Plano | Plats, Permits and Fees

Plano Plats, Permits and Fees: Plat Types, Deadlines and What the City Charges

A Plano project passes through up to three City reviews. The plat is the recorded map that divides land into lots, governed by the Subdivision Ordinance. Site plan review, under Article 3 of the Zoning Ordinance, applies to apartments, townhomes, patio homes and small lot subdivisions. The building permit comes last. This page gives the steps, the deadlines in City code and state law, and the fees, from the ordinances that set them. The Plano overview has the summary.

Plano plats and fees in six facts

When a Plat Is Needed

Sec. 16-131 of the Code of Ordinances adopts the Subdivision Ordinance "the same as if copied verbatim herein" and says all land in the City's limits or legal jurisdiction "shall be developed in accordance with the subdivision ordinance." It is unlawful to subdivide or plat land, or to sell lots, that "has not been platted or subdivided in accordance with the subdivision ordinance." The current Subdivision Ordinance PDF is dated September 1, 2025, and its latest changes came from Ordinance No. 2025-8-14, which followed the 2025 state laws.

Sec. 3.1A sorts plats into two classes:

  • Minor subdivisions "create no more than four lots and do not require the creation of a new street or the extension of municipal facilities." The Director of Planning may approve them or refer them to the Planning and Zoning Commission. They need a final plat or a conveyance plat.
  • Major subdivisions "involve the creation of new streets, the extension of municipal facilities, or the creation of more than four lots." They usually take two steps, a preliminary plat and a final plat.

A preliminary plat must be approved before public improvements, such as streets and water lines, are built. The step may be skipped if the owner signs a subdivision improvement agreement with enough surety, a bond or deposit that pays for the work if the owner does not finish it. "Lots may be sold and building permits obtained after approval of the plat by the Approval Authority, and filing of the signed plat."

Studies Before the Preliminary Plat

Sec. 3.1B, added by Ordinance No. 2025-8-14, requires site review and engineering studies before a preliminary plat "to evaluate the impacts of the proposed development on the public infrastructure system": drainage plans, flood studies, water and sewer plans, traffic studies, and a water and sewer capacity study. In the capacity study, the City checks whether the project needs larger or offsite pipes. If the applicant will not provide the mitigation the study calls for, the plan "will be denied," and that result may not be appealed or varied. An approved study reserves the project's water and sewer demand for as long as the project is vested under Local Government Code chapter 245, which has a city judge a permit by the rules "in effect at the time" the original application, plan or plat was filed.

A pre-application meeting with planning and engineering staff is offered before a preliminary plat (Subdivision Ordinance Sec. 3.2) and required before a site plan application (Zoning Ordinance Sec. 3.100.5). The City's Plan and Plat Checklists page links the request form and the checklists each application must include.

The 30-Day Clock

Sec. 3.1A.b requires the Planning Department to publish, at least 30 days before each year, a calendar of official submittal dates, generally two a month and at least one. An application is submitted on the first submittal date after the fee is paid, the other legal requirements are met, and the plat is delivered or mailed by certified mail. That date "shall constitute the filing date."

  • The approval authority must approve, conditionally approve or disapprove within 30 calendar days of the official submission date; if it does not act, "the application shall be deemed approved."
  • A conditional approval or disapproval must list each requirement, "with citation to the appropriate regulation or law."
  • A resubmittal must be decided within 15 calendar days, or it is deemed approved.
  • The review period may be extended up to 30 days, but only on the applicant's written request.
  • A withdrawn application may be resubmitted with no new fee if it is rescheduled within 60 days.

These steps match Local Government Code 212.009, which says a plat "is approved by the municipal authority unless it is disapproved within that period."

Replats and Amending Plats

A replat changes an approved final plat, and under Sec. 7.1 it follows the same standards and steps as a new plat. Section 7.1.c adds a hearing for some residential replats: where, in the preceding five years, any of the area was limited by zoning to "not more than two (2) residential units per lot," or a lot in the earlier plat was limited that way by deed restrictions. Notice is published before the 15th day before the hearing and mailed to owners in the original subdivision within 200 feet. If the replat needs a variance and owners of 20 percent of the notified area protest, approval needs "three-fourths (3/4) of the Commission members present."

The City text and state law differ on when the hearing is held. Sec. 7.1.c.2 says final action "may be taken only after a public hearing" for every such replat. Local Government Code 212.015(a-1) requires the hearing only "if a proposed replat described by Subsection (a) requires a variance or exception." State law controls where the two conflict, so ask the Planning Department whether your replat, with no variance, will be set for a hearing.

Two shorter routes exist. Under Sec. 7.2, the Director of Planning may approve an amending plat, with no notice or hearing, to fix errors, cure a building that crosses a lot line, or move lot lines between adjacent lots when all owners join and no lot is added. And under Sec. 7.1.d, a building setback line on a recorded plat can be removed without a replat if the Board of Adjustment grants a yard variance and the owner records it.

Planning and Engineering Fees

Fees are set in Sec. 16-19 of the Code of Ordinances. Ordinance No. 2025-11-2 replaced the whole section from January 1, 2026, and Ordinance No. 2026-3-7 amended it again, adding a waiver for some government applicants and a new notice fee. The City's schedule, marked "Effective March 23, 2026," lists:

Item Fee
Pre-application meeting for zoning or development $350
Concept plan $1,050
Preliminary site plan $200 per acre
Site plan $200 per acre
Conveyance plat $750
Preliminary plat or preliminary replat $150 per acre
Final plat or replat $800
Minor plat $500
Amended plat $300
Vacation of plat $1,250
Plan or plat extension or reinstatement $400
Subdivision Ordinance variance $150 per variance
Engineering plan review $1,000 per original submission; $500 per resubmittal
Engineering inspection, grading, paving and sidewalks $0.65 per sq ft or $5.85 per sq yd, each
Engineering inspection, drainage, water and wastewater $2.00 per linear foot
Water and sewer study $10,000
Flood study $3,500
Traffic impact analysis (other than regional) $850
Landscape plan $750
Board of Adjustment request $550
Notice fee $200 per project plus $5 for each mailing

Source: City of Plano, Development Fees for Planning and Engineering Services, Ordinance No. 2026-3-7, "Effective March 23, 2026," read October 8, 2026. Fees by the acre or foot round up to the next whole unit.

The municode copy is older than these ordinances. Supplement 153 of the Code, which carries ordinances through October 2025, still prints the older Sec. 16-19, with a final plat at "$250.00 plus $5.00 per lot" and a preliminary plat at "$280.00 per acre." The later ordinances replaced that table and control.

Building Permit Fees

Ordinance No. 2025-11-4 repealed the 2020 Building Inspections fee schedule "in its entirety" and adopted a new one. The City posts it as the Building Inspections Fee Schedule effective January 2, 2026. The housing lines:

Permit Fee
New single-family residence $0.48 per sq ft under roof + $80 plan review + $75 plumbing certificate
Duplex $0.48 per sq ft + $90 plan review + $150 plumbing certificate
Multi-family residential $0.65 per sq ft + $90 plan review, plus trade inspections by floor area
Addition, alteration or backyard cottage $0.48 per sq ft ($40 minimum) + $45 plan review + $0.01 per sq ft per trade ($45 minimum each)
Plan review deposit 65 percent of the building permit fee, applied to the total and not refundable
Re-inspections $75 first, $100 second, $125 third, $150 after that

Source: Exhibit "A" to Ordinance No. 2025-11-4, City of Plano Building Inspections Department Fee Schedule.

The City's Residential Permits page still links an older "Building Inspections Fee Schedule," Exhibit A to Ordinance No. 2020-3-6, with first re-inspections at $50. The 2025 ordinance repealed it, so use the 2025 figures. State law sets the permit clock: Local Government Code 214.904 gives a city 45 days to grant or deny a permit, give written reasons it cannot yet decide, or agree on a deadline, and a city that misses the deadline "may not collect any permit fees associated with the application."

Park Fee, and No Impact Fees

Chapter 16, Article XII imposes a park fee "on all residential development" to pay for neighborhood and linear parks. Sec. 16-266, last amended by Ordinance No. 2025-7-11 on July 28, 2025, sets $5,691 for each single-family home and $4,359 for each multi-family home, across 14 park service areas. The fee is collected before the building permit at the rate in effect when the permit application was filed. It does not apply to remodeling, rebuilding a damaged structure, or "permits required for backyard cottages or accessory uses."

An impact fee is a one-time charge on new building that pays for added public water, sewer or road capacity, under Local Government Code chapter 395. Plano has none in its code for water or wastewater. The editor's note to Chapter 21, Article VI says Ordinance No. 2009-8-23, adopted August 24, 2009, repealed the former Article VI "in its entirety, which pertained to impact fees." One cross-reference was left behind: Sec. 21-181 still refers to crediting deposits "against impact fees due for water or wastewater facilities in the manner prescribed in Article VI of this chapter," an article that is now reserved. Chapter 21, Article V, covers pro rata fees and the extension of water and wastewater mains.

Site Plan Review

Article 3 of the Zoning Ordinance sets three plans: a concept plan, a preliminary site plan and a site plan. "Concept plans and preliminary site plans require review and approval by the Planning & Zoning Commission. Site plans may be approved by city staff provided that they conform to preliminary plans." Site plan review applies to planned developments, nonresidential and multifamily development, patio home and townhome projects, RCD and NBD residential development, mobile home parks, parking lots of more than 20 spaces, and Single-Family Small Lot subdivisions. A detached house or a duplex on an existing platted lot is not on that list.

Best For

  • ✓ A split into four lots or fewer on an existing street, which the Director of Planning can approve as a minor plat.
  • ✓ A lot line move between two neighbors, done as a $300 amending plat with no hearing.
  • ✓ A backyard cottage, which pays building permit fees and no park fee.

Usually Fails When

  • ✕ The budget leaves out the $5,691 park fee for each new house, due before the permit.
  • ✕ The schedule ignores the water and sewer capacity study the City requires before a preliminary plat.
  • ✕ The applicant relies on the old municode fee table instead of the 2026 schedule.

What To Verify Before Spending Money

  • → This year's submittal calendar from the Planning Department.
  • → Whether your replat will be set for a hearing.
  • → The current fee schedules, which the City Council changed in November 2025 and March 2026.

Where to Go Next

Related on VanPlex: the Plano overview, Texas property tax and how Texas zoning works.

Frequently Asked Questions

Do I need a plat to build in Plano? +
Yes, if the land is not already platted or is being divided. Plano Code Sec. 16-131 makes it "unlawful for any owner or agent of any owner to subdivide or plat any land" or to sell lots that were not platted under the Subdivision Ordinance. Under Sec. 3.1A of that ordinance, lots may be sold and building permits obtained after the plat is approved and the signed plat is filed.
What is a minor plat in Plano? +
A minor plat in Plano covers a minor subdivision, which under Subdivision Ordinance Sec. 3.1A creates no more than four lots and needs no new street and no extension of City facilities. The Director of Planning may approve it or refer it to the Planning and Zoning Commission. Since March 23, 2026, a minor plat costs $500.
How long does Plano have to approve a plat? +
Plano's Subdivision Ordinance Sec. 3.1A.d gives the approval authority 30 calendar days after the official submission date to approve, conditionally approve or disapprove a plat, or the plat is deemed approved. After a conditional approval or disapproval, a resubmittal must be decided within 15 days. This matches Local Government Code 212.009.
When can I submit a plat in Plano? +
Plano's Planning Department publishes a calendar of official submittal dates at least 30 days before each year, usually two dates a month and at least one, under Subdivision Ordinance Sec. 3.1A.b. A plat counts as submitted on the first submittal date after the fee is paid, the other requirements are met, and the plat is delivered or sent by certified mail.
Does a replat in Plano need a public hearing? +
Plano Subdivision Ordinance Sec. 7.1.c calls for a Planning and Zoning Commission hearing on a replat of land limited, in the past five years, to two homes per lot by zoning or deed restrictions, with notice to owners within 200 feet. Local Government Code 212.015(a-1) requires that hearing only when the replat needs a variance or exception. The statute controls.
Can I fix a lot line in Plano without a full replat? +
Often, yes. Plano's Director of Planning may approve an amending plat under Subdivision Ordinance Sec. 7.2 to correct errors, cure a building encroachment, or move lot lines between adjacent lots when all owners join and no lot is added. No notice or hearing is needed. Since March 23, 2026, an amended plat costs $300.
How much is the building permit for a new house in Plano? +
Under Plano's Building Inspections fee schedule adopted by Ordinance No. 2025-11-4, a new single-family residence pays $0.48 per square foot under roof, plus an $80 plan review fee and a $75 plumbing certificate. By VanPlex arithmetic, a 2,500 square foot house pays $1,200 plus $155, or $1,355, for those three items.
Does Plano charge impact fees? +
Plano's Code of Ordinances has no water or wastewater impact fee article. The editor's note to Chapter 21, Article VI says Ordinance No. 2009-8-23, adopted August 24, 2009, repealed the former article, "which pertained to impact fees." Plano does charge a park fee of $5,691 per new single-family home and $4,359 per new multi-family home.
When is the Plano park fee paid? +
The Plano park fee is collected before the building permit is issued, under Code Sec. 16-267, at the rate in effect when the permit application was filed. The rate is $5,691 per single-family home and $4,359 per multi-family home. It does not apply to remodeling, rebuilding a damaged home, or permits for backyard cottages and accessory uses.
How long does Plano have to issue a building permit? +
Local Government Code 214.904 gives a Texas city 45 days after a permit application is submitted to grant or deny it, explain in writing why it cannot yet decide, or agree on a deadline. After a written notice, the city has 30 more days. A city that misses the deadline may not collect the permit fees and must refund any it collected.

Official sources (checked October 2026)

City of Plano, Subdivision Ordinance (PDF, September 1, 2025 edition)
https://content.civicplus.com/api/assets/2fed5546-e296-4a5a-ba0b-4482225e6d89
Plano Subdivision Ordinance, Article III (platting procedures)
https://content.civicplus.com/api/assets/2fed5546-e296-4a5a-ba0b-4482225e6d89#page=23
Plano Subdivision Ordinance, Article VII (replatting procedures)
https://content.civicplus.com/api/assets/2fed5546-e296-4a5a-ba0b-4482225e6d89#page=98
Plano Zoning Ordinance, Article 3 (site plan review)
https://content.civicplus.com/api/assets/fc707d33-03b6-4993-9a8a-9244962a2c91#page=21
Plano Code of Ordinances, Chapter 16, Article VII (subdivision ordinance adopted by reference)
https://library.municode.com/tx/plano/codes/code_of_ordinances?nodeId=PTIICOOR_CH16PLDE_ARTVIIPLDESULA
Plano Code of Ordinances, Chapter 16, Article II (development fees)
https://library.municode.com/tx/plano/codes/code_of_ordinances?nodeId=PTIICOOR_CH16PLDE_ARTIIFEGE
Plano Code of Ordinances, Chapter 16, Article XII (park fee)
https://library.municode.com/tx/plano/codes/code_of_ordinances?nodeId=PTIICOOR_CH16PLDE_ARTXIIPAREFE
Plano Code of Ordinances, Chapter 21, Article VI (impact fees, repealed)
https://library.municode.com/tx/plano/codes/code_of_ordinances?nodeId=PTIICOOR_CH21UT_ARTVIRE
City of Plano, Development Fees for Planning and Engineering, Ordinance No. 2026-3-7 (PDF)
https://content.civicplus.com/api/assets/ca315230-a1fe-43c3-84dc-52bbddc72476
City of Plano, November 2025 ordinances, including Nos. 2025-11-2 and 2025-11-4 (PDF)
https://content.civicplus.com/api/assets/83a41b67-3d2c-4bce-9c9e-aaa418449261
City of Plano, Building Inspections Fee Schedule, Ordinance No. 2025-11-4 (PDF)
https://content.civicplus.com/api/assets/465fd3b7-2f75-4bb6-9044-6a62da9fd3ba
City of Plano, Plan and Plat Checklists page
https://www.plano.gov/plan-and-plat-checklists
Local Government Code 212.009 (plat approval deadlines)
https://statutes.capitol.texas.gov/Docs/LG/htm/LG.212.htm#212.009
Local Government Code 212.015 (residential replats)
https://statutes.capitol.texas.gov/Docs/LG/htm/LG.212.htm#212.015
Local Government Code 214.904 (building permit deadlines)
https://statutes.capitol.texas.gov/Docs/LG/htm/LG.214.htm#214.904
General information, not legal advice. Texas has no statewide zoning code. Each city writes its own rules, and deed restrictions recorded on a lot can forbid what the city allows. Confirm current requirements with the city planning department, read the deed restrictions for your lot, and talk to a Texas-licensed attorney or architect before you buy land or file plans.