Dallas | Plats, Permits and Fees
Dallas Plats, Permits and Fees: Steps, Deadlines and What the City Charges
A Dallas project that creates lots passes through two City reviews. The first is the plat, the recorded map that divides land into lots, decided by the City Plan Commission within 30 days. The second is the building permit. Each has a fee, and new homes also pay a park land fee or give land for a park. This page gives the steps, the deadlines in state law and the City's fee figures. The Dallas overview gives the short version.
Dallas plats and fees in six facts
- The City Plan Commission reviews and acts on all subdivision plats except administrative plats, and "Their action on plats is final." Source: City of Dallas Platting Guidelines, December 2024
- If the Commission does not act within 30 days of submittal, "the plat is automatically approved." Source: City of Dallas Platting Guidelines
- A minor plat in a single family, duplex or townhouse district with no lot over 3 acres costs $2,895, and the minor plat final fee is $840. Source: City of Dallas Permit Fee Schedule, effective July 1, 2025
- The building permit fee for new multifamily construction is $652 per dwelling unit. Source: City of Dallas Permit Fee Schedule, Table A-II
- Since November 12, 2025 the park land fee-in-lieu for a single family or duplex home is two percent of the median family income per dwelling unit, updated each January 1. Source: Ordinance No. 33280
- A Texas city has 45 days to grant or deny a building permit application, give written reasons it cannot yet decide, or agree in writing on a deadline. Source: Local Government Code 214.904
Kinds of Plat
The City's subdivision page says: "Property must be subdivided prior to the issuance of a building permit for construction of any residential or commercial building." The Platting Guidelines of December 2024 define a plat as "the graphic presentation of one (1) or more lots or tracts of land" that "establishes a legal building site and is generally required before a building permit or certificate of occupancy can be issued." There are "two steps to the platting process, Preliminary Plat approval and Final Plat approval."
| Type | When it applies | Fee pattern |
|---|---|---|
| Minor plat | Five acres or less in R, D or TH districts, or three acres or less elsewhere, with no new public streets, water, wastewater, paving or drainage | Preliminary plat fee only, no final plat fee |
| Major plat | Any plat other than a minor plat or a correction plat | Separate preliminary and final plat fees |
| Replat | Changes part of a recorded plat; a residential replat covers land zoned or deed restricted for no more than two homes | By size, as above |
| Minor amending plat | Minor changes to a recorded plat that cannot create or remove a lot | $850 |
| Revised plat | Adds up to 10 percent to the area of a preliminary plat | Half of the original fee |
Source: City of Dallas, Platting Guidelines, December 2024, pages 3, 4 and 15.
Major plats pay twice "since site/grading plans, engineering plans, bonds, and contracts are frequently required in the platting process for Major Plats." A bond here is a financial guarantee that the developer will build the streets and pipes the plat shows. Small corrections can go to staff: the Subdivision Administrator may approve "Correction Plats or Minor Amending Plats" for minor errors and lot line adjustments outside residential districts, under Local Government Code 212.016. The lot size page covers the lot pattern rule and the residential replat.
The Steps and the 30-Day Rule
- Consult first. "It is strongly recommended that the applicant consult with a Subdivision Planner prior to formal submission."
- File through a surveyor. Applications "must be submitted to the Subdivision Administrator by a Surveyor registered in the State of Texas." Submission days are Wednesdays and Thursdays, 8 a.m. to 5 p.m., at the Oak Cliff Municipal Center, 320 E. Jefferson Blvd. An incomplete application is returned.
- Hearing date. Staff review the application for completeness "and schedules a City Plan Commission hearing date within 30 days of the application acceptance date."
- Routing. The plat goes to City departments and utility companies the day it is accepted, and their comments are due at least thirteen days before the hearing. Staff form the recommendation at a meeting, generally on a Friday two weeks before the hearing.
- Decision. The Commission, "fifteen Commission members, residents of the City of Dallas, appointed by the City Council," meets on scheduled Thursdays. Its action on plats "is final," and an applicant who disputes a condition goes to the Commission's Subdivision Review Committee on the morning of the meeting.
The guidelines state the deadline plainly: "If the City Plan Commission does not take action on the plat application within thirty days of submittal of the plat, the plat is automatically approved." This matches Local Government Code 212.009, which requires a city to "approve, approve with conditions, or disapprove a plat within 30 days after the date the plat is filed." Under the sections that follow in chapter 212, a conditional approval or denial must list each condition or reason in writing, the applicant may answer with no deadline set by the City, and the City then has 15 days to decide on the answer.
Because the Commission acts as a "quasi-judicial" body on plats, "applicants may not contact any member of the Commission prior to the hearing." A plat cut from an unplatted tract that is not a residential replat "can be approved on the consent agenda," as staff wrote in a March 2026 report, which means the Commission approves it with other routine items in one vote.
Conditions, the Final Plat and Recording
Approval comes with conditions. The March 26, 2026 report on a 198-lot plat lists 31, among them: water and wastewater review under Chapter 49 of the City code, civil engineering plans for drainage, paving and street lighting, right-of-way dedication of 28 feet from the centerline of new local streets, a 10-foot by 10-foot corner clip at intersections, monuments at set corners, and a tree survey for the City arborist "prior to an early release request or the recordation of the plat, whichever occurs first."
The final plat is accepted only after "all departments requiring releases have provided written releases." The normal deadline is "Tuesday, 12:00 Noon, the week of the City Plan Commission hearing," and the Chairman and Secretary of the Commission sign it. The owner then files it with the county clerk, with "a copy of the tax certificate for the property" showing county and City taxes are paid; the guidelines list Dallas, Collin, Denton and Kaufman counties. The owner must return "at minimum one original and a scanned PDF" to the Subdivision Section, and failure "may result in holds being placed on your Building Permit(s)/Certificate(s) of Occupancy."
How long approvals last. "An approved Major Preliminary Plat is effective for five (5) years from the date of the Commission action if no progress has been made toward completion of the project," and a minor plat, minor amending plat or administrative plat expires after two years without progress. Progress includes "an application for a permit," "incurring of costs for developing the project," "posting of fiscal security, or payment of utility connection fees or impact fees."
Plat Fees
| Plat fee (Chapter 52, Sec. 303.13.3.4) | Amount |
|---|---|
| Minor plat, no lot over 3 acres, single family, duplex or townhouse district | $2,895 |
| Minor plat, a lot over 3 acres, same districts | $3,364 |
| Minor plat, final fee | $840 |
| Major plat, preliminary, less than 20 lots, no lot over 3 acres | $3,963 |
| Major plat, final, less than 20 lots, no lot over 3 acres | $6,238 |
| Major plat, preliminary, more than 20 lots, no lot over 3 acres | $3,342 |
| Major plat, final, more than 20 lots, no lot over 3 acres | $4,180 |
| Minor amending plat, certificate of correction, vacation of plat, or building line removal or relocation | $850 |
| Early release of a building or foundation permit | $269 |
Source: City of Dallas, Permit Fee Schedule effective July 1, 2025, and the "New Subdivision Fees (Effective May 1st, 2024)" page of the Platting Guidelines, which match. A $15 technology fee applies to each document.
Two fee tables in one guide. The December 2024 guidelines print an older table on page 14, with fees such as "$1,548 plus $17 per lot" for a small major plat and $2,664 plus $26 per lot for a minor plat, and the newer table on page 15. The July 2025 Permit Fee Schedule matches the newer table, so use it, and confirm the amount with the Subdivision Section when you file. The fee schedule itself warns that its figures "are for informational purposes only and are subject to change," and points to Chapter 52 and Ordinance 33080.
Two lines of the fee table read oddly. A final major plat of "less than 20 lots, if no lot exceeds 3 acres" costs $6,238, more than the $4,180 for "more than 20 lots"; and the table does not say what a plat of exactly 20 lots pays. Ask the Subdivision Section which line applies before you budget.
Building Permit Fees
Building permit fees are in Chapter 52 of the City code, Sec. 303, and the Permit Fee Schedule prints them. A new house or duplex pays by floor area under Table A-I; a new apartment building pays $652 per dwelling unit under Table A-II, which "Does not apply to accessory structures."
| Permit or review | Fee |
|---|---|
| New single-family or duplex, 0 to 700 sq ft | Square feet x 1.07 |
| New single-family or duplex, 701 to 2,350 sq ft | Square feet x 0.34569, plus $300 |
| New single-family or duplex, 2,351 to 10,500 sq ft | Square feet x 0.077, plus $800 |
| New single-family or duplex, 10,501 sq ft and up | Square feet x 0.0272, plus $1,000 |
| New multifamily construction (Table A-II) | $652 per dwelling unit |
| Residential or multifamily plan review | $0.046 per sq ft or $577, whichever is greater |
| Document handling, one- and two-family dwellings | $25 |
| Technology fee | $15 per document submitted |
| Surcharge in planned development, SUP and deed-restricted areas | 10 percent of the total permit fee |
| Zoning verification letter | $302 |
Source: City of Dallas, Permit Fee Schedule effective July 1, 2025, Tables A-I and A-II and the Planning and Development rows. Table A-I also sets a minimum inspection fee, starting at $125 for one trade.
By VanPlex arithmetic on Table A-I, a 2,000 square foot house pays 2,000 x 0.34569 + $300 = $991.38 for the permit, plus $577 for plan review (2,000 x $0.046 is $92, below the $577 floor), plus $25 for document handling. A fourplex built as one multifamily building pays 4 x $652 = $2,608 under Table A-II, plus plan review. The 10 percent surcharge applies in planned development, specific use permit and deed-restricted areas.
What the permit needs. Chapter 52, Sec. 302.2.1, as restated by Ordinance No. 33192, has the building official issue a permit when the work complies "with the codes and all other applicable laws and ordinances" and "All fees specified in Section 303 and required by any other applicable city ordinance have been paid." Under Sec. 306.1, "No certificate of occupancy is required for" single family uses, handicapped group dwelling units, duplex uses, or accessory buildings to a house or duplex. Under state law, no Texas city may require fire sprinklers in a one- or two-family dwelling (Occupations Code 1301.551).
The 45-day rule. Local Government Code 214.904 gives a city until the 45th day after a permit application is submitted to grant or deny it, give written notice of why it cannot yet decide, or agree on a deadline in writing. A city that misses the deadline "may not collect any permit fees associated with the application" and must refund those it collected. VanPlex found no published review time for Dallas residential permits on the pages it read.
Park Land Dedication
Ordinance No. 33280, passed November 12, 2025, moved park land dedication into a new Article 8A of Chapter 51A and changed the fees. Dedication means giving land to the City for a park. The fee-in-lieu is the payment made instead. The Park director "shall determine whether the owner of property is required to dedicate land, pay a fee-in-lieu of dedication, or both."
- Fee-in-lieu. Single family or duplex: "Two percent of the median family income" per dwelling unit. Multifamily one-bedroom: "One percent of the median family income per dwelling unit." Two or more bedrooms: "One and three-fourths percent."
- Yearly update. "On January 1 of each year, the director shall calculate the fee-in-lieu for each type of development," using the Census Bureau's latest "five-year estimate of median family income for all families within Dallas."
- When paid. "For single family or duplex uses, payment of the fee-in-lieu is required at the time of issuance of building permits." For multifamily it is due at the final certificate of occupancy.
- Land instead. One acre per 100 single family or duplex homes, one acre per 255 one-bedroom apartments, and one acre per 127 apartments of two or more bedrooms. A dedicated park must be at least 0.5 acre.
- Affordable units. The multifamily rule "does not apply to reserved dwelling units," as defined in the City's mixed-income housing rules, Division 51A-4.1100.
An owner can appeal the director's decision to the City Plan Commission "within 30 days after the date of the decision," and the Commission must decide within 60 days of the appeal or the owner's request is granted. The fee the director set for January 1, 2026 is not printed in the ordinance; ask the Park and Recreation Department for the current figure.
The Permit Fee Schedule's water and wastewater rows are review fees, such as $1,848 for an initial engineering plan submittal and $2,500 for a capacity analysis, and VanPlex found no water, wastewater, drainage or roadway impact fee in the documents it read. Ask Dallas Water Utilities which connection charges apply to your lot.
Best For
- ✓ A minor plat on five acres or less in a single family, duplex or townhouse district with no new streets or utility mains.
- ✓ An applicant whose surveyor files a complete application on a Wednesday or Thursday, so the 30-day period starts.
- ✓ A small apartment building, where the permit fee is $652 per unit and no certificate of occupancy fee applies to a duplex.
Usually Fails When
- ✕ The budget leaves out the park land fee-in-lieu due at the building permit.
- ✕ The signed final plat is never recorded and returned, and the City holds the building permit.
- ✕ The plan assumes the older fee table printed on page 14 of the 2024 guidelines.
What To Verify Before Spending Money
- → Whether your plat is minor or major, and which fee line applies, with the Subdivision Section.
- → The park land fee-in-lieu set for the current year by the Park and Recreation Department.
- → Water and wastewater connection charges for the lot, with Dallas Water Utilities.
Where to Go Next
Related on VanPlex: the Dallas overview, how Texas zoning works, and Texas property tax.
Frequently Asked Questions
How long does the City of Dallas take to approve a plat?
What is the difference between a minor plat and a major plat in Dallas?
How much does a minor plat cost in Dallas?
How much is a building permit for a new house in Dallas?
What is the Dallas park land fee for a new home?
When must I give land for a park in Dallas instead of paying the fee?
Who signs and records a Dallas final plat?
Can I talk to a City Plan Commission member about my Dallas plat?
Does a new Dallas house need a certificate of occupancy?
How long is a Dallas preliminary plat approval good for?
Official sources (checked October 2026)
Get new guides by email
New VanPlex guides and articles on multiplex rules, building costs and permits, sent to your inbox.
Planning a multiplex in Dallas?
VanPlex builds multiplexes in British Columbia, Canada. For a lot in Dallas, our team makes a custom proforma by hand and emails it to you in 24 to 48 hours.
Get a proforma for your address