Sacramento has four ways to make smaller lots for homes you can sell one by one: the missing middle lot standards, an SB 9 urban lot split, an SB 684 map of up to ten parcels, and an ordinary parcel or subdivision map. Each has its own size limits, zones and review. This page sets them side by side, with the City's 2026 fees. The Sacramento overview covers the missing middle ordinance in short.

Sacramento lots in six facts

Four Paths to Smaller Lots

A subdivision divides one legal lot into two or more. California's Subdivision Map Act sets the process, and each city adds its own rules. In Sacramento the rules for maps sit in Title 17: Chapter 17.828 for tentative maps, Chapter 17.832 for parcel maps, Chapter 17.864 for SB 9 and Chapter 17.868 for SB 684. A tentative map is the first drawing of the new lots that the City approves. A parcel map or final map is the recorded map that legally creates them.

Path Zones Lot size Review
Missing middle lots (Ordinance 2024-0027) R-1, R-1A, R-1B, R-2 1,200 sq ft minimum; 16 ft wide (31 ft corner); 160 ft deepest Tentative map application; site plan and design review for the homes
SB 9 urban lot split (City Code 17.864.030) RE, R-1 Two parcels, each at least 1,200 sq ft and at least 40% of the original Ministerial, decision within 60 days of a complete application
SB 684 / SB 1123 (City Code Chapter 17.868) Vacant RE; R-1 to R-5, RMX, RO and listed nonresidential zones Up to 10 parcels, each at least 600 sq ft (1,200 in RE); no width, depth or frontage minimum Ministerial, decision within 60 days of a complete application
Standard tentative parcel map Any zone Zone minimum from Title 17 Zoning Administrator hearing when a parcel map waiver is sought

Sources: Ordinance 2024-0027, Section 6.A; City forms CDD-0436, CDD-0684 and CDD-0461, all read October 9, 2026.

Outside these paths, a new lot must meet the base zone minimum. The City's September 2020 summary in the Housing Element lists 5,200 square feet for an interior R-1 lot and 6,200 for a corner lot, 2,900 in R-1A, 3,200 in R-1B, and 2,600 (interior) or 3,100 (corner) for a duplex lot in R-2. The full list is on the zoning districts page.

Missing Middle Lot Standards

Section 6.A of Ordinance 2024-0027 sets three numbers. "The minimum lot size is 1,200 square feet." The minimum lot width is 16 feet, "plus an additional 4 feet on each side that abuts a lot containing a detached single-unit dwelling." Corner lots must be 31 feet wide. "The maximum lot depth is 160 feet." These apply in R-1, R-1A, R-1B and R-2 to any project that meets the ordinance's definition of missing middle housing.

The width rule rewards rows of attached homes. A 16-foot lot works where it sits between other narrow lots or townhouse lots. Next to an ordinary house on one side, the lot must be 20 feet wide; between two ordinary houses, 24 feet (VanPlex arithmetic: 16 + 4 + 4). The 160-foot depth limit stops long, narrow lots from running deep into a block.

The City says the purpose is ownership. Its FAQ states: "One of the primary goals of the MMH interim ordinance is to promote entry-level homeownership opportunities." To sell the homes on separate lots, or as condominiums in a "common interest subdivision," the FAQ says "a planning application for the approval of a tentative map is required." It advises hiring qualified surveyors or licensed civil engineers and notes that a real estate attorney can explain other options, such as housing cooperatives and tenancy-in-common, where owners share one lot.

Small lots also change the building rules. On a lot under 2,900 square feet, the missing middle rear setback falls from 15 feet to 4 feet. A duplex on a lot of 2,600 square feet or less, or on an interior lot under 52 feet wide, must fit inside the ordinance's "base building envelope," a set of sloped planes that shape the roof. The parking, setbacks and height page explains those rules.

SB 9 Urban Lot Splits in Sacramento

SB 9 lets an owner split one lot in a single-family zone into two, with staff approval and no hearing. Sacramento applies it through City Code Section 17.864.030 and its SB 9 application, Form CDD-0436. The form's first eligibility question is whether the site is "zoned Rural Estate (RE) or Single-Unit Dwelling (R-1)." Lots in R-1A, R-1B or R-2 can use the missing middle lot standards instead.

The lot split checklist asks five things beyond the zone. Each new parcel must be at least 1,200 square feet. The split may create "no more than two new parcels of approximately equal area," with neither smaller than 40 percent of the original. The site must not have been split under SB 9 before, and the owner, or anyone acting with the owner, must not have split an adjacent parcel under SB 9. The owner must agree to live in one of the homes for three years, unless the owner is a community land trust or a qualified nonprofit corporation.

Historic status can stop a split. The form asks whether the parcel is a landmark on the State Historic Resources Inventory or a city landmark, and whether the split would demolish or alter a contributing structure in a historic district. Tenant history matters too: the form lists housing "occupied by a tenant in the last three years" among the types a project may not demolish or alter, and asks whether the owner withdrew units from rent under the Ellis Act in the last 15 years.

The subdivision standards are short. Each parcel needs "at least 20 feet of developed public street frontage or public alley frontage; or an easement for access and the provision of public services and facilities." The tentative parcel map must meet Section 17.832, and each new parcel needs separate water and sewer services. The tentative map guide sends urban lot split applicants to Form CDD-0436 first.

The 2025 Title 17 omnibus ordinance changed the review to follow SB 450, a 2024 state law. Section 35 of the ordinance added: "The city shall approve or deny an application submitted under this section within 60 days of receipt of a complete application. If the city does not approve or deny the complete application within 60 days, the application will be deemed approved." A denial must come with "a full set of comments" listing what is deficient and how to fix it. The ordinance also limits the grounds for denial to a building official's written finding of "a specific, adverse impact" on public health and safety that cannot be mitigated.

SB 684 Maps of Up to Ten Parcels

SB 684 and SB 1123 let a builder pair a small subdivision with the homes on it, approved by staff. Sacramento codified this in City Code Chapter 17.868. Its SB 684 application, Form CDD-0684, says "Applications must consist of both a subdivision and plans for dwellings." The project must have 10 or fewer homes and a tentative map of 10 or fewer parcels; ADUs and junior ADUs do not count toward the 10.

The site limits come from the state law. The site must be 5 acres or less, or 1.5 acres or less in the RE zone, where it must also be vacant. The form defines vacant as "having no permanent structure, unless the permanent structure is abandoned and unhabitable." The site must be "substantially surrounded" by urban uses, which the form defines as at least 75 percent of the perimeter adjoining developed residential, commercial, public, transit or retail parcels. Homes occupied by tenants in the five years before the application, rent-restricted homes and homes withdrawn from rent in the last 15 years are protected from demolition.

The lots can be small. Item 21 of the objective standards sets a minimum parcel size of 600 square feet, or "1,200 square feet if located in the RE zone," and adds: "There are no minimum requirements for lot width, depth, or frontage." Side and street-side setbacks are 4 feet unless the zone allows less, the rear setback is 4 feet, and no setback is required between homes, although the building code still applies. The average home size, counting ADUs, may not exceed 1,750 net habitable square feet.

The project must also be dense enough. If the zone has a maximum density, the project must reach the greater of 66 percent of that maximum or 19.8 homes per acre; in a zone with no maximum, 19.8 per acre. If either calculation needs more than 10 homes, the form says the project "is not eligible under SB-684/SB-1123." Floor area follows the General Plan maximum for one or two homes. For three to seven homes the limit is "1.0, or the maximum FAR established in the General Plan, whichever is greater," and for eight to ten homes it is 1.25 or the General Plan maximum. State law changes on January 1, 2027: the version of Government Code 65852.28 that starts that day bars a city from setting a floor area ratio standard "that is less than 1.25" for these projects.

The form is stricter than the statute on one point. It asks whether the site was established under SB 684 "or City Code Section 17.864.030 (i.e., SB 9)." Government Code 66499.41(a)(2)(D) requires only that the lot "was not established pursuant to this section," the SB 684 section. State law controls where the two differ, so ask the Planning Division before you plan an SB 684 map on a lot created by an SB 9 split.

Missing middle rules still apply where they fit. Item 10 of the form asks whether a project that is missing middle housing meets Ordinance 2024-0027, then notes that the ordinance's bulk control standards "do not apply to SB-684 projects since they conflict with Gov't Code Sec. 65852.28(b)(2)(E)." The homes must also meet the Citywide Infill Housing Design Standards, a checklist printed in the form.

One line of the form disagrees with the rest. Its "After submittal" note says the planner reviews for compliance "with City Code Chapter 17.864," the SB 9 chapter, while the form's title and overview name Chapter 17.868 as the local SB 684 code. Chapter 17.868 is the chapter that applies; treat the note as a typing error.

Ordinary Tentative and Parcel Maps

The Planning Division handles tentative maps, and the Development Engineering section of Public Works handles final parcel maps, final maps, lot mergers and lot line adjustments, according to the City's Tentative Map Application Information Guide. A lot line adjustment moves the line between two existing lots without creating a new one. A tentative map application needs the Planning Entitlement Application (Form CDD-0063), a preliminary title report prepared within six months, a grant deed for each parcel, a soils report or approved waiver, and a preliminary grading plan or approved waiver.

The map must show contour lines at intervals of no more than one foot, unless the Utilities Department waives them. The guide adds that a "Topographic survey will not be waived in areas within the 100-year flood hazard boundary." The map must also show trees and their drip lines, every existing structure, and the proposed setback lines for each lot.

For four or fewer parcels, the parcel map waiver application explains that "a Tentative Map and a Parcel Map are required." Section 17.832.110 lets the Zoning Administrator waive the parcel map at a noticed public hearing, considered with the tentative map. The Zoning Administrator must find that the subdivision meets the code and the Subdivision Map Act, matches the General Plan, and has adequate existing boundary monuments. An approved waiver skips the City Council notification step in Section 17.832.090, and the City then reviews a certificate of compliance in place of a parcel map.

Map application Fee Worksheet
SB 9 urban lot split $4,208 Staff
SB 9 resubmittal, urban lot split $1,841 Staff
SB 684 tentative map (1 to 10 lots) $4,471 Staff
SB 684 resubmittal $2,893 Staff
Tentative parcel map, 1 to 4 parcels $6,575 Director
Tentative subdivision map, 5 to 50 parcels $7,035 plus $500 per lot over 4 Director
Minor revision to a tentative map $5,457 Director
Time extension, tentative map $4,997 Director
Public Works review, parcel map waiver determination $700 deposit Director
Parks review, tentative map of 1 to 4 parcels $537 Staff and Director

Source: City of Sacramento, Staff Level Fees (CDD-0089) and Director Level Fees (CDD-0091), both revised July 12, 2026. A planning technology fee of 10 percent of the entitlement and environmental fees is added. Public Works, Utilities and Fire review deposits are extra.

Best For

  • ✓ Selling townhouse-style homes on 1,200 square foot lots in R-1 to R-2 under the missing middle standards.
  • ✓ An owner-occupant in RE or R-1 who wants two lots with a 60-day decision under SB 9.
  • ✓ A builder with a site of up to 5 acres who wants up to 10 small fee-simple lots under SB 684.

Usually Fails When

  • ✕ An SB 9 split is planned on an R-1A, R-1B or R-2 lot, which the City form does not accept.
  • ✕ An SB 684 site held homes occupied by tenants in the last five years.
  • ✕ The minimum density calculation for an SB 684 site needs more than 10 homes.

What To Verify Before Spending Money

  • → Your zone and any historic district status on the Land Information Lookup App.
  • → Street or alley frontage, or an access easement, for each new parcel.
  • → Separate water and sewer service for each parcel with the Department of Utilities.

Where to Go Next

Related on VanPlex: the Sacramento overview, SB 9 and SB 684 and SB 1123.

Frequently Asked Questions

What is the smallest lot I can create for missing middle housing in Sacramento? +
A Sacramento missing middle lot can be as small as 1,200 square feet under Section 6.A of Ordinance 2024-0027. It must be at least 16 feet wide, 31 feet on a corner, and no more than 160 feet deep. An interior lot needs 4 more feet of width on each side that abuts a lot with a detached single-unit dwelling, so a lot between two such houses needs 24 feet.
Which Sacramento zones can use an SB 9 urban lot split? +
The City of Sacramento's SB 9 application, Form CDD-0436 dated September 1, 2026, asks whether the site is "zoned Rural Estate (RE) or Single-Unit Dwelling (R-1)." A lot in another zone is not eligible under the form. Each new parcel must be at least 1,200 square feet, and neither parcel may be smaller than 40 percent of the original lot, as Government Code 66411.7 requires.
How long does Sacramento take to decide an SB 9 lot split? +
Sacramento must approve or deny a complete SB 9 urban lot split within 60 days, or the application is deemed approved. The 2025 Title 17 omnibus ordinance added that rule to City Code Section 17.864.030.C to follow SB 450. The City's application says review happens in two phases, completeness and then compliance, and that "The 60-day compliance review timeframe may not be paused or extended."
Do I have to live on the property after an SB 9 lot split in Sacramento? +
Yes, unless you are a community land trust or qualified nonprofit corporation. Sacramento's SB 9 application asks the owner to agree to occupy a dwelling unit on the property "as their principal residence for a minimum of three years" from approval of the urban lot split. Government Code 66411.7(g)(1) requires the applicant to sign an affidavit stating that intent.
What frontage does each parcel need after an SB 9 split in Sacramento? +
Each parcel needs at least 20 feet of developed public street frontage or public alley frontage, or an easement for access and public services, under the City of Sacramento's SB 9 subdivision standards. Without an easement, the applicant must agree to convey one. Each new parcel must also have separate water and sewer services, and the tentative parcel map must meet City Code Section 17.832.
How small can SB 684 lots be in Sacramento? +
Sacramento SB 684 lots can be as small as 600 square feet, or 1,200 square feet in the RE zone, under the City's Form CDD-0684. The form notes, "There are no minimum requirements for lot width, depth, or frontage." The map may create up to 10 parcels for up to 10 homes, and ADUs and junior ADUs do not count toward the 10.
Which Sacramento zones qualify for SB 684 subdivisions? +
Sacramento's SB 684 application lists vacant RE lots; R-1, R-1A, R-1B, R-2, R-2A, R-2B, R-3, R-3A, R-4, R-4A, R-5, RMX, RO, OB, OB-2, OB-3, EC, SC, C-1, C-2, C-3 and M-T; and C-4, M-1, M-1(S), M-2 and M-2(S) inside the Central City. The site must be 5 acres or less, or 1.5 acres or less in the RE zone.
What minimum density does an SB 684 project need in Sacramento? +
A Sacramento SB 684 project on a site not in the Housing Element inventory must meet the greater of 66 percent of the zone's maximum density or 19.8 dwelling units per acre, under Form CDD-0684. Where the zone has no maximum density, 19.8 units per acre applies. If the result is more than 10 units, the form says the project is not eligible under SB 684 or SB 1123.
Can I skip the parcel map for a small Sacramento subdivision? +
Sometimes. Sacramento City Code Section 17.832.110 lets the Zoning Administrator waive the parcel map for a subdivision of four or fewer parcels at a noticed public hearing. The City's Form CDD-0461 lists three findings, including adequate existing boundary monuments as determined by the Director of Public Works. Public Works charges a $700 deposit for the waiver determination under the July 12, 2026 fee worksheet.
Who prepares a tentative map in Sacramento? +
A Sacramento tentative map must be drawn to scale "by or under the direction of a registered civil engineer or licensed land surveyor," according to the City's Tentative Map Application Information Guide, Form CDD-0443. The scale must be at least one inch equals 100 feet. The application also needs a preliminary title report no older than six months and a soils report or an approved waiver.

Official sources (checked October 2026)

City of Sacramento, Ordinance 2024-0027, Missing Middle Housing Interim Ordinance (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/Housing/Missing-Middle-Housing/O2024-0027%20An%20Interim%20Ordinance%20Broadening%20the%20Range%20of%20Housing%20Types%20Permitted%20by%20Right.pdf
City of Sacramento, Missing Middle Housing Interim Ordinance FAQ, updated January 6, 2025 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/Housing/Missing-Middle-Housing/MMHOrdinance_FAQs_01.06.25.pdf
City of Sacramento, 2025 Title 17 Omnibus Ordinance, City Council report, File 2026-00023 (PDF)
https://sacramento.legistar1.com/sacramento/attachments/54f47351-7ea0-4176-af31-bdbc80abf133.pdf
City of Sacramento, SB 9 application, Form CDD-0436 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/planning-forms/CDD-0436-SB-9-Ministerial-Approval-of-Two-Dwellings-and-Urban-Lot-Splits.pdf
City of Sacramento, SB 684 application, Form CDD-0684 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/planning-forms/CDD-0684-SB-684-Planning-Approval-Form.pdf
City of Sacramento, Tentative Map Application Information Guide, Form CDD-0443 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/planning-forms/CDD-0443-Tentative-Map-Application-Guide.pdf
City of Sacramento, Parcel Map Waiver Application, Form CDD-0461 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/planning-forms/CDD-0461-Parcel-Map-Waiver-Application.pdf
City of Sacramento, Staff Level Fees, Form CDD-0089 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/planning-forms/CDD-0089-STAFF-FEE-WORKSHEET.pdf
City of Sacramento, Director Level Fees, Form CDD-0091 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/planning-forms/CDD-0091-DIRECTOR-FEE-WORKSHEET.pdf
City of Sacramento, Housing Element 2021-2029, Appendix H-5, Constraints (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/Long-Range/Housing-Element/H5_Sac-HE_Amended_Final_Constraints_Dec142021.pdf
Government Code 66411.7 (SB 9 urban lot splits)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66411.7
Government Code 66499.41 (SB 684 subdivision maps)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66499.41
Government Code 65852.28 (SB 684 housing standards)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=65852.28
VanPlex newsletter

Get new guides by email

New VanPlex guides and articles on multiplex rules, building costs and permits, sent to your inbox.

General information, not legal advice. California housing law changes every year, and each city adds its own rules on top of state law. Confirm current requirements with the city or county planning department, and with a California-licensed attorney or architect, before you buy land or file plans.

Planning a multiplex in Sacramento?