San Francisco Lot Size and Subdivisions: Minimum Lots, SB 9 and SB 684
Splitting a lot is how an owner turns one property into two or more that can be sold on their own. In San Francisco three rule sets decide it: the minimum lot size in Planning Code Section 121, the state's SB 9 and SB 684 laws as SF Planning applies them, and the map process run by San Francisco Public Works. This page covers all three, plus the City's paths for condominiums. The San Francisco overview has the wider picture.
San Francisco lots and subdivisions in six facts
- Ordinance No. 248-23 set the San Francisco minimum lot width at 20 feet and the minimum lot area at 1,200 square feet. Source: Ordinance No. 248-23, Section 121
- An SB 9 lot split in San Francisco needs an RH-1, RH-1(D) or RH-1(S) parcel of at least 2,400 square feet, with each new parcel at least 1,200 square feet. Source: SF Planning, Director Bulletin No. 8
- Public Works reviews every subdivision: a parcel map for four or fewer parcels and a final map for five or more. Source: SF Public Works, Parcel Map / Final Map application
- From July 1, 2026, a parcel map for new construction condominiums or a land subdivision of four or fewer units or lots costs $15,670, plus $50 per lot or unit. Source: SF Public Works, Mapping application fee schedule
- SB 684 maps in San Francisco may create up to 10 parcels, each at least 600 square feet in a multifamily zone. Source: SF Planning, Director Bulletin No. 8
- Since January 12, 2026, a housing project may not merge lots that hold certain historic buildings unless it keeps the historic building. Source: Ordinance No. 245-25, Section 121.7(e)
The Minimum Lot Since 2023
A minimum lot rule sets the smallest width and area a new lot may have. San Francisco's rule is Planning Code Section 121. Ordinance No. 248-23, the Housing Production ordinance finally passed by the Board of Supervisors on December 12, 2023, rewrote it. The page images of the ordinance show the new text in double underline: "The minimum lot width shall be 20 feet" and "The minimum lot area shall be 1,200 sq. ft." The district-by-district figures were struck out.
| Rule in Section 121 | Before Ordinance No. 248-23 | After |
|---|---|---|
| Minimum lot width | 33 ft in RH-1(D); 25 ft in all other districts | 20 ft |
| Minimum lot area | 4,000 sq ft in RH-1(D); 2,500 sq ft in other districts; 1,750 sq ft for a lot fronting within 125 ft of a street corner | 1,200 sq ft |
| Match the larger lots nearby | New lots had to match a larger prevailing lot pattern, up to 33 ft and 4,000 sq ft | Rule deleted |
| Narrower lots by Conditional Use | Lots of at least 1,500 sq ft with one home, by Planning Commission approval | Rule deleted |
Source: Ordinance No. 248-23, Section 121(b), (d), (e) and (f), pages 7 and 8, read on the page images.
Section 121(b) still sends every subdivision through the Subdivision Code and the state Subdivision Map Act, "including the requirement for consistency with the General Plan." Even with the 1,200 square foot minimum, an ordinary split goes through the Public Works map process below, with Planning and environmental review. The 1,200 figure matters most because it matches the SB 9 minimum, so an RH-1 lot of 2,400 square feet can produce two lots that meet both rules. By VanPlex arithmetic, a lot 25 feet wide (the width the code describes for RH-1 lots) and 100 feet deep (the depth ZA Bulletin No. 5 calls typical) has 2,500 square feet, which clears that line.
The older Section 121 also made a new lot match a larger "predominant pattern" nearby. That clause was struck too. Ordinance No. 248-23 at first kept the old figures inside the Family Housing Opportunity Special Use District, but the Board's final amendments struck those lines as well, which is why the table above shows one citywide figure.
Four Ways to Divide a Lot
| Path | Districts | Lots created | Who reviews |
|---|---|---|---|
| SB 9 urban lot split | RH-1, RH-1(D), RH-1(S) | 2 lots, each at least 1,200 sq ft and 40% to 60% of the original | Planning ministerial review; Public Works parcel map |
| SB 684 / SB 1123 | Multifamily zones; vacant single-family lots | Up to 10 lots, at least 600 sq ft (1,200 sq ft on a vacant single-family lot) | Planning ministerial review; Public Works map |
| Ordinary parcel map | Any district | 4 or fewer parcels, each meeting Section 121 | Public Works with Planning referral and a CEQA determination |
| Ordinary final map | Any district | 5 or more parcels or units | Public Works; goes to the Board of Supervisors |
Sources: SF Planning Director Bulletin No. 8; SF Public Works Parcel Map / Final Map application and mapping page.
SB 9 Lot Splits in RH-1 Districts
SB 9 lets an owner split one single-family lot into two with ministerial review, which means staff check fixed rules and there is no public hearing. SF Planning's Director Bulletin No. 8 sets out how San Francisco applies it. The parcel must be in an RH-1, RH-1(D) or RH-1(S) district. For a lot split, the bulletin adds these tests:
- Original parcel size. "Only parcels 2,400 square feet and larger are eligible for a ministerial lot split."
- Resulting parcel size. No new parcel may be more than 60 percent or less than 40 percent of the original, and "both newly created parcels must be at least 1,200 square feet."
- One split only. A parcel created by an earlier SB 9 split cannot be split again, and an owner who split an adjacent parcel under SB 9, alone or "acting in concert" with others, cannot split this one.
- Owner occupancy after the split. The applicant signs an affidavit to live in one unit "as their principal residence for a minimum of three years from the date of the approved lot split," unless the applicant is a community land trust or qualified nonprofit.
- Easements. A split may need easements for utilities and physical access, and those must meet fire and building safety code.
The general SB 9 tests also apply: the bulletin says the parcel "must be owner-occupied or vacant for three (3) years prior to the application," that parcels with units under local rent control are not eligible, that a unit withdrawn under the Ellis Act in the past 15 years makes the parcel ineligible, and that Article 10 and 11 historic properties and districts are excluded. Government Code 66411.7 words the occupancy test as housing "occupied by a tenant in the last three years," and the statute controls where the City's shorter phrase differs. SB 9 also "prohibits the correction of nonconforming zoning conditions as a condition for ministerial approval of a lot split," so the City cannot make an owner fix an older yard or height problem before splitting.
The order of filing is set by SF Planning's SB 9 page: for a lot split only, "Apply for a Parcel Map for a Lot Split with San Francisco Public Works," then send the SB 9 supplemental application to [email protected]. The same page says Planning will approve or comment "Within 60 days of submittal of a complete application." It also warns that new units often need their own electric and water meters, and that "a utilities easement may be needed," so it tells owners to contact PG&E and the SFPUC early. The homes that can go on each lot are on the ADUs and SB 9 page.
SB 684 and SB 1123 Small-Lot Maps
SB 684 (2023) and SB 1123 (2024) let an owner divide a lot into as many as 10 small lots with 10 homes, again with ministerial review. The full state rules are on the SB 684 and SB 1123 page. Director Bulletin No. 8 sets San Francisco's reading:
- Zoning. A parcel zoned for multifamily use, or a parcel "that is vacant and zoned for single-family residential development." Vacant means no permanent structure, unless the building is abandoned and uninhabitable as found by the Department of Building Inspection.
- Existing lot. No larger than five acres in a multifamily zone or one and one-half acres in a vacant single-family zone, surrounded on 75 percent of its edge by urban uses, and not created by an earlier SB 684 or SB 9 split.
- New lots. At least 600 square feet in multifamily zones and 1,200 square feet in vacant single-family zones, with 10 or fewer parcels and 10 or fewer units.
- Average size. The average home "does not exceed 1,750 net habitable square feet."
- Density. At least one new home on each parcel. For a site outside the Housing Element list, at least 66 percent of the maximum density the zoning allows.
- Existing homes. No demolition of rent-controlled or affordable units, units occupied by tenants in the past five years, or units withdrawn under the Ellis Act in the past 15 years.
The bulletin also notes that "State Law ADUs may be included and do not count toward the 10-unit maximum project size," and that SB 684 "does not provide an inherent right to construct 10 units if the underlying zoning and density calculations do not allow it, though the City cannot preclude developing at least 30 units per acre." By VanPlex arithmetic, an RM-1 lot of 8,000 square feet at one unit per 800 square feet allows 10 units, the SB 684 maximum.
Two dates matter here. Director Bulletin No. 8 says it was updated in September 2025, and it says that projects proposing 10 units must meet the City's Inclusionary Housing Ordinance. Ordinance No. 136-26, passed July 21, 2026 and listed by SF Planning as effective August 22, 2026, says in its title that it deletes "Inclusionary Affordable Housing Program requirements for projects under 25 units." The later ordinance controls, so ask SF Planning which inclusionary rule applies to a 10-unit map filed now. Government Code 66499.41 itself was amended again by Chapter 1006 of the Statutes of 2026 (SB 1090), effective September 30, 2026, with a further version operative January 1, 2027; the bulletin predates both.
The Public Works Map Process
San Francisco Public Works' Bureau of Surveying and Mapping "processes and reviews all subdivision projects that occur in San Francisco, including all condominium conversions." Its Parcel Map / Final Map application (dated July 30, 2026) sorts maps in two groups: a parcel map for "four or fewer parcels" and a final map for "five or more parcels." The steps it lists before filing are:
- retain "a California licensed land surveyor or a civil engineer who was licensed before 1982" to prepare the map;
- obtain a current 3R Report, a records report issued by the Department of Building Inspection, for each residential property;
- confirm all application items are current, since applications that are not complete "will be rejected";
- prepare the public notice mailing to the owner and to property owners "within a 300-foot radius," using Public Works return envelopes.
After Public Works finds the application complete, "it refers the application to the City Planning Department," which checks the General Plan, Planning Code Section 101.1 and the rest of the Planning Code. The application says the City "is prohibited from issuing tentative map approval without a California Environmental Quality Act (CEQA) determination." CEQA is the state law on environmental review. Public Works then sends a letter of approval, conditional approval or disapproval of the tentative map. Those owners or "any interested party" may appeal the decision to the Board of Supervisors "within 10 days of the date of the decision." All applications go in electronically, and Public Works says every project needs one point of contact, the project surveyor.
| Application | Total fee from July 1, 2026 |
|---|---|
| Parcel map, condominium conversion of 4 units or less | $16,811 |
| Parcel map, new construction condominiums and land subdivisions of 4 units or lots or less | $15,670 |
| Final map, all subdivisions of 5 units or lots or more | $17,015 |
| Lot line adjustment | $5,454 |
| Certificate of compliance | $4,314 |
| Pre-application meeting | $291 per hour |
| Department of Building Inspection review fee | $1,356 |
Map fees include a $1,000 processing fee and add $50 per land lot or condominium unit. Public Works calls them "minimum base fees" and may add time and materials. Source: SF Public Works, Mapping Application Fee Schedule, effective July 1, 2026.
The fee schedule's own example: a 10-unit new construction condominium map costs $17,015 plus 10 times $50, or $17,515. Recording a map adds a state fee of $75 for each new parcel number, capped at $225 per document. The mapping web page says resubmittals carry "an additional $250.00 administrative fee," while the July 2026 fee schedule and application both say $295. The fee schedule is the later adopted figure.
Lot Mergers and Historic Buildings
Combining lots can make a larger building possible. Public Works says "A Merger of four or fewer lots can be done by Lot Line Adjustment Application." The Family Zoning Plan added a limit in Planning Code Section 121.7(e): for a housing development project, "Lot Mergers are not permitted, unless the Project maintains the Historic Building in compliance with the Preservation Design Standards and modified standards under Section 206.10(d) for the life of the project, and the requirement is recorded in a Notice of Special Restrictions." A Notice of Special Restrictions is a document recorded on the title that binds later owners. The demolition and historic buildings page explains what counts as a historic building in San Francisco.
Condominium Paths Without a Lot Split
A condominium lets each unit be sold separately while the land stays shared. San Francisco has three paths that matter for small projects. First, the four-unit density exception: SF Planning's summary says a project that uses it to add units to an existing single-family home "may apply to form condos through the new construction pathway" if the owner signs an affidavit to live in one unit for three years after the Certificate of Final Completion and Occupancy. Second, SB 9 without a split: Director Bulletin No. 8 says the two units "could be sold as condominiums at project completion."
Third, ADUs. Ordinance No. 113-25, effective August 10, 2025, allows one State Program ADU per lot to be sold as a condominium when the lot holds four or fewer units, the ADU application was submitted on or after May 1, 2025, and the ADU is not a junior ADU. On a lot with an existing single-family home, only a detached ADU qualifies; with a new home, a detached or attached ADU qualifies. A safety inspection by a certified building inspector is needed before the condominium plan is recorded. Older buildings converting to condominiums follow a separate Public Works process: its page lists the Expedited Conversion Program for 2 to 6 units as "SUSPENDED."
Best For
- ✓ An RH-1 lot of 2,400 sq ft or more with no tenants in the past three years, using an SB 9 split.
- ✓ A vacant single-family lot or a multifamily lot where an SB 684 map of up to 10 lots fits the density.
- ✓ An owner who wants separate sale without a split, through the four-unit, SB 9 or ADU condominium paths.
Usually Fails When
- ✕ The house had a tenant, a rent-controlled unit or an Ellis Act withdrawal in the look-back period.
- ✕ The lot is an Article 10 or 11 historic property, which SB 9 excludes.
- ✕ A merger of lots would remove a historic building that Section 121.7(e) protects.
What To Verify Before Spending Money
- → Lot area and width from the Assessor block map before paying a surveyor.
- → The current Public Works fee schedule and application version.
- → Which inclusionary rule SF Planning applies after Ordinance No. 136-26.
Where to Go Next
Related on VanPlex: the San Francisco overview, SB 9 in California and SB 684 and SB 1123.
Frequently Asked Questions
What is the minimum lot size in San Francisco?
Can I split my lot under SB 9 in San Francisco?
Who approves a lot split in San Francisco, Planning or Public Works?
How much does a parcel map cost in San Francisco?
Can I use SB 684 to build 10 homes on a San Francisco lot?
What is the average unit size limit for SB 684 in San Francisco?
Can I merge two lots in San Francisco to build housing?
Can an ADU be sold as a condominium in San Francisco?
Can the four-unit exception homes become condominiums in San Francisco?
Do I need a land surveyor to subdivide a San Francisco lot?
Official sources (checked October 2026)
Get new guides by email
New VanPlex guides and articles on multiplex rules, building costs and permits, sent to your inbox.
Planning a multiplex in San Francisco?
VanPlex builds multiplexes in British Columbia, Canada. For a lot in San Francisco, our team makes a custom proforma by hand and emails it to you in 24 to 48 hours.
Get a proforma for your address