Written by David Babakaiff · Co-Founder, VanPlex | 25+ Years BC Construction Last reviewed: October 2026

Oakland | Permits and Fees

Oakland Permits and Fees: Design Review Tracks, 2026-27 Fees, Impact Fees and Deadlines

A housing project in Oakland usually needs two approvals: a planning approval, which for most new buildings is some form of design review, and a building permit. This page explains the design review tracks, lists the FY 2026-27 planning and map fees, shows how the impact fees are counted, and gives the state deadlines the City must meet. Fees come from the Master Fee Schedule adopted by Ordinance No. 13883, and impact fee rates from Ordinance No. 13853. The Oakland and Berkeley overview has the short version.

Oakland permits and fees in six facts

  • The FY 2026-27 Master Fee Schedule, adopted by Ordinance No. 13883 on June 16, 2026, sets the Ministerial Project Design Review fee at $5,574.28. Source: Master Fee Schedule FY 2026-27
  • A major Conditional Use Permit costs $10,461.68, a major variance $11,058.06, a minor variance or minor Conditional Use Permit $4,959.35, and a rezoning $7,496.08. Source: Master Fee Schedule FY 2026-27
  • Projects of two to four units on a parcel, ADUs, houses of 1,750 sq ft or less and SB 684 projects are exempt from the affordable housing impact fee. Source: OMC 15.72.040.C
  • Ordinance No. 13853 set the FY 2025-26 affordable housing impact fee for multi-family housing at $36.17 per sq ft in Zone 1 and $29.18 in Zone 2, and charges 0 percent in Zone 3 through FY 2027-28. Source: Ordinance No. 13853, Exhibit D
  • Impact fee amounts adjust each July 1 by a construction cost index, whether or not the Master Fee Schedule has been amended. Source: OMC 15.72.050.B, 15.74.050
  • A Regular Design Review decision by the Director of City Planning becomes final 10 days after the decision unless appealed, after notice mailed 17 days ahead to owners and occupants within 300 feet. Source: Planning Code 17.136.040

The Design Review Tracks

Every residential zone chapter requires design review for new buildings and exterior changes. Design review is the City's check of a building's look, size and fit with its site. Which track a project takes decides who signs off, whether neighbors get notice, and whether anyone can appeal.

Track Who decides Used for Notice and appeal
Design review exemption Staff Small work, and ADUs that meet every ADU rule Final and not appealable (17.136.025)
Small Project Design Review Director of City Planning Listed small projects, such as new living units inside an existing building outside S-9 Track One decisions final and not appealable (17.136.030)
Ministerial Design Review Director or designee Up to 30 new units, no use permit, variance, PUD or development agreement No hearing, not appealable (Ordinance No. 13855)
By Right Residential Approval Staff Projects eligible under S-13 or S-14, and fully affordable projects outside historic areas Not subject to the design review procedures (17.136.023)
Regular Design Review Director, or Planning Commission on referral Projects not covered above, and any project needing a use permit or variance Notice within 300 ft; appeal within 10 days (17.136.040)

Source: Oakland Planning Code Sections 17.136.023 to 17.136.040, Supplement 59, and Ordinance No. 13855, Section 17.136.038 as added.

The design review exemption in Section 17.136.025 applies only when the work is on its list, needs no other design review, use permit or variance, is "exempt from the California Environmental Quality Act (CEQA)," matches the existing or historic design, and will not have "a significant effect on the structure's character-defining elements." CEQA is the state law that requires an environmental study for some projects. An ADU that conforms to "all regulations in Section 17.103.080 and Chapter 17.88" is on the list.

Regular Design Review is the full track. Under Section 17.136.040, notice is posted on the site and mailed "to all owners and occupants within three hundred (300) feet of the project site," "not less than seventeen (17) days prior to the date set for decision." A Director's decision "shall become final ten (10) calendar days after the date of initial decision unless appealed to the City Planning Commission or the Commission's Residential Appeals Committee," and those appeal decisions "are not ultimately appealable to the City Council." When the Director refers a project to the Planning Commission instead, the Commission holds a hearing and its decision can be appealed to the City Council within ten days.

Ministerial Design Review, added by Ordinance No. 13855, passed July 15, 2025, is the track most small housing projects will want. It covers projects with "no more than thirty (30) new dwelling, Work/Live, or Live/Work units," no use permit and no variance. "The project shall not be subject to a public hearing of any type," and "The decision by the Director or their designee shall be final immediately and not appealable." It does not cover sites with a landmark, a National Register listing, or an S-7 or S-20 zone. The Supplement 59 edition of the Planning Code does not yet show this section; its Supplement History Table lists ordinances through No. 13868 and omits No. 13855.

Planning Fees for 2026-27

Section 17.136.020 says an application must be "accompanied ... by the fee prescribed in the city master fee schedule." Ordinance No. 13883, passed June 16, 2026 according to the Legistar record, set the FY 2026-27 amounts. The City's June 4, 2026 supplemental report corrected only a fee unit in the Economic and Workforce Development schedule, so the Planning and Building amounts below are those in Exhibit A.

Planning fee FY 2026-27 amount
Ministerial Project Design Review, report fee $5,574.28
Regular Design Review, report fee, minor project $4,937.86
Regular Design Review, report fee, major project $9,204.02
Design review exemption for ADUs (Category I, II and III) $878.58 per application
ADU amnesty program $1,461.53 per application
Major Conditional Use Permit, report fee $10,461.68
Minor Conditional Use Permit, report fee $4,959.35
Major variance, report fee $11,058.06
Minor variance, report fee $4,959.35
Rezoning $7,496.08
Tentative parcel map (Planning) $5,445.46
Mills Act application $3,207.69
Two or more resubmittals, major discretionary cases $2,788.74
Two or more resubmittals, minor zoning cases $655.61

Source: City of Oakland, FY 2026-27 Master Fee Schedule, Exhibit A to Ordinance No. 13883, Planning and Building Department, Planning and Zoning section, "Proposed 2026-27" column. The Regular Design Review rows sit under the heading "8. Regular Design Review" with the line "Design Review in the S-7 or S-20 zones" printed beneath it.

Most of these fees rose for FY 2026-27. The schedule shows Ministerial Project Design Review up 28 percent from $4,363.28 and the ADU design review exemption fee up 79 percent from $491.62. The Department of Transportation charges its own map review fees, listed on the lot size and subdivisions page. Environmental review, building permit and plan check fees are separate lines in the schedule.

Impact Fees by the Square Foot

An impact fee is a one-time charge on new building to pay for the demand it adds to city services. Oakland has three for housing: the affordable housing impact fee in Chapter 15.72, and the capital improvements and transportation impact fees in Chapter 15.74. Ordinance No. 13853, passed July 15, 2025, changed all three "To Calculate Impact Fees For Residential Projects On A Square Footage Basis." The rates are set by impact fee zone.

Housing type Affordable housing fee per sq ft (Zone 1 / 2 / 3) Capital improvements per sq ft (Zone 1 / 2 / 3) Transportation per sq ft
Multi-family housing $36.17 / $29.18 / 0% of $19.73 $1.84 / $1.10 / $0.37 $1.10 in all zones
Townhome housing $14.98 / $10.97 / 0% of $5.99 $2.21 / $1.47 / $0.74 $0.74 in all zones
Single-family housing $12.66 / $9.08 / 0% of $4.40 $2.94 / $2.21 / $0.74 $0.74 in all zones

Source: Ordinance No. 13853, Supplemental Exhibit D, Master Fee Schedule, Impact Fees, "Proposed 2025-26" column (FY 2025-26). Amounts adjust each July 1 under Sections 15.72.050.B and 15.74.050.

Three notes govern these rates. First, the Zone 3 affordable housing rate "shall be charged at zero (0) percent of the listed square footage rate for remaining portion of Fiscal Year 2025-26 and during Fiscal Year 2026-27 and Fiscal Year 2027-28." Ordinance No. 13853 also moved an area from Zone 2 to Zone 3, bounded in part by International Boulevard, 2nd Avenue, Park Boulevard and 23rd Avenue. Second, the amounts "shall automatically be adjusted annually for inflation on July 1st" by a Marshall and Swift building cost index, and "The adjustment shall be automatically effective whether or not the Master Fee Schedule has been amended." So ask the City for the rate in effect when you submit the building permit, which is the date the fee is locked under Section 15.72.040.A. Third, a project pays only on its added residential floor area.

Section 15.72.040.C exempts from the affordable housing fee, among others: ADUs; affordable housing; "Missing Middle housing: Any combination of between two (2) and no more than four (4) units on a parcel"; one-family homes of "one thousand seven hundred fifty (1,750) square feet or less"; and SB 684 projects. For more than four units, the fee is charged on the added floor area minus "the four (4) smallest units." The Chapter 15.74 fees exempt ADUs and some small nonresidential projects, and affordable housing is exempt from the capital improvements fee but "not exempt from the transportation impact fee."

A worked example by VanPlex, at the FY 2025-26 multi-family rates in Zone 1: a new six-unit building of 900 square feet per unit adds 5,400 square feet. The affordable housing fee applies to 5,400 minus 3,600, or 1,800 square feet, which at $36.17 is $65,106. The capital improvements fee on 5,400 square feet at $1.84 is $9,936, and the transportation fee at $1.10 is $5,940. A fourplex of the same unit size would pay no affordable housing fee. The schedule's split between "Multi-Family," "Townhome" and "Single-Family" housing decides which row applies, so confirm the category with the City.

Section 15.72.070 makes the fee due "prior to the issuance of a temporary certificate of occupancy or certificate of occupancy, whichever occurs first," the City's sign-off that a building is ready to live in. Section 15.74.070 has the same first sentence, then adds "no building permit may be issued for any Development Project subject to this Chapter unless the impact fee is paid to the City." The two sentences disagree on timing for the Chapter 15.74 fees, so ask the Planning and Building Department which one it applies to your permit.

Deadlines the City Must Meet

  • Completeness. Government Code 65943: "Not later than 30 calendar days after any public agency has received an application for a development project, the agency shall determine in writing whether the application is complete."
  • Ministerial projects. Government Code 65950(a)(6): "sixty days from the date of receipt of a complete application if the project is subject to ministerial review." A project found exempt from CEQA gets 60 days from that finding under 65950(a)(5).
  • ADUs. Government Code 66317: completeness "not later than 15 business days," and approval or denial "within 60 days" of a complete application when there is an existing home on the lot.
  • SB 9. Government Code 65852.21 and 66411.7: a two-unit project or lot split "shall be considered and approved or denied within 60 days," or it is deemed approved.
  • Parcel maps. Oakland Section 16.24.080: the Director acts on a tentative parcel map "within fifty (50) days," or the map "shall be deemed approved."
  • Hearings. Government Code 65905.5: once a code-compliant housing project is complete, the City "shall not conduct more than five hearings."

The ministerial tracks hold no hearing at all, so a fourplex that fits the zone and the City's objective design standards avoids hearings under Ministerial Design Review. The CEQA and permit streamlining page explains the state deadlines in more depth.

ADU and SB 9 Costs

An ADU that meets every rule needs only the design review exemption, $878.58 per application in FY 2026-27, plus its building permit. It pays none of the three impact fees. An unpermitted ADU built before 2021 can apply for amnesty at $1,461.53. The ADU and SB 9 page has the ADU rules. Ordinance No. 13855 lists "SB 9 ministerial approval of two lots under Government Code Sections 65852.21 and 66411.7" among the project types for Ministerial Design Review. An SB 9 lot split also needs a tentative parcel map, $5,445.46 to Planning and $2,501.11 to the Department of Transportation for map review.

Best For

  • ✓ A fourplex that fits the zone, through Ministerial Design Review with no hearing and no affordable housing fee.
  • ✓ ADUs that meet every rule, at $878.58 for the design review exemption and no impact fees.
  • ✓ Projects in impact fee Zone 3, where the affordable housing fee is 0 percent through FY 2027-28.

Usually Fails When

  • ✕ The project needs a variance or a use permit, which moves it to Regular Design Review with notice and appeals.
  • ✕ A five-plus unit project in Zone 1 did not budget the affordable housing fee above the four smallest units.
  • ✕ The site is in an S-7 or S-20 zone, which rules out Ministerial Design Review.

What To Verify Before Spending Money

  • → The impact fee zone of the parcel and the rate in effect on the building permit submittal date.
  • → Which housing type row (multi-family, townhome or single-family) the City applies.
  • → Whether the Planning Bureau will take the project as Ministerial Design Review.

Where to Go Next

Related on VanPlex: the Oakland and Berkeley overview, the California impact fees page and the CEQA and permit streamlining page.

Frequently Asked Questions

How much does design review cost in Oakland in 2026-27? +
Oakland's FY 2026-27 Master Fee Schedule, adopted by Ordinance No. 13883 on June 16, 2026, lists Ministerial Project Design Review at $5,574.28 and Regular Design Review at $4,937.86 for a minor project and $9,204.02 for a major project. The design review exemption for an ADU is $878.58 per application.
Who decides a fourplex application in Oakland? +
In Oakland, a fourplex that meets the zoning and needs no use permit or variance can go through Ministerial Design Review, decided by the Director of City Planning or a designee with no hearing and no appeal, under Ordinance No. 13855. Otherwise Regular Design Review applies, decided by the Director or, on referral, the Planning Commission.
Does Oakland charge impact fees on a fourplex? +
A fourplex in Oakland is exempt from the affordable housing impact fee under Section 15.72.040.C.4, which covers two to four units on a parcel outside a planned unit development. The transportation and capital improvements impact fees in Chapter 15.74 still apply per square foot. At FY 2025-26 rates the transportation fee for multi-family housing was $1.10 per square foot.
What are Oakland's impact fee zones? +
Oakland charges its affordable housing, capital improvements and transportation impact fees by zone, from the maps in Sections 15.72.140 and 15.74.150. Ordinance No. 13853 moved an area bounded in part by International Boulevard, Park Boulevard and 23rd Avenue from Zone 2 to Zone 3, and set the Zone 3 affordable housing fee at 0 percent through FY 2027-28.
When are Oakland impact fees paid? +
Oakland Sections 15.72.070 and 15.74.070 make the impact fees due in one installment before the temporary certificate of occupancy or certificate of occupancy is issued, whichever comes first. Section 15.74.070 also says no building permit may be issued unless the fee is paid, which conflicts with its first sentence, so confirm the timing with the City.
How long does Oakland have to decide whether an application is complete? +
Under Government Code 65943, Oakland must decide within 30 calendar days whether a development application is complete. For an ADU, Government Code 66317 shortens this to 15 business days and requires a decision within 60 days of a complete application when there is an existing home on the lot. SB 9 projects and lot splits also get 60 days.
Can Oakland hold many hearings on a code-compliant housing project? +
No more than five. Government Code 65905.5 says that once a housing development project that meets the objective general plan and zoning standards is deemed complete, a city shall not conduct more than five hearings, counting continued hearings, and must approve or disapprove it at one of them. Oakland's Ministerial Design Review holds no hearing at all.
How much does it cost to resubmit plans in Oakland? +
Oakland's FY 2026-27 Master Fee Schedule added resubmittal fees. When a case has two or more resubmittals, the fee is $2,788.74 for major discretionary cases such as planned unit developments, rezonings and maps, and $655.61 for minor zoning cases. Revisions cost $201.48 for a design review exemption and $268.64 for Small Project Design Review.
What does a Mills Act application cost in Oakland? +
Oakland's FY 2026-27 Master Fee Schedule lists the Mills Act application fee at $3,207.69, up 10 percent from $2,920.41. The schedule lists it in the Planning and Zoning section of the Planning and Building Department fees, next to the zoning confirmation letter and zoning compliance review fees.
Do Oakland impact fees go up every year? +
Yes. Oakland Sections 15.72.050 and 15.74.050 adjust the impact fees each July 1 by the change in a Marshall and Swift building cost index from January to January. The adjustment takes effect whether or not the Master Fee Schedule has been amended, so the FY 2025-26 rates in Ordinance No. 13853 may differ from the rate charged in FY 2026-27.

Official sources (checked October 2026)

Ordinance No. 13883, FY 2026-27 Master Fee Schedule, Exhibit A (PDF)
https://oakland.legistar1.com/oakland/attachments/c9f664b9-adad-4f37-85c2-faa8c4c1cce1.pdf
City of Oakland, supplemental report on the FY 2026-27 Master Fee Schedule, June 4, 2026 (PDF)
https://oakland.legistar1.com/oakland/attachments/3cb2ac90-6fa0-4565-9cd1-3113b3866e05.pdf
Legistar record, File 26-0746 (Ordinance No. 13883, passed June 16, 2026)
https://webapi.legistar.com/v1/oakland/matters/37327
Ordinance No. 13853, impact fee amendments with Exhibits A to D, as posted July 3, 2025 (PDF)
https://oakland.legistar1.com/oakland/attachments/0ee8a371-4326-43aa-9eed-7cb30c826db7.pdf
Legistar record, File 25-0661 (Ordinance No. 13853, passed July 15, 2025)
https://webapi.legistar.com/v1/oakland/matters/36271
Oakland Municipal Code, Chapter 15.72, affordable housing impact fees (Supplement 103)
https://library.municode.com/ca/oakland/codes/code_of_ordinances?nodeId=TIT15BUCO_CH15.72AFHOIMFE
Oakland Municipal Code, Chapter 15.74, transportation and capital improvements impact fees
https://library.municode.com/ca/oakland/codes/code_of_ordinances?nodeId=TIT15BUCO_CH15.74TRCAIMIMFE
Oakland Planning Code, Chapter 17.136, design review procedure (Supplement 59)
https://library.municode.com/ca/oakland/codes/planning_code?nodeId=TIT17PL_CH17.136DEREPR
Ordinance No. 13855, Ministerial Design Review, text as posted June 24, 2025 (PDF)
https://oakland.legistar1.com/oakland/attachments/5cf1cdb9-bb0a-4b2b-9137-52440d0879c8.pdf
Oakland Municipal Code, Chapter 16.24, parcel maps
https://library.municode.com/ca/oakland/codes/code_of_ordinances?nodeId=TIT16SU_CH16.24PAMA
Government Code 65943 (completeness review)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=65943
Government Code 65950 (decision deadlines)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=65950
Government Code 65905.5 (five-hearing limit)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=65905.5
Government Code 66317 (ADU application deadlines)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66317
Government Code 65852.21 (SB 9 two-unit projects)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=65852.21
VanPlex newsletter

Get new guides by email

New VanPlex guides and articles on multiplex rules, building costs and permits, sent to your inbox.

General information, not legal advice. California housing law changes every year, and each city adds its own rules on top of state law. Confirm current requirements with the city or county planning department, and with a California-licensed attorney or architect, before you buy land or file plans.