Dallas | Plats, Permits and Fees

Dallas Plats, Permits and Fees: Steps, Deadlines and What the City Charges

A Dallas project that creates lots passes through two City reviews. The first is the plat, the recorded map that divides land into lots, decided by the City Plan Commission within 30 days. The second is the building permit. Each has a fee, and new homes also pay a park land fee or give land for a park. This page gives the steps, the deadlines in state law and the City's fee figures. The Dallas overview gives the short version.

Dallas plats and fees in six facts

Kinds of Plat

The City's subdivision page says: "Property must be subdivided prior to the issuance of a building permit for construction of any residential or commercial building." The Platting Guidelines of December 2024 define a plat as "the graphic presentation of one (1) or more lots or tracts of land" that "establishes a legal building site and is generally required before a building permit or certificate of occupancy can be issued." There are "two steps to the platting process, Preliminary Plat approval and Final Plat approval."

Type When it applies Fee pattern
Minor plat Five acres or less in R, D or TH districts, or three acres or less elsewhere, with no new public streets, water, wastewater, paving or drainage Preliminary plat fee only, no final plat fee
Major plat Any plat other than a minor plat or a correction plat Separate preliminary and final plat fees
Replat Changes part of a recorded plat; a residential replat covers land zoned or deed restricted for no more than two homes By size, as above
Minor amending plat Minor changes to a recorded plat that cannot create or remove a lot $850
Revised plat Adds up to 10 percent to the area of a preliminary plat Half of the original fee

Source: City of Dallas, Platting Guidelines, December 2024, pages 3, 4 and 15.

Major plats pay twice "since site/grading plans, engineering plans, bonds, and contracts are frequently required in the platting process for Major Plats." A bond here is a financial guarantee that the developer will build the streets and pipes the plat shows. Small corrections can go to staff: the Subdivision Administrator may approve "Correction Plats or Minor Amending Plats" for minor errors and lot line adjustments outside residential districts, under Local Government Code 212.016. The lot size page covers the lot pattern rule and the residential replat.

The Steps and the 30-Day Rule

  • Consult first. "It is strongly recommended that the applicant consult with a Subdivision Planner prior to formal submission."
  • File through a surveyor. Applications "must be submitted to the Subdivision Administrator by a Surveyor registered in the State of Texas." Submission days are Wednesdays and Thursdays, 8 a.m. to 5 p.m., at the Oak Cliff Municipal Center, 320 E. Jefferson Blvd. An incomplete application is returned.
  • Hearing date. Staff review the application for completeness "and schedules a City Plan Commission hearing date within 30 days of the application acceptance date."
  • Routing. The plat goes to City departments and utility companies the day it is accepted, and their comments are due at least thirteen days before the hearing. Staff form the recommendation at a meeting, generally on a Friday two weeks before the hearing.
  • Decision. The Commission, "fifteen Commission members, residents of the City of Dallas, appointed by the City Council," meets on scheduled Thursdays. Its action on plats "is final," and an applicant who disputes a condition goes to the Commission's Subdivision Review Committee on the morning of the meeting.

The guidelines state the deadline plainly: "If the City Plan Commission does not take action on the plat application within thirty days of submittal of the plat, the plat is automatically approved." This matches Local Government Code 212.009, which requires a city to "approve, approve with conditions, or disapprove a plat within 30 days after the date the plat is filed." Under the sections that follow in chapter 212, a conditional approval or denial must list each condition or reason in writing, the applicant may answer with no deadline set by the City, and the City then has 15 days to decide on the answer.

Because the Commission acts as a "quasi-judicial" body on plats, "applicants may not contact any member of the Commission prior to the hearing." A plat cut from an unplatted tract that is not a residential replat "can be approved on the consent agenda," as staff wrote in a March 2026 report, which means the Commission approves it with other routine items in one vote.

Conditions, the Final Plat and Recording

Approval comes with conditions. The March 26, 2026 report on a 198-lot plat lists 31, among them: water and wastewater review under Chapter 49 of the City code, civil engineering plans for drainage, paving and street lighting, right-of-way dedication of 28 feet from the centerline of new local streets, a 10-foot by 10-foot corner clip at intersections, monuments at set corners, and a tree survey for the City arborist "prior to an early release request or the recordation of the plat, whichever occurs first."

The final plat is accepted only after "all departments requiring releases have provided written releases." The normal deadline is "Tuesday, 12:00 Noon, the week of the City Plan Commission hearing," and the Chairman and Secretary of the Commission sign it. The owner then files it with the county clerk, with "a copy of the tax certificate for the property" showing county and City taxes are paid; the guidelines list Dallas, Collin, Denton and Kaufman counties. The owner must return "at minimum one original and a scanned PDF" to the Subdivision Section, and failure "may result in holds being placed on your Building Permit(s)/Certificate(s) of Occupancy."

How long approvals last. "An approved Major Preliminary Plat is effective for five (5) years from the date of the Commission action if no progress has been made toward completion of the project," and a minor plat, minor amending plat or administrative plat expires after two years without progress. Progress includes "an application for a permit," "incurring of costs for developing the project," "posting of fiscal security, or payment of utility connection fees or impact fees."

Plat Fees

Plat fee (Chapter 52, Sec. 303.13.3.4) Amount
Minor plat, no lot over 3 acres, single family, duplex or townhouse district $2,895
Minor plat, a lot over 3 acres, same districts $3,364
Minor plat, final fee $840
Major plat, preliminary, less than 20 lots, no lot over 3 acres $3,963
Major plat, final, less than 20 lots, no lot over 3 acres $6,238
Major plat, preliminary, more than 20 lots, no lot over 3 acres $3,342
Major plat, final, more than 20 lots, no lot over 3 acres $4,180
Minor amending plat, certificate of correction, vacation of plat, or building line removal or relocation $850
Early release of a building or foundation permit $269

Source: City of Dallas, Permit Fee Schedule effective July 1, 2025, and the "New Subdivision Fees (Effective May 1st, 2024)" page of the Platting Guidelines, which match. A $15 technology fee applies to each document.

Two fee tables in one guide. The December 2024 guidelines print an older table on page 14, with fees such as "$1,548 plus $17 per lot" for a small major plat and $2,664 plus $26 per lot for a minor plat, and the newer table on page 15. The July 2025 Permit Fee Schedule matches the newer table, so use it, and confirm the amount with the Subdivision Section when you file. The fee schedule itself warns that its figures "are for informational purposes only and are subject to change," and points to Chapter 52 and Ordinance 33080.

Two lines of the fee table read oddly. A final major plat of "less than 20 lots, if no lot exceeds 3 acres" costs $6,238, more than the $4,180 for "more than 20 lots"; and the table does not say what a plat of exactly 20 lots pays. Ask the Subdivision Section which line applies before you budget.

Building Permit Fees

Building permit fees are in Chapter 52 of the City code, Sec. 303, and the Permit Fee Schedule prints them. A new house or duplex pays by floor area under Table A-I; a new apartment building pays $652 per dwelling unit under Table A-II, which "Does not apply to accessory structures."

Permit or review Fee
New single-family or duplex, 0 to 700 sq ft Square feet x 1.07
New single-family or duplex, 701 to 2,350 sq ft Square feet x 0.34569, plus $300
New single-family or duplex, 2,351 to 10,500 sq ft Square feet x 0.077, plus $800
New single-family or duplex, 10,501 sq ft and up Square feet x 0.0272, plus $1,000
New multifamily construction (Table A-II) $652 per dwelling unit
Residential or multifamily plan review $0.046 per sq ft or $577, whichever is greater
Document handling, one- and two-family dwellings $25
Technology fee $15 per document submitted
Surcharge in planned development, SUP and deed-restricted areas 10 percent of the total permit fee
Zoning verification letter $302

Source: City of Dallas, Permit Fee Schedule effective July 1, 2025, Tables A-I and A-II and the Planning and Development rows. Table A-I also sets a minimum inspection fee, starting at $125 for one trade.

By VanPlex arithmetic on Table A-I, a 2,000 square foot house pays 2,000 x 0.34569 + $300 = $991.38 for the permit, plus $577 for plan review (2,000 x $0.046 is $92, below the $577 floor), plus $25 for document handling. A fourplex built as one multifamily building pays 4 x $652 = $2,608 under Table A-II, plus plan review. The 10 percent surcharge applies in planned development, specific use permit and deed-restricted areas.

What the permit needs. Chapter 52, Sec. 302.2.1, as restated by Ordinance No. 33192, has the building official issue a permit when the work complies "with the codes and all other applicable laws and ordinances" and "All fees specified in Section 303 and required by any other applicable city ordinance have been paid." Under Sec. 306.1, "No certificate of occupancy is required for" single family uses, handicapped group dwelling units, duplex uses, or accessory buildings to a house or duplex. Under state law, no Texas city may require fire sprinklers in a one- or two-family dwelling (Occupations Code 1301.551).

The 45-day rule. Local Government Code 214.904 gives a city until the 45th day after a permit application is submitted to grant or deny it, give written notice of why it cannot yet decide, or agree on a deadline in writing. A city that misses the deadline "may not collect any permit fees associated with the application" and must refund those it collected. VanPlex found no published review time for Dallas residential permits on the pages it read.

Park Land Dedication

Ordinance No. 33280, passed November 12, 2025, moved park land dedication into a new Article 8A of Chapter 51A and changed the fees. Dedication means giving land to the City for a park. The fee-in-lieu is the payment made instead. The Park director "shall determine whether the owner of property is required to dedicate land, pay a fee-in-lieu of dedication, or both."

  • Fee-in-lieu. Single family or duplex: "Two percent of the median family income" per dwelling unit. Multifamily one-bedroom: "One percent of the median family income per dwelling unit." Two or more bedrooms: "One and three-fourths percent."
  • Yearly update. "On January 1 of each year, the director shall calculate the fee-in-lieu for each type of development," using the Census Bureau's latest "five-year estimate of median family income for all families within Dallas."
  • When paid. "For single family or duplex uses, payment of the fee-in-lieu is required at the time of issuance of building permits." For multifamily it is due at the final certificate of occupancy.
  • Land instead. One acre per 100 single family or duplex homes, one acre per 255 one-bedroom apartments, and one acre per 127 apartments of two or more bedrooms. A dedicated park must be at least 0.5 acre.
  • Affordable units. The multifamily rule "does not apply to reserved dwelling units," as defined in the City's mixed-income housing rules, Division 51A-4.1100.

An owner can appeal the director's decision to the City Plan Commission "within 30 days after the date of the decision," and the Commission must decide within 60 days of the appeal or the owner's request is granted. The fee the director set for January 1, 2026 is not printed in the ordinance; ask the Park and Recreation Department for the current figure.

The Permit Fee Schedule's water and wastewater rows are review fees, such as $1,848 for an initial engineering plan submittal and $2,500 for a capacity analysis, and VanPlex found no water, wastewater, drainage or roadway impact fee in the documents it read. Ask Dallas Water Utilities which connection charges apply to your lot.

Best For

  • ✓ A minor plat on five acres or less in a single family, duplex or townhouse district with no new streets or utility mains.
  • ✓ An applicant whose surveyor files a complete application on a Wednesday or Thursday, so the 30-day period starts.
  • ✓ A small apartment building, where the permit fee is $652 per unit and no certificate of occupancy fee applies to a duplex.

Usually Fails When

  • ✕ The budget leaves out the park land fee-in-lieu due at the building permit.
  • ✕ The signed final plat is never recorded and returned, and the City holds the building permit.
  • ✕ The plan assumes the older fee table printed on page 14 of the 2024 guidelines.

What To Verify Before Spending Money

  • → Whether your plat is minor or major, and which fee line applies, with the Subdivision Section.
  • → The park land fee-in-lieu set for the current year by the Park and Recreation Department.
  • → Water and wastewater connection charges for the lot, with Dallas Water Utilities.

Where to Go Next

Related on VanPlex: the Dallas overview, how Texas zoning works, and Texas property tax.

Frequently Asked Questions

How long does the City of Dallas take to approve a plat? +
Dallas staff schedule a City Plan Commission hearing within 30 days of accepting a complete plat application, by the December 2024 Platting Guidelines. The Commission then approves, approves with conditions or denies, and "If the City Plan Commission does not take action on the plat application within thirty days of submittal of the plat, the plat is automatically approved." Local Government Code 212.009 sets the same 30 days.
What is the difference between a minor plat and a major plat in Dallas? +
A Dallas minor plat covers five acres or less in a single family, duplex or townhouse district, or three acres or less elsewhere, and needs no new public streets, water, wastewater, paving or drainage. Any other plat, except a correction plat, is a major plat. Minor plats pay a preliminary fee but no final plat fee; major plats pay both, since they often need engineering plans and bonds.
How much does a minor plat cost in Dallas? +
A Dallas minor plat in a single family, duplex or townhouse district costs $2,895 when no lot exceeds 3 acres and $3,364 when one does, plus an $840 minor plat final fee, in the Permit Fee Schedule effective July 1, 2025. A $15 technology fee applies to each document. County recording fees are separate, and the applicant pays them to the county clerk.
How much is a building permit for a new house in Dallas? +
Dallas charges a new single-family or duplex permit fee by floor area under Table A-I of the Permit Fee Schedule: square feet times 0.34569, plus $300, for 701 to 2,350 square feet. For a 2,000 square foot house that is $991.38 by VanPlex arithmetic. Plan review adds $0.046 per square foot or $577, whichever is greater, and a $25 document fee.
What is the Dallas park land fee for a new home? +
Under Ordinance No. 33280 of November 12, 2025, the Dallas park land fee-in-lieu for a single family or duplex home is two percent of the median family income per dwelling unit. For apartments it is one percent per one-bedroom unit and one and three-fourths percent for two or more bedrooms. The Park director recalculates the fees each January 1 from Census data, and a house pays at the building permit.
When must I give land for a park in Dallas instead of paying the fee? +
The Dallas Park director decides whether an owner dedicates land, pays the fee-in-lieu, or both, under Sec. 51A-8A.1004 adopted by Ordinance No. 33280. A dedicated park must be at least 0.5 acre, and the director may require land where it will sit within a 10-minute walk of 1,000 residents or more. The formula is one acre per 100 single family or duplex homes.
Who signs and records a Dallas final plat? +
The Chairman and Secretary of the Dallas City Plan Commission sign the final plat, under the December 2024 Platting Guidelines. The owner or the owner representative then picks up the signed plats, takes them to the county, obtains the tax certificates and files with the county clerk. One original and a scanned PDF must come back to the Subdivision Section, or the City may hold building permits.
Can I talk to a City Plan Commission member about my Dallas plat? +
No. The Dallas Platting Guidelines say the City Plan Commission serves as a "quasi-judicial" body in reviewing and approving subdivision plats, so "applicants may not contact any member of the Commission prior to the hearing." The Commission has fifteen members, residents of Dallas appointed by the City Council, and meets on scheduled Thursdays except the fifth Thursday of a month and holidays.
Does a new Dallas house need a certificate of occupancy? +
No certificate of occupancy is required for single family uses, handicapped group dwelling units, duplex uses, or accessory buildings to a house or duplex, under Chapter 52, Sec. 306.1 as restated by Dallas Ordinance No. 33192 in August 2025. A temporary certificate of occupancy for a one- or two-family dwelling is listed at $250 in the City Permit Fee Schedule effective July 1, 2025.
How long is a Dallas preliminary plat approval good for? +
A Dallas major preliminary plat stays in effect for five years from the City Plan Commission action if no progress is made, citing Local Government Code 245.005, by the December 2024 Platting Guidelines. A minor plat, minor amending plat or administrative plat expires two years after approval without progress. Progress includes a final plat application, a permit application, posting security or paying utility fees.

Official sources (checked October 2026)

VanPlex newsletter

Get new guides by email

New VanPlex guides and articles on multiplex rules, building costs and permits, sent to your inbox.

General information, not legal advice. Texas has no statewide zoning code. Each city writes its own rules, and deed restrictions recorded on a lot can forbid what the city allows. Confirm current requirements with the city planning department, read the deed restrictions for your lot, and talk to a Texas-licensed attorney or architect before you buy land or file plans.