  • ADUs. Government Code 66317: approve or deny "within 60 days from the date the permitting agency receives a completed application if there is an existing single-family or multifamily dwelling on the lot."
  • SB 9 homes. Government Code 65852.21(h): 60 days, and "If the local agency has not approved or denied the completed application within 60 days, the application shall be deemed approved."
  • SB 9 lot splits. Government Code 66411.7: 60 days for the parcel map.
  • Small-lot maps. Government Code 66499.41: approve or deny a parcel map or tentative map "within 60 days from the date the local agency receives a completed application."
  • Historic Preservation Permits. The City's own Section 13.48.270 gives the Director sixty days. See the historic properties page.

The Four Construction Taxes

San Jose writes four taxes on new building into Title 4 of its code, each with its rate in the text. They are separate from planning fees. Chapter 4.47 says its tax "is in addition to the taxes imposed under Chapters 4.46, 4.54, and 4.64."

Tax One-family house Building of 3 or 4 homes Building of 5 to 19 homes
Building and Structure Construction Tax (Ch. 4.46) 1.75% of 88% of valuation 1.75% of 88% of valuation 1.75% of 88% of valuation
Commercial-Residential-Mobilehome Park Building Tax (Ch. 4.47) 2.75% of 88% of valuation 2.75% of 88% of valuation 2.75% of 88% of valuation
Construction Tax (Ch. 4.54), per home $150.00 $101.75 $82.50
Residential Construction Tax (Ch. 4.64), per home $180.00 $122.10 $99.00

Sources: San Jose Municipal Code 4.46.050, 4.47.040, 4.54.050 and 4.64.050. Each home in a two-family dwelling pays $114.00 (Chapter 4.54) and $136.80 (Chapter 4.64); each home in a building of 20 or more pays $75.00 and $90.00.

The two percentage taxes use a valuation set by the building official. Section 4.46.050 says the valuation comes from "the most current building valuation data table published by the International Code Council," using the "average" rate for "residential - multiple and one and two family, Type VB Construction." The rate "will be rounded to the nearest fifty-cent increment" and "The regional modifier will not be used." The current rate is not printed in the code. Together, the two percentage taxes come to 4.5 percent of 88 percent of the valuation, which is 3.96 percent of it.

All four are "due and payable at the time a building permit is issued." Chapters 4.46, 4.47 and 4.54 refund the tax if the permit expires or is revoked before construction. Section 4.64.060 lets the Residential Construction Tax be deferred until the City authorizes the electrical meter, if the builder posts a surety bond. Under Section 4.47.050, unpaid tax becomes delinquent with "a penalty in the sum of twenty percent." Per-home taxes for a fourplex come to $895.40 (4 times $101.75 plus $122.10), before the percentage taxes. Construction on a designated landmark under a Historic Preservation Permit is exempt from the Chapter 4.46 tax.

Section 4.46.039.13 suspends part of the Chapter 4.46 tax for "Qualified Multifamily Housing Incentive Program" projects, those eligible under Resolution No. RES2024-420 of December 10, 2024 as amended: 50 percent for "the first 3,600 residential units" that obtain a building permit by February 28, 2027, then 25 percent "of up to 8,743 additional residential units." A modified project must keep "a density of at least 50 DU/AC" to stay eligible.

Park Fees

San Jose charges for parks through two chapters. Chapter 19.38 applies to subdivisions: "Every residential subdivider shall dedicate land, pay a parkland fee in lieu of dedication, or both." The land is set by a formula: "Minimum acreage dedication = .003 acres × Number of dwelling units × Average number of persons per dwelling unit," using federal census household sizes. A fee paid instead of land is "based on the value of land in the City," and is paid before the map is approved, or under an agreement at the first building permit and no later than one year after map approval.

Chapter 14.25 covers "new residential units that are not subject to the requirements of Chapter 19.38," such as homes built without a subdivision. It rests on the policy of "at least three (3) acres of real property for each one thousand (1,000) persons," uses the same schedule of fees and credits, and says "no building permit for a residential unit subject to this chapter shall be issued unless and until the park impact fee has been paid." Low income and moderate income units pay too. The dollar amounts are in the Council's schedule of fees and credits, which was not among the documents opened for this page. Under state law, an ADU of 750 square feet or less is exempt from impact fees.

ADU, School and Inclusionary Charges

  • ADU impact fees. Government Code 66311.5(c) bars "any impact fee upon the development of an accessory dwelling unit that has 750 square feet of interior livable space or less or a junior accessory dwelling unit that has 500 square feet of interior livable space or less." Above 750 square feet, fees "shall be charged proportionately in relation to the square footage of the primary dwelling unit."
  • ADU utility fees. An ADU or junior ADU is not "a new residential use for purposes of calculating connection fees or capacity charges for utilities" unless built with a new single-family house.
  • School fees. The State Allocation Board raised the 2026 maximum Level I fee for residential construction to $5.38 per square foot. A district levies the Level I fee only after it "conducts a Justification Study" linking new development to school facility costs.
  • Inclusionary housing. Projects of 20 or more homes owe affordable units under Chapter 5.08, built on site or through the compliance options in Sections 5.08.510 to 5.08.590, which include an in-lieu fee. For most of those options, the requirement becomes "no less than twenty percent (20%) of the total of all units." See the three or more homes page.

Best For

  • ✓ ADUs of 750 sq ft or less, which owe no impact fees under state law.
  • ✓ Small projects decided by staff with state 60-day deadlines.
  • ✓ Large rental projects that qualify for the Multifamily Housing Incentive Program tax suspension.

Usually Fails When

  • ✕ An application is filed with unpaid fees, which San Jose does not treat as received.
  • ✕ An appeal is filed after 5:00 p.m. on the tenth day.
  • ✕ The building permit expires and the project restarts under a later fee schedule.

What To Verify Before Spending Money

  • → The current Council fee resolution for planning, map and park fees.
  • → The building official's current valuation rate for the two percentage taxes.
  • → The school district that serves your lot and its current fee.

Where to Go Next

Related on VanPlex: the San Jose overview, California impact fees and CEQA and permit streamlining.

Frequently Asked Questions

Who decides a site development permit in San Jose? +
The Director of Planning decides a San Jose site development permit, and the Planning Commission hears any appeal, under Table 20-260 in Municipal Code 20.100.220. The City Council becomes the first decision maker when the project needs a certified environmental impact report, unless the project includes every mitigation measure the draft report found necessary.
How long does San Jose have to tell me my application is incomplete? +
Thirty calendar days. San Jose Municipal Code 20.100.150 requires the Director to say within thirty calendar days of receiving an application whether it is complete, and to list what is missing. The same thirty days applies after each resubmittal. If the Director does not decide in time, the application is deemed complete and eligible for a hearing.
When do I pay San Jose construction taxes? +
When the building permit is issued. San Jose Municipal Code 4.46.070, 4.47.050, 4.54.070 and 4.64.060 make the Building and Structure Construction Tax, the Commercial-Residential-Mobilehome Park Building Tax, the Construction Tax and the Residential Construction Tax due at permit issuance. Chapters 4.46, 4.47 and 4.54 refund the tax if the permit expires or is revoked before construction.
How much are the San Jose per-unit construction taxes for a fourplex? +
For a building of three or four homes, San Jose charges a Construction Tax of $101.75 per home under Municipal Code 4.54.050 and a Residential Construction Tax of $122.10 per home under 4.64.050. For a fourplex that is $895.40 in total for the two taxes. The two percentage taxes on building valuation in Chapters 4.46 and 4.47 are added on top.
How does San Jose set the building valuation for construction taxes? +
The San Jose building official sets a residential valuation rate from the most current Building Valuation Data table of the International Code Council, using the average rate for Type VB residential construction, under Municipal Code 4.46.050. The rate is rounded to the nearest fifty cents, and the regional modifier is not used. The two percentage taxes apply to that valuation.
Is there a San Jose construction tax break for large apartment projects? +
Yes, for qualified projects. San Jose Municipal Code 4.46.039.13 suspends 50 percent of the Building and Structure Construction Tax for the first 3,600 homes in Qualified Multifamily Housing Incentive Program projects that get a building permit by February 28, 2027. From March 1, 2027, 25 percent is suspended for up to 8,743 more homes.
How is the San Jose park fee calculated for a subdivision? +
San Jose Municipal Code 19.38.310 sets the parkland dedication at 0.003 acres times the number of homes times the average number of persons per home from federal census data. When a fee is paid instead of land, 19.38.325 bases it on the value of land in San Jose, and the amounts are in the City Council schedule of fees and credits.
Do San Jose park fees apply to homes built without a subdivision map? +
Yes. San Jose Municipal Code Chapter 14.25 applies park impact requirements to new homes that are not covered by the subdivision parkland chapter, 19.38. Under 14.25.310, no building permit is issued until the park impact fee is paid or an exemption is shown. Low income and moderate income units also pay the fee under 14.25.500 and 14.25.510.
Do ADUs pay connection fees in San Jose? +
Usually not. Government Code 66311.5 says an ADU or junior ADU is not a new residential use for water and sewer connection fees or capacity charges unless it was built with a new single-family house. For an ADU or junior ADU inside the space of a house, no new separate utility connection or related fee may be required, with the same exception.
What school fee applies to new homes in San Jose in 2026? +
The State Allocation Board set the 2026 maximum Level I school fee at $5.38 per square foot of residential assessable space, in its January 28, 2026 item. A district may levy the Level I fee after a study links new homes to school facility costs. Under Government Code 66311.5, an ADU of less than 500 square feet counts as adding less than 500 square feet of assessable space.

Official sources (checked October 2026)

SJMC Chapter 20.100, administration and permits (20.100.120 to 20.100.240, Table 20-260)
https://library.municode.com/ca/san_jose/codes/code_of_ordinances?nodeId=TIT20ZO_CH20.100ADPE
SJMC Chapter 20.195, ministerial approvals (20.195.220, 20.195.330)
https://library.municode.com/ca/san_jose/codes/code_of_ordinances?nodeId=TIT20ZO_CH20.195MIAP
SJMC Chapter 20.10, Section 20.10.100, fees
https://library.municode.com/ca/san_jose/codes/code_of_ordinances?nodeId=TIT20ZO_CH20.10GEPRZODI
SJMC Chapter 4.46, Building and Structure Construction Tax
https://library.municode.com/ca/san_jose/codes/code_of_ordinances?nodeId=TIT4REFIBUTA_CH4.46BUSTCOTA
SJMC Chapter 4.47, Commercial-Residential-Mobilehome Park Building Tax
https://library.municode.com/ca/san_jose/codes/code_of_ordinances?nodeId=TIT4REFIBUTA_CH4.47COSIBIPABUTA
SJMC Chapter 4.54, Construction Tax
https://library.municode.com/ca/san_jose/codes/code_of_ordinances?nodeId=TIT4REFIBUTA_CH4.54COTA
SJMC Chapter 4.64, Residential Construction Tax
https://library.municode.com/ca/san_jose/codes/code_of_ordinances?nodeId=TIT4REFIBUTA_CH4.64RECOTA
SJMC Chapter 14.25, park impact requirements
https://library.municode.com/ca/san_jose/codes/code_of_ordinances?nodeId=TIT14PUWOIM_CH14.25PAIMRE
SJMC Chapter 19.38, parkland dedication
https://library.municode.com/ca/san_jose/codes/code_of_ordinances?nodeId=TIT19SU_CH19.38PADE
SJMC Chapter 19.32, improvements and fees
https://library.municode.com/ca/san_jose/codes/code_of_ordinances?nodeId=TIT19SU_CH19.32IMFE
SJMC Chapter 5.08, inclusionary housing
https://library.municode.com/ca/san_jose/codes/code_of_ordinances?nodeId=TIT5HO_CH5.08INHO
Government Code 66311.5 (ADU fees)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66311.5
Government Code 66317 (ADU application deadlines)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66317
Government Code 65852.21 (SB 9 two-unit projects)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=65852.21
Government Code 66499.41 (SB 684 and SB 1123 maps)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66499.41
State Allocation Board, 2026 school fee adjustment (January 28, 2026, PDF)
https://www.dgs.ca.gov/-/media/Divisions/OPSC/Resources/CCI-Adjustments/01282026_Index-Adjustment-on-Development_Approved_FINAL.pdf
VanPlex newsletter

Get new guides by email

New VanPlex guides and articles on multiplex rules, building costs and permits, sent to your inbox.

General information, not legal advice. California housing law changes every year, and each city adds its own rules on top of state law. Confirm current requirements with the city or county planning department, and with a California-licensed attorney or architect, before you buy land or file plans.

Planning a multiplex in San Jose?

VanPlex builds multiplexes in British Columbia, Canada. For a lot in San Jose, our team makes a custom proforma by hand and emails it to you in 24 to 48 hours.

Get a proforma for your address