San Francisco | Permits and Fees
San Francisco Permits and Fees: Review Steps, Deadlines and Fee Tables
Three City departments handle a small housing project in San Francisco. The Planning Department checks zoning and runs approvals and hearings, Public Works handles lot splits and condominium maps, and the Department of Building Inspection (DBI) issues building permits and collects impact fees. This page sets out the order of steps, the review deadlines and the fees each department charges, from the schedules in force in October 2026.
San Francisco permits and fees in six facts
- SF Planning calculates its development application fee from the estimated construction cost, and full payment is required for an application to be complete. Source: SF Planning, Fee Schedule for Applications
- Under the FY 2026-27 schedule effective August 31, 2026, the Planning fee for new construction under $100,000 is $3,589, and a demolition permit is $2,373. Source: SF Planning, Fee Schedule FY 2026-27 notice
- The Department of Building Inspection charges $526 an hour for plan review and $519 an hour for inspection, effective July 12, 2026. Source: DBI, Table 1A-D, Standard Hourly Rates
- Section 311 notice starts a 30-day period for neighbors to review and comment on a permit in RH and RM districts. Source: SF Planning, ZA Bulletin No. 4
- SF Planning must approve or comment on an SB 9 application within 60 days of a complete application, and State ADUs get a 60-day review. Source: SF Planning, SB 9 page and Director Bulletin No. 3
- Development impact fees in San Francisco are collected by the Department of Building Inspection and adjusted each January. Source: SF Planning, Fee Schedule FY 2026-27 notice
Who Does What, in Order
| Step | Who | What to know |
|---|---|---|
| Check zoning and history | Planning (Property Information Map); Rent Board for tenancy | Zoning, height, historic status and eviction records set the path |
| Preliminary or project review | Planning | Project Review Meeting $595 for five or fewer units; optional SB 330 preliminary application |
| Planning application or approval | Planning; Planning Commission for Conditional Use | Ministerial paths end in a Planning Approval Letter; Conditional Use needs a hearing |
| Neighborhood notice | Planning | 30-day Section 311 notice where required; none for SB 9 and State ADUs |
| Lot split or condominium map | Public Works, Bureau of Surveying and Mapping | Parcel map for 4 or fewer parcels, final map for 5 or more |
| Building permit and inspections | Department of Building Inspection | Plan review and inspection fees; impact fees collected |
Sources: SF Planning ZA Bulletin No. 4, Director Bulletin No. 8 and FY 2026-27 fee notice; SF Public Works Parcel Map / Final Map application.
SF Planning's historic preservation FAQ describes the split plainly: "The Department of Buildings Inspection (DBI) issues permits, which the Planning Department planners review for compliance with the Planning Code." For a ministerial project the order is fixed by the application forms. The SB 9 packet says that after approval "the Planning Department will issue a Planning Approval Letter," and the owner then submits the building permit to DBI, noting in the description of work "that the permit is part of an SB 9 application." For a lot split, Public Works comes first. ADU permits start online through the City's ADU application, and SF Planning says Local Program ADUs get "In-house review by Planning" before the building permit review.
Two early checks save the most time. The first is the Property Information Map, which shows the zoning, the height and bulk district and the historic status. The second is the tenant and eviction history at the Rent Board, because SB 9, the Local ADU Program, the four-unit exception and Housing Choice-SF all turn on it. SF Planning's Project Review Meeting, a paid meeting with staff on code questions, costs $595 for projects of five or fewer units under the FY 2026-27 schedule.
Review Deadlines
State law sets the clock for the ministerial paths, and San Francisco's documents repeat it:
- SB 9. SF Planning's SB 9 page says that "Within 60 days of submittal of a complete application, the Planning Department will review and approve the application, or issue a full set of comments." Government Code 65852.21 sets the same 60 days for two-unit projects, and 66411.7 for lot splits.
- State Program ADUs. Director Bulletin No. 3 lists a "60-day review from the date of a complete application." Government Code 66317 says an ADU application not decided in 60 days "shall be deemed approved."
- Neighborhood notice. Where Section 311 applies, the notice "initiates a 30-day notification period for neighborhood review and comment," according to ZA Bulletin No. 4.
- Tentative map appeals. Public Works says neighbors within 300 feet or any interested party may appeal a tentative map decision to the Board of Supervisors "within 10 days of the date of the decision."
The ministerial paths also skip steps that take time. The SB 9 application says "CEQA review is not required for SB 9 eligible projects," and that the City "will not accept Discretionary Review applications for these projects." Director Bulletin No. 3 says the same for State ADUs and adds "No appeal opportunity." A project that needs a Conditional Use hearing, such as a demolition under Section 317 or a home over 4,000 square feet, has no such deadline in these documents and depends on the Planning Commission calendar.
Section 311 Neighborhood Notice
ZA Bulletin No. 4 (revised March 2026) explains Planning Code Section 311, "adopted March 4, 1996," which requires notice to neighbors and owners for permits "involving new construction, change of use, or building expansions in RH/RM Districts." Whether notice is needed depends on two things: "the location of a project within the City" and "a project's scope of work." Inside the Priority Equity Geographies Special Use District, areas the Housing Element identifies as having many vulnerable residents, "all project applications ... that propose new construction, demolition, or expansions to buildings, with certain exceptions, require notification." Outside it, only certain scopes of work do.
For housing, the key interpretation is the exemption for adding units. The bulletin says Ordinance No. 248-23 "added Section 311(b)(3) to create specific triggers for neighborhood notice for building permits outside the Priority Geographies SUD," and that "These triggers included an exception from neighborhood notice if at least one new dwelling unit is added." The exemption "applies per building permit," so the building being altered must itself gain a unit. Outside the special use district, a "vertical alteration," such as a new floor on top or a roof raised more than 30 inches, needs notice unless a unit is added. The bulletin also cites "Ordinance 243-83" as the source of the special use district, while the rest of the bulletin and the ordinance title name Ordinance No. 248-23; the ordinance is the one on record.
The fee for mailing notice is $123 plus $4.36 per envelope under the FY 2026-27 schedule. A permit renewed more than three years after its notice may need new notice under long-standing Department practice.
Planning Application Fees
SF Planning's fee page, last updated August 29, 2026, says "The Fee Schedule for fiscal year 2026-27 is now in effect" and that "Full payment is required upon submission of your application to be considered complete." Its download link opens a schedule marked "EFFECTIVE AUGUST 29, 2025" and updated June 15, 2026, while the Department's 30-day notice says the new schedule takes effect August 31, 2026. The figures below are from that FY 2026-27 notice; confirm the current figure when you apply.
| Application | FY 2026-27 fee |
|---|---|
| New construction, cost $0 to $99,999 | $3,589 |
| New construction, cost $100,000 to $499,999 | $3,591 plus 3.950% of the cost above $100,000 |
| New construction, cost $500,000 to $999,999 | $19,701 plus 1.260% of the cost above $500,000 |
| New construction, cost $1,000,000 to $4,999,999 | $26,130 plus 0.487% of the cost above $1,000,000 |
| Change of use or alteration, cost $0 to $9,999 | $516 |
| Demolition permit | $2,373 |
| Building permit neighborhood notification | $123 plus $4.36 per envelope |
| Back check fee for permit revisions | $374 |
| Variance, cost $20,000 or more | $6,036 |
| Publicly-initiated discretionary review | $807 |
| Project Review Meeting, five or fewer units | $595 |
| Historic Resources Review | $2,766 |
Source: SF Planning, Fee Schedule FY 2026-27 notice, Sections 1, 3 and 6. Some fees include a Board of Appeals surcharge of $45; the Board of Supervisors appeal surcharge is $240.
The schedule explains its sliding scale with an example: for a cost of $1,450,000 in the $1,000,000 to $4,999,999 range, the $1,000,000 range minimum is subtracted, and the fee is the remaining $450,000 times the variable rate, plus the base fee and any surcharge. Fees are "adjusted by the two-year average consumer price index (CPI) change" each year. Most applications are also "subject to billing for staff time and materials if the cost of reviewing the application exceeds the initial fee charged." An application withdrawn before a hearing can be refunded the initial fee "less the cost of time and materials expended," if the request comes "within six months of the project closure date."
The schedule also lists enforcement penalties that bear on housing projects: "up to $250,000 per unit" for the removal of a dwelling unit or the addition of four or more unauthorized units, "up to $500,000 per structure" for significant alteration or demolition of a historic property, and "up to $150,000" for misrepresentation of tenant information, a penalty the fee page says was added April 22, 2026.
Building Permit and Map Fees
DBI charges its own fees. Its Table 1A-D, effective July 12, 2026, sets hourly rates of $526 for plan review, $519 for inspection, $555 for off-hour inspection, $672 for housing inspection and $303 for administration, and notes that "Additional fees may apply to your building permit." DBI's other permit fee tables were not used for this page, because VanPlex could not confirm which version is in force. Public Works charges for maps: a parcel map for new construction condominiums or a land split of four or fewer lots costs $15,670 from July 1, 2026, plus $50 per lot or unit. The lot size and subdivisions page lists the other map fees.
Impact Fees and Inclusionary Housing
Development impact fees are one-time charges on new development for transit, parks, child care and other services. The Planning fee schedule says they "are collected by the Department of Building Inspection; they are adjusted annually in January based on Annual Infrastructure Construction Cost Inflation Estimates." Three recent ordinances change when and how much is paid:
- Ordinance No. 196-25 postponed "the collection of development impact fees for designated residential development projects to the date of first certificate of occupancy or first temporary certificate of occupancy, whichever occurs first," to comply with Government Code 66007.
- Ordinance No. 136-26, passed July 21, 2026 and listed by SF Planning as effective August 22, 2026, amends the Building Code "to reduce Planning Code Article 4 development impact fees and allow deferral of payment of such fees," and deletes inclusionary requirements for projects under 25 units.
- Ordinance No. 222-25 sets the ADU rule: no impact fees for ADUs or junior ADUs under 750 square feet of gross floor area, or for ADUs on lots with three existing units or fewer; other ADUs pay in proportion to the primary dwelling.
Ordinance No. 136-26 prints its fee changes as added and deleted text that the page layer mixes, so this guide does not state the new percentages. Ask SF Planning for the fee assessment on your project, and check the inclusionary rule, since the Family Zoning Plan page still describes the earlier 10-unit threshold. State limits on fees are on the impact fees page.
Best For
- ✓ An SB 9 or State ADU project that wants a 60-day decision with no hearing or appeal.
- ✓ A project outside the Priority Equity Geographies that adds a unit and so skips Section 311 notice.
- ✓ An owner who budgets Planning fees from the construction cost table before filing.
Usually Fails When
- ✕ The application is filed without full payment, so it is not complete and the clock has not started.
- ✕ A Conditional Use hearing is needed and the schedule assumes a 60-day decision.
- ✕ The budget uses impact fee rates from before Ordinance No. 136-26.
What To Verify Before Spending Money
- → Which fee schedule version Planning applies on the day you file.
- → Whether the lot is inside the Priority Equity Geographies Special Use District.
- → The impact fee assessment and payment date after Ordinances No. 196-25 and 136-26.
Where to Go Next
Related on VanPlex: the San Francisco overview and impact fees in California.
Frequently Asked Questions
How much is the San Francisco Planning fee for a new fourplex?
What does the San Francisco Department of Building Inspection charge per hour?
What is Section 311 neighborhood notice in San Francisco?
Does adding a unit avoid neighborhood notice in San Francisco?
How long does San Francisco have to decide an SB 9 application?
When are impact fees paid in San Francisco?
Do ADUs pay impact fees in San Francisco?
Can I get a refund of a San Francisco Planning application fee?
What is the fee for a San Francisco discretionary review request?
Who issues building permits in San Francisco?
Official sources (checked October 2026)
Get new guides by email
New VanPlex guides and articles on multiplex rules, building costs and permits, sent to your inbox.
Planning a multiplex in San Francisco?
VanPlex builds multiplexes in British Columbia, Canada. For a lot in San Francisco, our team makes a custom proforma by hand and emails it to you in 24 to 48 hours.
Get a proforma for your address