San Diego Three or More Homes: RM Zones, Complete Communities, Density Bonus and SB 79
On a single-family lot, San Diego's path to more homes runs through ADUs and SB 9, covered on the ADUs and SB 9 page. For three or more primary homes in one building or group, the land usually needs multifamily zoning or a program that sets zoning aside. This page covers the RM zones, the City's inclusionary and density bonus rules, Complete Communities Housing Solutions, and how San Diego is applying SB 79.
San Diego three or more homes in six facts
- San Diego's inclusionary housing rule applies to projects of 10 or more homes outside the Coastal Overlay Zone and 5 or more inside it. Source: SDMC 142.1302
- The City density bonus rules apply to developments of five or more homes and implement Government Code 65915, the State Density Bonus Law. Source: SDMC 143.0710, 143.0715
- Complete Communities Housing Solutions replaces the zone floor area ratio with 4.0, 6.5 or 8.0 by area, with no limit Downtown, in exchange for affordable homes. Source: SDMC 143.1010(a)
- Inside the Coastal Height Limit Overlay Zone, Complete Communities projects outside Downtown are held to a floor area ratio of 2.5 and a height of 30 feet. Source: SDMC 143.1010(a)
- SB 79 projects in San Diego may reach 85 feet within 200 feet of a qualifying stop, 65 feet within a quarter mile and 55 feet within a half mile. Source: Information Bulletin 479
- Ordinance O-22099 exempts land more than a one-mile walk from a qualifying stop and delays SB 79 in fire zones, on historic sites and on sites facing one foot of sea level rise. Source: Ordinance O-22099
Start With the RM Zone
The RM (Residential, Multiple Unit) zones allow "multiple dwelling unit development at varying densities." Each sets a lot area per home, from one home per 3,000 square feet in RM-1-1 to one per 200 in RM-4-11, and the zoning districts page lists all 12. The minimum lot is 6,000 square feet in RM-1-1 to RM-2-6 and 7,000 in RM-3-7 to RM-4-11.
The RM floor area ratio rises with the number of homes in the three lowest zones. In RM-1-1 it is 0.75 for one or two homes, 1.0 for three to seven, and 1.25 for eight or more. RM-1-1 and RM-1-2 also carry lot consolidation rules, for projects that combine lots. Every RM zone requires "Common open space" and private exterior open space, and the RM-1 zones have a 30-foot height limit with an angled plane at the front and sides. The parking, setbacks and height page explains those limits.
ADUs are added on top of RM density. Section 141.0302(b)(2) allows up to two detached ADUs with a new apartment building, and an existing building may add up to eight detached ADUs, never more than its existing units, plus ADUs in unused space up to 25 percent of the units.
Inclusionary Housing: 10 Homes, or 5 Near the Coast
Inclusionary housing is a rule that a market-rate project must include some affordable homes or pay a fee instead. Section 142.1302 says San Diego's rule "applies to all residential development of 10 or more dwelling units outside of the Coastal Overlay Zone, five or more dwelling units within the Coastal Overlay Zone." Since July 1, 2024, Section 142.1304 requires a rental project to offer "At least 10 percent of the total dwelling units" at a cost that "does not exceed 30 percent of 60 percent of median income." A for-sale project offers 10 percent at a cost affordable to median income households or 15 percent to moderate income households.
A City bulletin states the threshold differently. Information Bulletin 501 (August 2026) says the ordinance "requires all new residential developments of two units or more to provide affordable housing or pay a fee in lieu of providing affordable housing." The code sets 10 homes, or 5 in the Coastal Overlay Zone, and the code controls. Information Bulletin 400 states the same 10 and 5 thresholds as the code. Density bonus units are exempt under Section 142.1303(c).
The City Density Bonus
A density bonus lets a project build more homes than the zone allows in exchange for affordable homes. Section 143.0710 says the City's Affordable Housing Regulations "specify how compliance with California Government Code Section 65915 (State Density Bonus Law) will be implemented." Section 143.0715 says they apply "to any development with five or more dwelling units, not including density bonus dwelling units," the same threshold as Government Code 65915(i), which defines a housing development as "a development project for five or more residential units."
A rental project qualifies with "At least 5 percent of the pre-density bonus dwelling units" for very low income households or "At least 10 percent" for low income households, kept affordable "for a period of at least 55 years," or 10 percent for moderate income households. The agreement is signed with the San Diego Housing Commission. The tables that turn those percentages into bonus homes, and the incentives and waivers that come with them, are in Sections 143.0720 and 143.0740.
The City's regulatory updates page notes that AB 1287 "modifies state density bonus law (modeled after San Diego program)" and "Provides greater bonuses than City's Density Bonus 'stacking' provisions, but no additional incentives." The City code itself has a section titled "Additional Density Bonus allowed by the State," Section 143.0760.
Complete Communities Housing Solutions
Complete Communities Housing Solutions (CCHS), in Chapter 14, Article 3, Division 10, is "a floor area ratio-based density bonus incentive program for development within Sustainable Development Areas." A Sustainable Development Area is the land within a set walking distance of a major transit stop: 1.0 mile in Mobility Zones 1 and 3, and 0.75 mile in Mobility Zone 4. The code says CCHS does "not implement" state density bonus law, and Section 143.1002(b)(4) bars using both programs at once.
| Tier or rule | Where it applies | Maximum floor area ratio |
|---|---|---|
| FAR Tier 1 | Any part of the premises in the Downtown Community Planning Area | No maximum for residential |
| FAR Tier 2 | Regional or subregional employment area, or within one mile of a university campus with a medical center, in an SDA in Mobility Zone 3 | 8.0 |
| FAR Tier 3 | Sustainable Development Area in a community plan area in Mobility Zone 3 | 6.5 |
| FAR Tier 4 | Sustainable Development Area in a community plan area in Mobility Zone 4 | 4.0 |
| Family bonus | At least 10 percent two-bedroom and another 10 percent three-bedroom homes, one lease per home | Plus 1.5 in Tiers 2 to 4 |
| Coastal limit | Coastal Overlay Zone and Coastal Height Limit Overlay Zone, outside Tier 1 | 2.5 and 30 feet |
Source: SDMC 143.1001 and 143.1010(a) (PDF dated 9-2026).
- Eligible land. Zoning that is "commercial, residential, or mixed-use" and allows 20 homes per acre or more, or a plan designation of 20 or more within a quarter mile of a rail station. Outside Downtown and the mixed-use zones, a project must reach at least 80 percent of the zone's maximum density.
- Excluded. Proposition A lands, the Old Town San Diego Planned District, projects with visitor lodging other than SRO hotels, and designated historical districts, except non-contributing properties in the Ocean Beach Cottage Emerging Historical District and the Chinese Asian Thematic Historical District.
- Affordable homes. For rentals, at least 15 percent for very low income households, 15 percent for moderate income and 10 percent for low income, counted before the bonus; or 40 percent very low income; or 100 percent low income; or the 100 percent moderate income option.
- Waivers. The zone density, "Maximum structure height," maximum lot coverage, and outside the Coastal Height Limit Overlay Zone and airport zones, overlay height limits. Projects with at least 10 percent three-bedroom homes, one lease per home, skip the private open space rule.
- Fee waivers. If density reaches at least 120 percent of the zone maximum, impact fees are waived for covenant-restricted homes, for up to 30 percent of homes of 500 square feet or less when at least 10 percent have three bedrooms, and for qualifying three-bedroom homes.
- Incentives. Two to five Affordable Housing Incentives, such as deviations from development rules, by the share of lower income or three-bedroom affordable homes.
- Amenities. Each project includes "neighborhood-serving infrastructure amenities," such as the Neighborhood Enhancement Fee or a public space.
Two code sections describe the impact fee waiver differently. Section 142.0640(b)(4) lists the CCHS exemptions with no density condition. Section 143.1010(f) grants them only "if the development provides a residential density that is at least 120 percent of the maximum permitted density." Plan for the stricter reading in 143.1010(f) unless the City confirms otherwise. The 2026 code update, effective July 2026 outside the coastal zone, also "Permits the development of for-sale homes" under CCHS.
SB 79 in San Diego
SB 79 (2025) requires cities to allow mid-rise housing near qualifying rail and bus stops. Government Code 65912.157(n) says the section "shall not apply to a local agency until July 1, 2026." The City's SB 79 page says "SB 79 took effect on July 1, 2026," but "not all areas went into effect on July 1, 2026 since the City Council adopted an ordinance to phase in SB 79's implementation," and that the areas in effect that day were "about 24 percent of the total areas." SANDAG, the regional planning agency, mapped "a total of 74 transit stops" on June 18, 2026.
| Distance from qualifying stop | Maximum height (ft) | Maximum homes per acre | Maximum floor area ratio |
|---|---|---|---|
| Within 200 feet of a stop | 85 | 140 | 4.0 |
| Within 1/4 mile | 65 | 100 | 3.0 |
| Over 1/4 mile, within 1/2 mile | 55 | 80 | 2.5 |
Source: Information Bulletin 479 (July 2026). The bulletin says San Diego's stops "fall within the 'Tier 2' category."
Ordinance O-22099, passed by the Council on May 20, 2026 with final passage May 21, does four things. It exempts "all areas identified by the City as having more than one mile walking path to a TOD Stop." It phases in Low Resource areas "no later than one year following adoption of the seventh revision of the Housing Element." And it holds back Very High Fire Severity Zones, sites "with a historic resource designated as of January 1, 2025 on a local register," and sites "vulnerable to one foot of sea level rise" until a compliant alternative plan is adopted, or one year after that Housing Element, "whichever occurs first." The City's alternative plan is the Transit Village Plan, which City Planning "aims to present" to the Council "in early 2027."
Information Bulletin 479 sets the City's working rules. A site must appear on the "SB 79 Eligible Sites (2026) Layer" in ZAPP and be zoned for residential, mixed-use or commercial use. A project needs "at least five dwelling units" and at least 30 homes per acre or the zone minimum. Homes average no more than 1,750 net habitable square feet. A project of more than 10 homes sets aside 7 percent extremely low income, 10 percent very low income or 13 percent lower income homes, which also meets the City inclusionary rule. SB 79 projects use a Process One building permit, and the bulletin says SB 79 does not remove "any requirement for a Coastal Development Permit (CDP) for a project within the Coastal Overlay Zone."
Replacing the Homes You Remove
The Dwelling Unit Protection Regulations apply to every residential zone. Section 143.1210 says new development "shall include at least as many dwelling units as the most recent permitted development on the premises," and the owner must record a covenant before a demolition permit. A protected dwelling unit is one that, in the five years before the application, was rent-restricted for or rented by very low or low income households (seven years in Barrio Logan), or was taken off the rental market under the Ellis Act in the past ten years. A project that demolishes protected units "shall replace all existing or demolished protected dwelling units." The City's summary of the 2026 code update says it "Clarifies" that replacement must provide "the same total number of bedrooms," and the Complete Communities and SB 9 rules carry their own tenant tests.
Best For
- ✓ An RM-2 or RM-3 lot inside a Sustainable Development Area, where Complete Communities can replace the floor area ratio with 4.0 to 8.0.
- ✓ A commercial or residential lot on the SB 79 Eligible Sites layer within a quarter mile of a trolley stop.
- ✓ A project of 9 homes outside the coastal zone, below the 10-home inclusionary trigger.
Usually Fails When
- ✕ The lot is in the Coastal Height Limit Overlay Zone and the plan assumes Complete Communities height above 30 feet.
- ✕ The lot is in a Very High Fire Severity Zone, on a designated historic site, or in a Low Resource area, where SB 79 is delayed.
- ✕ The plan combines Complete Communities with the City density bonus, which Section 143.1002(b)(4) bars.
What To Verify Before Spending Money
- → Sustainable Development Area, Mobility Zone and SB 79 Eligible Sites layers on ZAPP.
- → Whether any home on the lot was rented to a lower income household in the past five years.
- → Whether the Transit Village Plan has been adopted on your application date.
Where to Go Next
Related on VanPlex: the San Diego overview, SB 79 in California and the duplex to fourplex guide.
Frequently Asked Questions
How many homes trigger affordable housing rules in San Diego?
What is Complete Communities Housing Solutions in San Diego?
How many affordable homes does a San Diego Complete Communities project need?
Can I use Complete Communities on a small San Diego RM lot?
Is SB 79 in effect in San Diego?
How do I know if my San Diego lot qualifies for SB 79?
How many affordable homes does an SB 79 project in San Diego need?
What is the Transit Village Plan in San Diego?
Does San Diego require replacing homes I demolish to build more units?
What affordable share earns a density bonus under San Diego city rules?
Official sources (checked October 2026)
Get new guides by email
New VanPlex guides and articles on multiplex rules, building costs and permits, sent to your inbox.
Planning a multiplex in San Diego?
VanPlex builds multiplexes in British Columbia, Canada. For a lot in San Diego, our team makes a custom proforma by hand and emails it to you in 24 to 48 hours.
Get a proforma for your address