San Antonio | Plats, Permits and Fees
San Antonio Plats, Permits, Review Deadlines and Development Fees
A San Antonio project needs two approvals before a home can be built: the plat, the recorded map that creates lots, and the building permit. The plat rules are in Article IV, Division 4 of the Unified Development Code (UDC), the permit rules are in Chapter 10 of the City Code, and the fee amounts are in the City's FY 2027 Development Fee Schedule. This page gives the steps, the deadlines and the fees. The San Antonio overview gives the short version of the zoning.
San Antonio plats, permits and fees in six facts
- A minor subdivision has four or fewer lots, fronts an existing street, creates no new street and needs no extension of municipal utilities. Source: San Antonio UDC 35-430
- The reviewing agency must act on a plat within 30 days after it is filed, and a plat is deemed approved unless it is approved or disapproved in that period. Source: San Antonio UDC 35-432
- The Planning Commission decides major plats, and the director of Development Services decides minor plats unless a variance is requested. Source: San Antonio UDC 35-432
- A minor subdivision plat of 0 to 3 acres costs $684.25 plus $92.00 per lot in FY 2027, before the two 4 percent surcharges. Source: City of San Antonio FY 2027 Development Fee Schedule
- A building permit becomes invalid unless work starts within 180 days after it is issued, or if work stops for 180 days. Source: San Antonio City Code 10-6
- Water and wastewater impact fees are governed by the regulations of the utility service provider, and the UDC itself sets no amounts. Source: San Antonio UDC 35-508 and 35-C106
When a Plat Is Required
UDC 35-430(a) requires a plat from the owner of land in the city or its extraterritorial jurisdiction (ETJ) "who divides the tract in two (2) or more parts." The ETJ is the land outside the city limits where the City applies its plat rules. The division counts whether it is made by a deed, a contract for deed, a contract of sale or "any other method."
The same subsection reaches land that was never platted. An owner "shall cause a plat to be made thereof upon a request for utility service or a building permit," unless an exception applies. State law supports this: the section notes that utilities may not connect land without a certificate that a plat is approved or is not required. So an old unplatted tract can need a plat before the first permit, with no lot split at all.
Subsection (c) lists 18 exceptions. These seven apply to houses and small projects:
- One house on an old tract inside the city. A permit for no more than one detached single-family dwelling on an unplatted tract or an old plat that the code calls antiquated needs no plat if the tract has at least 15 feet of frontage, has "an existing lot(s), block and NCB number," was created before January 1, 2005, meets the minimum square footage of its zoning, is under single ownership, needs no public utility extension, and no dwelling will be in a regulatory floodplain, the land the City regulates as likely to flood.
- Repair or replacement. Replacing or repairing an existing single-family dwelling needs no plat if it has had electrical service for more than five years. Expanding it "by up to one thousand (1,000) square feet" also needs none.
- An ADU. "An existing single-family residence can add a second residential structure provided that all requirements of section 35-371 are met."
- Previously platted lots. Land that is "a lot or the last remaining portion of a lot previously platted under the jurisdiction of the county or city."
- Work inside an existing building. Permits for work inside the outline of a lawfully permitted building, including remodeling, general repair and roofing.
- Large parts. Dividing land inside the city into parts greater than five acres, where each part has access and no public improvement is dedicated, for single-family or agricultural use.
- Old inner-city lots. A commercial or multi-family lot within "the original thirty-six (36) square mile area of San Antonio" whose boundaries were recorded before June 14, 1927 and that remains in its original configuration.
One line overrides the list: "Habitable uses within the regulatory floodplain shall always require platting." An owner who is unsure can ask for a certificate of determination. Under Section 35-430(d), the director decides whether a plat is required "within twenty (20) days after the date it receives the request" and issues the certificate within ten days after that. The City's Information Bulletin 101 lists a plat or this certificate among the items to have before applying for a new residential permit.
Minor and Major Subdivisions
Section 35-430(b) sorts every subdivision into one of two classes. A minor subdivision is one that involves four or fewer lots, fronts on an existing street, creates no new street and needs no extension of municipal utilities. A requirement to build a sidewalk, curb, turn lane or wider pavement does not turn a minor plat into a major one. A major subdivision is any other subdivision. The class decides who approves the plat and how long the reviews may take.
| Step | Who acts | Time limit in the UDC |
|---|---|---|
| Plat number and fees | Development Services | The plat application expires if the plat is not filed with the Planning Commission within 2 years |
| Completeness check of the request for letters of certification | Each reviewing department | 5 days for a minor subdivision, 10 days for a major one |
| Letters of certification | Certifying departments and utilities | 10 working days for a minor subdivision, 50 days for a major one; deemed issued if late |
| Decision on the filed plat | Director (minor) or Planning Commission (major) | 30 days after the plat is filed |
| Recording | Bexar County deed and plat records | Within 3 years of approval, or the approval expires |
Source: San Antonio UDC 35-431 and 35-432, Supplement 25 Update 1.
The letters of certification are the part that takes time. Before filing the plat, the applicant asks each certifying entity for a letter: the planning department, the Office of Historic Preservation, the San Antonio Water System (SAWS) or other water and wastewater provider, CPS Energy or other electric and gas provider, the parks department, the county and Development Services. If a letter "is not issued or denied within the time periods prescribed," it "shall be deemed issued" and the applicant may file without it (Section 35-431(d)).
The 30-Day Decision
Section 35-432(d) sets the deadline: "The reviewing agency shall act on a plat within thirty (30) days after the date the plat is filed." And: "A plat is deemed approved unless it is approved or disapproved within the thirty-day period." The rule matches state law. Local Government Code 212.009 says the municipal authority "shall approve, approve with conditions, or disapprove a plat within 30 days after the date the plat is filed."
The 30 days start when the filing is complete. A plat is "deemed filed" only once the plat, all required items, the performance agreement, tax certificates, the letters of certification and any variance request have been submitted. A variance is permission to depart from a rule. A performance agreement is the developer's written promise, backed by a guarantee, to build the required streets and utilities. For other applications, Section 35-402 gives the director five working days to say in writing whether an application is complete, and the applicant has 35 calendar days to supply what is missing.
The approval test favors the applicant: "The plat shall be approved unless it is inconsistent with any of the criteria set forth in article V of this chapter." Article V holds the development standards for streets, utilities, parks, trees and lot layout. Three time limits apply after that. A plat application expires if the plat is not approved within two years from the date the plat number was assigned. An approved plat expires if it is not recorded within three years. Section 35-430 adds that approved plats expire if not recorded within seven years of approval, whatever extensions were granted.
Replats and Amending Plats
Changing lots that are already platted is a replat. Section 35-440 allows a replat without vacating, or cancelling, the old plat when it is signed by the owners of the land being replatted, is approved after a public hearing, and does not try to amend or remove any covenants or restrictions, the private rules recorded with the land. The application comes with a signed affidavit of no conflict with existing covenants or restrictions.
A stricter process applies in single-family and duplex areas. Section 35-443 covers a replat where, during the preceding five years, any of the area was limited by zoning or by deed restrictions "to residential use for not more than two (2) residential units per lot." Notice of the hearing is published before the 15th day before the hearing and mailed to owners of lots in the original subdivision within 200 feet of the lots to be replatted. If the replat requires a variance and owners of at least 20 percent of that land file written protests, approval needs "the affirmative vote of at least three-fourths (¾) of the members present of the planning commission." The replat must be filed within six months of the hearing.
Small fixes have a shorter process. Under Section 35-441 the director may approve an amending plat that corrects an error, moves a lot line to remove an encroachment, or relocates lot lines between adjacent lots when all the owners join and no covenant is removed. Section 35-515(a)(2) names the amending plat as the way to remove a common property line between two lots under one owner.
Plat Fees
Two documents list plat fees, and they do not match. Appendix C of the UDC (Section 35-C103) prints one set. The City's FY 2027 Development Fee Schedule, revised September 2026, prints a higher set, and it is the document Development Services publishes for current fees. Budget with the FY 2027 column.
| Plat fee | FY 2027 fee schedule | UDC Appendix C |
|---|---|---|
| Minor subdivision plat, 0 to 3 acres | $684.25 | $595.00 |
| Minor subdivision plat, 3.01 to 10 acres | $925.75 | $805.00 |
| Per lot fee, minor and single-family major plats | $92.00 | $80.00 |
| Major plat, single-family development base fee | $718.75 | $625.00 |
| Major plat, non-single-family, per acre | $632.50 | $550.00 |
| Subdivision filing fee | $287.50 | $250.00 |
| Amending plat | $690.00 | $600.00 |
| Amending plat to eliminate a lot line | $287.50 | $250.00 |
| Replat, public hearing | $287.50 | $250.00 |
| Replat with notification | $690.00 | $600.00 |
| Development plat | $690.00 | $563.00 |
| Certificate of determination | $230.00 | $150.00 |
Sources: City of San Antonio, FY 2027 Development Fee Schedule, "Subdivision Plat Fees" and "Miscellaneous Plat Fees" tables, read October 8, 2026; San Antonio UDC 35-C103, Supplement 25 Update 1.
The surcharge differs too. Section 35-C101(g) describes a technological improvement fee of "three (3) percent of the fee assessed for zoning and platting permits." The FY 2027 schedule says "all fees are subject to a 4% Technological Improvement and a 4% Development Services surcharge" unless noted. On the schedule's figures, a minor plat that makes two lots from one tract of under three acres comes to $684.25 plus two lot fees of $92.00, or $868.25, before the surcharges, the filing fee and recording.
Recording has its own lines in the schedule: $81.00 for the mylar, the plastic sheet the plat is drawn on, $25.00 for the first page of an instrument and $4.00 for each added page, and a $57.50 Recordation Handling Fee. Plats in the ETJ also pay Bexar County fees, which the schedule lists separately.
Building Permits and Their Time Limits
Section 10-6 of the City Code requires any owner who intends "to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure" to apply to the building official and obtain a permit first. Three time limits apply:
- Application. An application "shall be deemed to have been abandoned one hundred eighty (180) days after the date of filing, unless such application has been pursued in good faith or a permit has been issued." The building official may grant extensions of up to 90 days each.
- Start of work. A permit "shall become invalid unless the work on the site authorized by such permit is commenced within one hundred eighty (180) days after its issuance."
- Stopped work. The permit also becomes invalid if the work "is suspended or abandoned for a period of one hundred eighty (180) days after the time the work is commenced." Extensions of up to 180 days each may be granted in writing for justifiable cause.
State law sets a deadline for the City. Under Local Government Code 214.904, a city must grant or deny a building permit, give written reasons it cannot yet decide, or agree on a deadline, by "the 45th day after the date an application for a permit is submitted." If the city then misses the later deadline, it "may not collect any permit fees associated with the application" and must refund fees already collected.
Two more rules apply at the start and the end of construction. Section 10-10(d) doubles the permit fees for anyone who starts work before getting the necessary permits. Section 10-12 says no building "shall be used or occupied in whole or part" until the building official has issued a certificate of occupancy, the City's written confirmation that the building passed its inspections.
Permit Fees for a New Home
The fee schedule says "New residential building plan review and permit fees (including trade permit fees) are based on square footage." One total covers the building, electrical, mechanical, general plumbing and sewer permits and plan review. Section 10-39 of the City Code prints an older version of the same table, adopted by Ordinance No. 2025-01-30-0075 on January 30, 2025.
| Size of the home (sq ft) | Total basic permit fees, FY 2027 schedule | Total basic permit fees, City Code 10-39 |
|---|---|---|
| 1,001 to 1,250 | $1,175.30 | $1,022 |
| 1,501 to 1,750 | $1,603.20 | $1,394 |
| 2,001 to 2,250 | $1,667.60 | $1,450 |
| 2,501 to 3,000 | $1,728.50 | $1,503 |
| 3,001 to 3,500 | $2,026.30 | $1,762 |
| 4,001 to 5,000 | $2,226.50 | $1,936 |
Sources: City of San Antonio, FY 2027 Development Fee Schedule, new residential construction table, read October 8, 2026; San Antonio City Code Sec. 10-39, Supplement 146. Each total includes the sewer permit, which is $64 in the Code table and $73.60 in the schedule.
Section 10-10(b) says a permit fee is paid "in accordance with the fee schedule adopted by the city," so the current schedule is the one to use. The schedule also says a license issued by the City is required to perform residential construction, and lists the City Residential Builder registration at $195.50. It does not say which table applies to a building of three or four units, so confirm that with Development Services. The three or more homes page covers the permit path for those buildings.
Impact Fees, Stormwater, Parks and Trees
An impact fee is a charge on new development to pay for the water and sewer capacity it uses. UDC 35-508 says "Impact fees are governed by the utility service provider's "utility regulations" which are incorporated by reference into this chapter," and Section 35-C106 names "the San Antonio Water System's Utility Service Regulations." Neither the UDC nor the City fee schedule prints an amount, so this page gives none. Ask SAWS for the fee for your meter size and location before you set a budget. Under Section 35-432, a plat is released for recording only when all required impact and drainage fees have been paid.
| Other City fee | FY 2027 amount |
|---|---|
| Storm water participation, single-family residential | $0.15 per sq ft of impervious cover |
| Storm water participation, multi-family | $0.20 per sq ft of impervious cover |
| Storm water participation, impervious cover increase under 100 sq ft | No fee |
| Tree Permit Residential Fee | $57.50 |
| Tree Plan Review Fee | $115.00 |
| Tree Mitigation (2010 or Greater) Fee | $200.00 |
| Flood Plan Development Permit | $50.00 |
| Residential demolition permit | $86.30 |
| Temporary Residential Certificate of Occupancy | $172.50 |
| Re-inspection Fee | $57.50 |
Source: City of San Antonio, FY 2027 Development Fee Schedule, revised September 2026, read October 8, 2026. The schedule marks the storm water, tree mitigation and flood permit rows as not subject to surcharges.
- Stormwater. Section 35-C109 sets the storm water fee as a "fee-in-lieu of providing detention," which means paying into the regional program in place of building a pond that holds runoff on the site. For single-family and duplex developments it must be paid before the plat is recorded. For redevelopment it is charged only on the increase in impervious cover, the roofs and paving that water cannot pass through.
- Parkland. Section 35-503 applies to residential subdivision plats. It requires one acre of parkland for each 70 dwelling units in the single-family and RM districts and one acre for each 114 units in the MF districts. A subdivision with fewer than 210 units may pay a fee for the whole requirement. The fee is the required acres times the land value per acre, plus $250 per dwelling unit, and the code limits the land value to $50,000 per acre, a figure it says may be revised each year in the budget. Land in an Infill Development Zone is exempt.
- Trees. Section 35-523 protects significant trees, which means a trunk of 6 inches or more in diameter at breast height for all species except those the section lists, and heritage trees of 24 inches or more. On a single-family lot, 35 percent of the significant tree inches and 100 percent of the heritage trees must be preserved, and the builder must plant two new trees of 1.5 inches. Up to 80 percent may be mitigated, which means paid for or replaced. Trees on a lot where a one, two or three-family home is complete are exempt.
- Floodplain. Section 35-F131 requires a floodplain development permit for all land development in an area of special flood hazard. Section 35-F142 allows a substantial improvement of a home in the floodplain only if the finished floor is at least one foot above the regulatory floodplain. The insurance and flood page covers flood insurance.
Page 3 of the fee schedule announces a fee waiver program for eligible projects in three categories, subject to funding availability: affordable housing, including accessory dwelling units; historic rehabilitation; and small business development. The page says the application opens in January 2027.
Best For
- ✓ A split into four or fewer lots on an existing street, which the director decides as a minor plat.
- ✓ A house on a lot that is already platted, which needs no plat step at all.
- ✓ A builder who files a complete plat package, since the 30 days run only from a complete filing.
Usually Fails When
- ✕ A permit is requested on an unplatted tract that meets none of the Section 35-430(c) exceptions.
- ✕ A replat in a single-family area needs a variance and neighbors within 200 feet protest.
- ✕ A budget uses the fee amounts printed in the UDC or the City Code in place of the FY 2027 schedule.
What To Verify Before Spending Money
- → Whether the lot is platted, by asking for a certificate of determination.
- → Current fees and surcharges in the FY 2027 Development Fee Schedule.
- → The SAWS impact fee, which neither the UDC nor the City fee schedule lists.
Where to Go Next
Related on VanPlex: the San Antonio overview, other 2025 Texas housing laws, and building codes from duplex to fourplex.
Frequently Asked Questions
When do I need a plat in San Antonio?
What is the difference between a minor plat and a major plat in San Antonio?
How long does plat approval take in San Antonio?
How much does it cost to plat a lot in San Antonio?
How much is a building permit for a new house in San Antonio?
How long is a San Antonio building permit good for?
What are the impact fees for a new home in San Antonio?
Does San Antonio charge a parkland fee on new subdivisions?
Do I need a tree permit to build a house in San Antonio?
What happens if I start building without a permit in San Antonio?
Official sources (checked October 2026)
Get new guides by email
New VanPlex guides and articles on multiplex rules, building costs and permits, sent to your inbox.