Written by David Babakaiff · Co-Founder, VanPlex | 25+ Years BC Construction Last reviewed: October 2026

San Diego | Permits and fees

San Diego Permits and Fees: Decision Processes, Deadlines and Development Impact Fees

Before building, a San Diego project needs the right approval and must pay several kinds of fees. The City's Development Services Department reviews building permits, and City Planning runs the development impact fees (DIF), one-time charges on new development that pay for parks, fire stations, libraries and streets. This page explains the City's five decision processes, the deadlines state law sets for small housing projects, and the fees in the Fiscal Year 2027 schedules. The California impact fees page covers the state rules.

San Diego permits and fees in six facts

  • San Diego decides permits in five processes: Process One is a staff decision with no hearing and, in most cases, no appeal, and Process Five is a City Council decision. Source: SDMC 112.0501 to 112.0509
  • Development impact fees in San Diego are paid before final inspection, at the lower of the schedule in effect when the application was deemed complete or when the fees are paid. Source: SDMC 142.0640(b)
  • The FY 2027 Citywide Park DIF for a multifamily home of 500 sq ft or less is $11,440, and for a single family home over 2,500 sq ft it is $23,432. Source: FY 2027 DIF schedule
  • In San Diego the first two ADUs on a lot are exempt from development impact fees regardless of size, and the first two SB 9 homes are exempt; the third and fourth SB 9 homes pay. Source: SDMC 142.0640(b)(1), (7)
  • The General Plan Maintenance Fee is $737, charged once per project at application, and has applied to all ADUs and JADUs since August 9, 2022. Source: IB 501 (August 2026); IB 400
  • San Diego must decide SB 9 two-home applications, SB 9 lot splits and ADU applications within 60 days of a complete application. Source: Gov. Code 65852.21, 66411.7, 66317

Five Decision Processes

Section 112.0501 says applications "shall be acted upon in accordance with one of the five decision processes." The higher the number, the more public notice and the higher the body that decides. Under Section 112.0502, a Process One application "may be approved or denied by a staff person," and "A public hearing will not be held." Information Bulletin 409 calls such an approval ministerial: a staff check against fixed rules.

Process Who decides Hearing and appeal Examples for housing
Process One Staff None; no appeal except as Section 141.0418 allows ADUs, SB 9 homes and lot splits, streamlined maps of 10 or fewer lots, SB 79 building permits
Process Two Staff, after a Notice of Future Decision None; appeal hearing at the Planning Commission on request Neighborhood Development Permit; coastal permit in the non-appealable area
Process Three Hearing Officer Public hearing; appeal to the Planning Commission Site Development Permit; parcel maps; coastal permit in the appealable area
Process Four Planning Commission Public hearing; appeal to the City Council Final maps; subdivisions on steep hillsides
Process Five City Council, after a Planning Commission recommendation Public hearings Tentative maps that vacate a public right-of-way

Sources: SDMC 112.0501 to 112.0509 (PDF dated 2-2025); SDMC 125.0430; SDMC 126.0707; SDMC Table 143-01A; IB 479.

In Process Two, staff mail a Notice of Future Decision, and the decision "shall be made no less than 11 business days after the date on which the Notice of Future Decision is mailed." In Processes Three, Four and Five, the City mails a Notice of Application "no later than 10 business days after" the application is deemed complete. Process Three is decided by a Hearing Officer at a public hearing, Process Four by the Planning Commission, and Process Five by the City Council after a Planning Commission recommendation hearing.

Most small housing projects use Process One. ADUs and junior ADUs are "a limited use decided in accordance with Process One." An SB 9 lot split is "a Process One parcel map," Streamlined Small Lot Subdivision maps are Process One, and an SB 79 project "shall require a Building Permit in accordance with Process One." Projects that need a Neighborhood Development Permit or Site Development Permit, such as building on steep hillsides or a small lot subdivision in an RM zone, move to Process Two or Three. The coastal permit adds its own process near the ocean, explained on the coast and hillsides page.

Review Deadlines

  • SB 9 two-home projects. Government Code 65852.21(h): an application "shall be considered and approved or denied within 60 days from the date the local agency receives a completed application," or it "shall be deemed approved."
  • SB 9 lot splits. Government Code 66411.7 sets the same 60 days. The City's regulatory updates page says that under SB 450, lot split and building permit applications "are each subject to a new 60-day review shot clock."
  • ADUs. Government Code 66317: "within 60 days" for a lot with an existing single-family or multifamily home. The City's summary of SB 543 says a city must check an ADU application for completeness "within 15 business days of submittal."
  • Preapproved ADU plans. Information Bulletin 400 says applications using a preapproved plan "will be subject to a 30-day review."
  • Streamlined Small Lot Subdivisions. Information Bulletin 414 says City staff "review and approve or deny the completed tentative map application within 60 days."

Each deadline runs from a complete application. San Diego's subdivision rules also let the City close a map file "after 90 calendar days" if the applicant fails to send requested materials or fees.

Development Impact Fees

Section 142.0640 is the City's DIF rule. The City Planning impact fees page says that "all new development within the city of San Diego is assessed for development impact fees based on the resolutions adopted for Citywide Development Impact Fees for Parks, Mobility, Fire and Libraries," and that the fee "is determined by the type, size and location of the development." The Fiscal Year 2027 schedule sets residential fees by home size.

Home type and size Park DIF Fire DIF Fire DIF (Underserved) Library DIF Mobility DIF
Multifamily, 500 sq ft or less $11,440 $699 $918 $1,774 $3,429
Multifamily, 751 to 800 sq ft $13,852 $846 $1,111 $2,149 $4,152
Multifamily, 1,301 sq ft or more $18,194 $1,112 $1,459 $2,823 $5,454
Single family, 1,000 sq ft or less $14,748 $901 $1,183 $2,288 $4,421
Single family, 1,951 to 2,000 sq ft $20,400 $1,246 $1,636 $3,165 $6,114
Single family, 2,501 sq ft or more $23,432 $1,431 $1,879 $3,635 $7,024

Source: Build Better San Diego Citywide Development Impact Fees, FY 2027 rates by asset type (PDF created September 10, 2026). Selected rows. The schedule prints two Fire columns and does not say on these pages which one applies to a given lot; the City's DIF calculator assigns the rates by parcel number.

Section 142.0640(b) says the fees "shall be paid prior to requesting a final inspection," at the amount from "the Development Impact Fee schedule in effect when the development application was deemed complete, or the Development Impact Fee schedule in effect when the fees are paid, whichever amount is lower." Under subsection (c), the fees rise each July 1 by "the one-year change (from March to March) in the Construction Cost Index (CCI) for Los Angeles." City Planning says a waiver or reduction must be requested "within 10 calendar days after the development impact fees are paid," with "A $2,500 deposit."

The exemptions in Section 142.0640(b) matter most for small projects:

  • "Accessory Dwelling Units less than 750 square feet in gross floor area, Junior Accessory Dwelling Units, movable tiny houses, and guest quarters are exempt."
  • "The first two Accessory Dwelling Units on a premises shall be exempt" from the fees "regardless of the gross floor area," except ADUs added to an unsplit SB 9 lot, which pay if they are "greater than 750 square feet." With more than two ADUs, the two smallest are exempt.
  • ADUs of any size are exempt where the owner records an affidavit to live on site "for a minimum of three years from the date of Building Permit issuance."
  • "The first two dwelling units constructed in accordance with Chapter 14, Article 3, Division 13 shall be exempt." The third and fourth SB 9 homes pay.
  • Inclusionary units built on site, permanent supportive housing, and qualifying Complete Communities homes are exempt.

The City's ADU exemption is worded differently from state law. The code exempts ADUs "less than 750 square feet in gross floor area." Government Code 66311.5(c)(1) bars any impact fee on "an accessory dwelling unit that has 750 square feet of interior livable space or less." For an ADU of exactly 750 square feet, or one whose gross area is over 750 while its livable space is 750 or less, the statute controls.

Building Permit and Other Fees

Information Bulletin 501 (August 2026) lists the construction permit fees. At submittal, the General Plan Maintenance Fee is $737.00, "collected once per project at the time of application," and the Mapping Fee is $12.16. Plan check fees come from Table 501A, and inspection fees are collected at issuance.

The bulletin explains that building permit fees "may be collected during different points of the permitting process: at project submittal, during review, at permit issuance, and during inspection." It adds that "Plan check fees and some administrative fees are non-refundable, but inspection fees may be refundable." Plan check fees are first figured from the plans at submittal and then checked during review, so a design change during review "may result in additional plan check fees." Impact fees are separate: Bulletin 501 says they "are due at the final inspection of completed buildings" but "can be paid at any time after the building permit has been issued." To estimate them, City Planning directs applicants to enter the parcel number and development details into its Citywide Development Impact Fees Calculator.

Project type (Table 501A) Plan check Inspection
House, duplex, or detached ADU over 500 sq ft (Res-SDU/DUP) $8,085.26 base; $4.10 per sq ft increment at the 3,000 sq ft step $8,401.90 base; $4.21 increment
Addition or remodel, attached ADU or JADU to 1,100 sq ft, detached ADU up to 500 sq ft $3,512.92 base; $6.98 increment at the 500 sq ft step $2,228.29 base; $4.46 increment
New multi dwelling unit building (New MDU) $4,627.13 base; $0.97 increment at the 5,000 sq ft step $2,130.97 base; $0.48 increment
Attached townhomes $14,100.60 base; $2.41 increment at the 6,000 sq ft step $12,054.89 base; $2.05 increment

Source: Information Bulletin 501, Table 501A (August 2026). The table prints a base rate and, at a stated base square footage, an increment rate per square foot; base square footage "includes the thickness of exterior walls."

  • DIF review. "A non-refundable hourly plan check fee based on 2.5 hours of review time will be added to all building permit projects" to calculate impact fees. The hourly rate in the FY 2027 schedule is $196.75.
  • Lead hazard fee. $58.00 on permits for structures built before 1978.
  • Regional Transportation Congestion Improvement Program (RTCIP) fee. Applies to new residential development; Bulletin 409 lists it for SB 9 homes, and Bulletin 400 says projects "proposing more than one ADU" pay it.
  • School fees. Paid to the school district before permit issuance, on the "assessable space." Information Bulletin 146 exempts residential construction adding no more than 500 square feet, and one new detached ADU or JADU of "less than 500 square feet."
  • Water and sewer. Capacity fees are "calculated by Equivalent Dwelling Unit (EDU)" and "Water capacity fees may be deferred."
  • Active Transportation In Lieu Fee. "$1,769.11 per excess Vehicle Mile Traveled" in Mobility Zone 4, due at final inspection.
  • ADU Home Density Bonus. A Community Enhancement Fee on bonus and affordable ADUs, "as established by San Diego Resolution." The City pages read for this guide do not state the amount.

Discretionary permits have their own fees in Information Bulletin 503 (September 2026). Its flat fee table lists $14,838.42 for a Neighborhood Development Permit, $18,372.18 for a stand-alone tentative map, $10,245.50 for a stand-alone map waiver, and $30,914.15 for a "Coastal Development Permit-Single Dwelling Unit/Companion Units (Process 2 Decisions Only)." A project with more than one approval uses a deposit account instead. Information Bulletin 414 says Streamlined Small Lot Subdivision maps "are subject to the same fees as other tentative maps."

Best For

  • ✓ Up to two ADUs of any size, which pay no development impact fees under SDMC 142.0640(b)(1)(A).
  • ✓ An SB 9 duplex, whose first two homes are exempt from impact fees.
  • ✓ A Process One project that fits the code, decided by staff with no hearing.

Usually Fails When

  • ✕ The plan adds a third and fourth SB 9 home and leaves their impact fees out of the budget.
  • ✕ The project needs a Neighborhood or Site Development Permit and the schedule assumes a Process One timeline.
  • ✕ An ADU added to an unsplit SB 9 lot exceeds 750 sq ft and is assumed to be fee-exempt.

What To Verify Before Spending Money

  • → Your DIF amount in the City Citywide DIF calculator, by parcel number and home size.
  • → The school district fee for your area, from the district, for homes over 500 sq ft of assessable space.
  • → The Community Enhancement Fee amount if you use the ADU Home Density Bonus.

Where to Go Next

Related on VanPlex: the San Diego overview, California impact fees and California ADU law.

Frequently Asked Questions

When are development impact fees paid in San Diego? +
San Diego Municipal Code 142.0640(b) requires development impact fees to be paid before requesting a final inspection, and no final inspection occurs until they are paid. The amount is the lower of the schedule in effect when the application was deemed complete or when the fees are paid. Information Bulletin 501 says they may be paid any time after permit issuance.
Do ADUs pay development impact fees in San Diego? +
Usually not. San Diego Municipal Code 142.0640(b)(1) exempts ADUs under 750 square feet, junior ADUs, and the first two ADUs on a premises regardless of size. ADUs are also exempt when the owner signs a recorded affidavit to live on site for three years. ADUs added to an SB 9 duplex on an unsplit lot pay if they exceed 750 square feet.
How much is the park impact fee for a new home in San Diego? +
The San Diego Fiscal Year 2027 Citywide Park Development Impact Fee depends on home size and type. A multifamily home of 500 square feet or less pays $11,440 and one of 1,301 square feet or more pays $18,194. A single family home of 1,000 square feet or less pays $14,748 and one over 2,500 square feet pays $23,432.
Do San Diego development impact fees go up every year? +
Yes. San Diego Municipal Code 142.0640(c) raises development impact fees adopted by City Council resolution every July 1, based on the March to March change in the Construction Cost Index for Los Angeles published by Engineering News-Record. The increase is automatic. If the one-year change is under 0.2 percent, the City Manager may keep fees unchanged.
Can I appeal a development impact fee in San Diego? +
Yes, through a waiver or reduction application under San Diego Municipal Code 142.0640(d). City Planning says it must be filed within 10 calendar days after the fees are paid, with a $2,500 deposit, and may be granted only if the City Council finds no reasonable relationship between the fee and the cost of facilities attributable to the project.
What is Process Two in San Diego permitting? +
Process Two is a San Diego staff decision made without a public hearing, under Municipal Code 112.0503. Staff mail a Notice of Future Decision and decide no sooner than 11 business days later, and an appeal hearing at the Planning Commission is available on written request. Neighborhood Development Permits and many coastal permits use Process Two.
Do ADUs pay school fees in San Diego? +
Sometimes. San Diego Information Bulletin 146 says residential construction that adds no more than 500 square feet of assessable space is exempt, and so is one new detached ADU or junior ADU with less than 500 square feet. Larger ADUs pay the fee set by the school district, based on a City Approval Report, before the permit is issued.
How fast must San Diego review a preapproved ADU plan? +
San Diego Information Bulletin 400 says permit applications that use a preapproved ADU plan, under AB 1332, are subject to a 30-day review and must still meet the Municipal Code. Other ADU applications on a lot with an existing home must be approved or denied within 60 days of a complete application under Government Code 66317.
What does a Neighborhood Development Permit cost in San Diego? +
San Diego Information Bulletin 503, dated September 2026, lists a flat fee of $14,838.42 for a Neighborhood Development Permit. The same table lists $18,372.18 for a stand-alone tentative map and $30,914.15 for a Coastal Development Permit for a single dwelling unit or companion units decided in Process Two. Projects with more than one approval type use a deposit account instead.
What is the Active Transportation In Lieu Fee in San Diego? +
The San Diego Active Transportation In Lieu Fee applies to residential and non-residential projects in Mobility Zone 4 and is due at final inspection, according to City Planning. The current fee is $1,769.11 per excess Vehicle Mile Traveled. Projects in Mobility Zones 2 or 3 instead provide mitigation measures or pay a buyout fee, Information Bulletin 501 says.

Official sources (checked October 2026)

SDMC Chapter 11, Article 2, Division 5, Decision Process (PDF, 2-2025)
https://docs.sandiego.gov/municode/MuniCodeChapter11/Ch11Art02Division05.pdf
SDMC Chapter 14, Article 2, Division 6, Section 142.0640, Development Impact Fees (PDF, 7-2026)
https://docs.sandiego.gov/municode/MuniCodeChapter14/Ch14Art02Division06.pdf
City of San Diego, Fiscal Year 2027 City Planning fee and DIF schedule (PDF)
https://www.sandiego.gov/sites/default/files/feeschedule.pdf
City of San Diego, City Planning, Impact Fees
https://www.sandiego.gov/planning/work/public-spaces/fees
City of San Diego, Information Bulletin 501, construction permit fees (August 2026)
https://www.sandiego.gov/development-services/forms-publications/information-bulletins/501
City of San Diego, Information Bulletin 503, discretionary permit fees (September 2026)
https://www.sandiego.gov/development-services/forms-publications/information-bulletins/503
City of San Diego, Information Bulletin 146, school fees (September 2026)
https://www.sandiego.gov/development-services/forms-publications/information-bulletins/146
City of San Diego, Information Bulletin 400, ADUs and JADUs (January 2026)
https://www.sandiego.gov/development-services/forms-publications/information-bulletins/400
City of San Diego, Information Bulletin 409, SB 9 (July 2026)
https://www.sandiego.gov/development-services/forms-publications/information-bulletins/409
City of San Diego, Development Services regulatory updates
https://www.sandiego.gov/development-services/regulatory-updates
Government Code 66311.5 (ADU impact fees)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66311.5
Government Code 66317 (ADU application deadlines)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66317
Government Code 65852.21 (SB 9 two-unit projects)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=65852.21
Government Code 66411.7 (SB 9 urban lot splits)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66411.7
VanPlex newsletter

Get new guides by email

New VanPlex guides and articles on multiplex rules, building costs and permits, sent to your inbox.

General information, not legal advice. California housing law changes every year, and each city adds its own rules on top of state law. Confirm current requirements with the city or county planning department, and with a California-licensed attorney or architect, before you buy land or file plans.