Sacramento | Permits and Fees

Sacramento Permits and Fees: Review Steps, Deadlines and 2026 Impact Fees

A Sacramento project of two or more homes usually needs a planning approval, then a building permit, and pays impact fees with the building permit. Impact fees are one-time charges that pay for parks, roads, water, sewer and affordable housing. This page lists the review steps and deadlines in Title 17 and the fees the City posted for 2026, with the date of each schedule. Fee figures change every July 1, so confirm them before you budget. The California impact fees page covers the state rules.

Sacramento permits and fees in six facts

Which Review a Project Gets

Most new homes need site plan and design review, the City's check of the site layout and building design under City Code Chapter 17.808. Missing middle projects without deviations are reviewed at staff level under Section 17.808.150. Projects with deviations are decided at director level, which can include a hearing, and tentative maps are priced on the director-level fee worksheet. The Planning and Design Commission hears appeals of director decisions. The three or more homes page explains the findings for missing middle projects.

Several paths are ministerial, which means staff approve a project that meets fixed standards, with no hearing: ADUs under Section 17.228.105, SB 9 projects under Chapter 17.864, SB 684 projects under Chapter 17.868, the City's infill housing permit under Chapter 17.860, and state SB 35 projects. Applications go through the City's e-Planning system and online Public Permit Portal. The forms say staff send an invoice once the materials are uploaded, and "Payment of the fee/deposit(s) results in the application being accepted for assignment to a staff planner."

Public hearings need notice. Under City Code Section 17.812.030, as amended by the 2025 Title 17 omnibus ordinance, mailed notice goes to owners of property within 500 feet of the site, and notice is given "at least ten days prior to the hearing," or 20 days for commission hearings on code amendments that affect permitted uses. If more than 1,000 owners would get mail, a newspaper notice of at least one-eighth page may be used instead.

Deadlines in Title 17

Sacramento applies the state Permit Streamlining Act through City Code Section 17.800.030. The 2025 Title 17 omnibus ordinance rewrote it to follow AB 130. "Within 30 days of submittal of an application and payment of the initial application fee, or of submittal of additional information in response to a written determination of an incomplete application, the planning director shall determine whether the application is complete." The City then decides development projects "within the timeframes in the Permit Streamlining Act." An applicant may appeal a completeness decision to the Planning and Design Commission, which must resolve it "not later than 60 days from the date of the appeal."

The applicant has duties too. Under Section 17.800.040.A, the planning director may find that an applicant failed to process an application in a timely manner if "60 calendar days have passed since the application has been deemed incomplete" and the requested information has not arrived. The section's title now reads "Withdrawal or denial of application for failure of applicant to process in a timely manner."

Ministerial paths have fixed clocks. SB 9 and SB 684 applications are approved or denied within 60 days of a complete application, and the City's forms say "The 60-day compliance review timeframe may not be paused or extended." An SB 9 application not acted on within 60 days "is deemed approved." For SB 35 projects, the City must list any conflicts within 60 days for projects of 150 units or fewer, 90 days for larger ones, and 30 days for a resubmittal that answers the City's written comments. State law gives ADU applications 60 days when the lot already has a home.

Planning Fees for 2026

The City's planning fees are on three worksheets: staff level, director level and commission level. The staff and director worksheets were revised July 12, 2026. Some amounts are flat fees and some are deposits. The worksheets explain: "If a deposit has been paid and processing of that application requires more staff time than has been allocated by the deposit fees charged per this schedule, the project will be assessed for the additional staff time at the staff hourly rate." That rate "is established by City Council Resolution 2026-0121."

Planning item Fee
Site plan and design review, single-unit or duplex dwelling (staff) $2,696 each
Site plan and design review, minor addition or alteration $789
Site plan and design review, building under 10,000 sq ft $2,696
Site plan and design review, 20,000 to 100,000 sq ft $12,558
Director-level hearing fee $5,129
City ministerial infill review, duplex dwelling $1,315 each
City ministerial infill review, under 10,000 sq ft $5,588
SB 684, single-unit or duplex dwelling $3,090 each
SB 684, 3 or more dwelling units $3,747
SB 9, single-unit or duplex dwelling $2,696 each
Density bonus agreement $4,339
Fourth review cycle and beyond $263 per hour
CEQA categorical exemption $920
Planning technology fee 10% of entitlement and environmental fees
Public Works entitlement review $1,760 deposit
Utilities entitlement review $616 deposit
Fire administrative and plan review $436 deposit
Parks review, new residential units $537

Source: City of Sacramento, Staff Level Fees (CDD-0089) and Director Level Fees (CDD-0091), revised July 12, 2026; page images checked. Map fees are on the lot size and subdivisions page.

The worksheets add rules that change the total. "Entitlements requested after a project has been started or as a result of a City enforcement action shall be charged double fees." When a project asks for several of the same entitlement, "only a single fee shall be charged for this class of entitlement," the highest one. Public Works, Utilities, Fire and Parks review is "based on full cost recovery," with the listed amount as the first deposit. A withdrawn application is refunded less the cost of processing it so far.

The building permit has its own fees, paid to the Building Division. The City's Residential New Building page lists those due on every new home permit, such as the building permit fee, plan review, the construction excise tax, the general plan fee and the technology fee, and those due in some cases. The City fee database shows the construction excise tax as ".008 x of the 2002 ICBO Valuation," a percentage of the building's value. A preliminary building permit fee estimate can be requested with Form CDD-0278; the City bills one hour of staff time for projects valued under $1 million and three hours at $1 million or more.

Impact Fees on New Homes

Impact fees are collected with the building permit. The City's Residential New Building page says the park impact fee "is due if the project will result in the establishment of a new dwelling unit," the housing impact fee is "Charged on new residential units as established in the Mixed Income Housing Ordinance (City Code 17.712)," and the residential construction tax is "Charged based on the number of bedrooms per dwelling unit."

Fee Amount
Housing impact fee (FY 2026-27) $3.58 per sq ft; $0 at 20 or more units per net acre (single-unit and duplex) or 40 or more (multi-unit); $1.55 in the Housing Incentive Zone
Park development impact fee (FY 2026/27), outside Central City and Housing Incentive Zones $3.49 per sq ft; $2,616 per unit up to 750 sq ft; $6,982 per unit at 2,000 sq ft and larger
Park development impact fee (FY 2026/27), Central City and Housing Incentive Zones $2.21 per sq ft; $1,642 per unit up to 750 sq ft; $4,381 per unit at 2,000 sq ft and larger
Transportation development impact fee, baseline (schedule as of July 1, 2024) Single-family $2,800 and multifamily $1,608 per unit outside the Housing Incentive/Transit Center Area; $1,680 and $965 inside it
Residential construction tax $250 per one-bedroom unit, $315 per two-bedroom unit, $385 per unit with three or more bedrooms
Water development fee (July 1, 2026 to January 21, 2027) $10,513.13 for a 3/4-inch meter; $10,953.50 for a 1-inch meter
Sewer development fee, single family residence $5,936.84 in the Combined Sewer Service Area; $2,670.74 in the Sewer Development Fee Service Area

Sources: Housing Impact Fee notice; Park Development Impact Fee notice; Transportation Development Impact Fee schedule (page image checked); City fee database entry for the residential construction tax (City Code 3.40); Department of Utilities residential fee schedule.

The housing impact fee depends on density. A project of single-unit or duplex dwellings at 20 or more units per net acre, or multi-unit dwellings at 40 or more, pays $0.00, so a dense missing middle project on a small lot may owe nothing. The Housing Impact Fee page lists eight exemptions, among them "Second residential units" and "A new single-unit dwelling built by an owner-builder on their property." The fees adjust for inflation on July 1 of each year.

Two documents carry dates that need care. The park fee notice in the City fee database is filed under a name ending "July_1_2027," but its text says the fee "will be increasing July 1, 2026" and labels the new rates "FY 2026/2027." The notice text controls. The transportation fee schedule in the database is "As of July 1, 2024," and its footnote says "Fee rates are adjusted annually effective July 1 based on the percentage change in the ENR CCI," a construction cost index, so the 2026 rates are higher than the table shows. Ask Public Works for the current figure.

Utility fees follow a schedule that changes on January 22, 2027. The Department of Utilities says fee adjustments adopted in fall 2023 "will be phased in over four years and will be in full effect Jan. 22, 2027." Its residential schedule for July 1, 2026 to January 21, 2027 also lists a drainage development fee per square foot of new hard surface, from $0.12 in a gravity basin to $4.15 in the Combined Sewer Service Area. Projects in the Sacramento Area Sewer District pay regional sewer fees at that district.

Some areas add their own fees. The Residential New Building page lists North Natomas fees, a habitat conservation fee in North Natomas, fees in the Downtown, Railyards and River District areas, and a Sacramento Area Flood Control Agency development impact fee on conditioned floor area in its fee area. VanPlex did not read amounts for these, so ask the contacts the Building Fees page lists.

School Fees and Fee Reductions

School districts set their own fees. The City collects none of them; it needs proof of payment before it issues the permit. The City's School District Impact Fees sheet, revised September 9, 2026, lists the residential rates:

School district Area covered Residential fee per sq ft
Sacramento City Unified Downtown, Pocket/Greenhaven, south to Elder Creek and Meadowview $5.38
Natomas Unified North of the American River, east of the Sacramento River $5.17
Twin Rivers Unified North Sacramento and Del Paso $5.38
Robla Elementary plus Twin Rivers Area bordered by Ascot, Winters, Norwood, Raley and Rio Linda Blvd. $2.90 plus $2.48
San Juan Unified Haggin Oaks, Campus Commons, University Ave. $5.38
Elk Grove Unified South of Elder Creek, bordered by Hwy 99 and Elk Grove-Florin Rd. $7.23

Source: City of Sacramento, School District Impact Fees, Form CDD-0226, revised September 9, 2026 (page image checked). The sheet says: "RATES SHOWN ARE FOR REFERENCE ONLY; CONFIRM FINAL FEES WITH THE APPLICABLE DISTRICT."

Affordable homes can pay less. Under the City's Reduced Impact Fees for Affordable Housing Units Program, "Eligible development impact fees may be reduced by up to $10,000 per qualifying affordable dwelling unit." A rental unit must serve a low- or moderate-income household at an affordable rent for at least 30 years under a recorded deed restriction; a for-sale unit must go to a low-income household at an affordable price. The program draws on "$3 million each year from the General Fund/Measure U," first come, first served. The fees it can reduce include the park, water, sewer, storm drainage and several area fees.

ADUs have their own rule. State law bars impact fees on an ADU of 750 square feet or less, and the City's transportation fee schedule and housing impact fee page exempt ADUs. The ADUs and SB 9 page gives the details.

Best For

  • ✓ Dense missing middle projects at 20 or more units per net acre, which pay no housing impact fee.
  • ✓ Projects in the Central City or a Housing Incentive Zone, where park fees per square foot are lower.
  • ✓ Affordable units with a 30-year deed restriction, which can cut impact fees by up to $10,000 each.

Usually Fails When

  • ✕ The budget uses the 2024 transportation fee table without the yearly increase.
  • ✕ A permit is pulled after work started, which doubles the planning fees.
  • ✕ An incomplete application sits for 60 days without the requested information.

What To Verify Before Spending Money

  • → A fee estimate from the Building Division using Form CDD-0278.
  • → The school district for your address and its current rate.
  • → Whether your site is in North Natomas, the Railyards, the River District or the flood control fee area.

Where to Go Next

Related on VanPlex: the Sacramento overview, impact fees in California and CEQA and permit streamlining.

Frequently Asked Questions

How long does Sacramento take to say a planning application is complete? +
Thirty days. Sacramento City Code Section 17.800.030.B, as amended by the 2025 Title 17 omnibus ordinance, gives the planning director 30 days from submittal and payment of the initial fee, or from receipt of more information, to decide whether an application is complete and say in writing what is missing. An applicant may appeal the decision to the Planning and Design Commission, which must resolve it within 60 days.
What happens if I do not answer a Sacramento incomplete letter? +
Sacramento may treat the application as not processed. City Code Section 17.800.040.A, as amended by the 2025 Title 17 omnibus ordinance, lets the planning director find that an applicant failed to process an application in a timely manner if 60 calendar days have passed since it was deemed incomplete and the requested information has not been provided. The section's title calls the result withdrawal or denial.
How much is the housing impact fee in Sacramento? +
From July 1, 2026 to June 30, 2027, Sacramento's housing impact fee is $3.58 per square foot for single-unit and duplex dwellings below 20 units per net acre and multi-unit dwellings below 40 units per net acre. It is $0.00 at or above those densities and for conversions of nonresidential buildings, and $1.55 in the Housing Incentive Zone. The fee is set by the Mixed Income Housing Ordinance, City Code Chapter 17.712.
Which homes are exempt from the Sacramento housing impact fee? +
The City of Sacramento's Housing Impact Fee page lists eight exempt project types, including room additions, second residential units, developments with 10 percent regulated low income housing units, and a new single-unit dwelling built by an owner-builder on their own property. An owner-builder uses Form CDD-0334 to request the waiver. Mobilehome parks and some projects with older approvals are also exempt.
How is the Sacramento park impact fee charged on a small home? +
Sacramento's Park Development Impact Fee for FY 2026/2027 is charged per square foot of residential space, with a minimum per unit for homes up to 750 square feet and a maximum for homes of 2,000 square feet and larger. Outside the Central City and Housing Incentive Zones, that is $3.49 per square foot, at least $2,616 and at most $6,982 per unit. The fee is due when a project adds a new dwelling unit.
Do ADUs pay the Sacramento transportation impact fee? +
No. A footnote to the City of Sacramento's Transportation Development Impact Fee schedule says "Low income housing and second residential units (accessory dwelling units) are exempt." State law separately bars impact fees on an ADU of 750 square feet or less under Government Code 66311.5. For other homes, the baseline schedule as of July 1, 2024 lists $2,800 per single-family unit and $1,608 per multifamily unit outside the Housing Incentive/Transit Center Area.
How much are school fees for new homes in Sacramento? +
School fees in Sacramento depend on the school district. The City's School District Impact Fees sheet, revised September 9, 2026, lists residential rates of $5.38 per square foot for Sacramento City Unified, Twin Rivers and San Juan, $5.17 for Natomas Unified and $7.23 for Elk Grove Unified. In the Robla area, owners pay both Robla ($2.90) and Twin Rivers ($2.48). The City collects none of these; it needs proof of payment.
What does a new water connection cost in Sacramento? +
The Sacramento Department of Utilities residential fee schedule for July 1, 2026 to January 21, 2027 lists a water development fee of $10,513.13 for a 3/4-inch meter and $10,953.50 for a 1-inch meter, with credit for existing connections. A 1-inch easement tap installation is $4,507 plus $723 for the meter. The sewer development fee for a single family residence is $2,670.74 outside the combined sewer area.
Can a Sacramento affordable housing project get impact fees reduced? +
Yes, by up to $10,000 for each qualifying affordable dwelling unit under Sacramento's Reduced Impact Fees for Affordable Housing Units Program, last modified by Resolution 2024-0233 on June 25, 2024. Rental units must serve low- or moderate-income households at affordable rent for at least 30 years. The City funds the program with $3 million each year, first come, first served, and applicants use Form CDD-0410.
What does it cost to appeal a Sacramento planning decision? +
Sacramento's Director Level Fees worksheet, revised July 12, 2026, lists $6,312 for an applicant's appeal to the Planning and Design Commission and $415 for a third-party appeal. The Staff Level Fees worksheet lists $415 for a request to reconsider a staff action at the director level. An appeal is void if it is not filed and its fees paid on time, under City Code Section 17.812.060.H.

Official sources (checked October 2026)

City of Sacramento, Staff Level Fees, Form CDD-0089, revised July 12, 2026 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/planning-forms/CDD-0089-STAFF-FEE-WORKSHEET.pdf
City of Sacramento, Director Level Fees, Form CDD-0091, revised July 12, 2026 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/planning-forms/CDD-0091-DIRECTOR-FEE-WORKSHEET.pdf
City of Sacramento, 2025 Title 17 Omnibus Ordinance, City Council report, File 2026-00023 (PDF)
https://sacramento.legistar1.com/sacramento/attachments/54f47351-7ea0-4176-af31-bdbc80abf133.pdf
City of Sacramento, Housing Impact Fee page
https://www.cityofsacramento.gov/community-development/planning/housing/housing-impact-fee
City of Sacramento, Housing Impact Fee notice, July 1, 2026 to June 30, 2027 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/Housing/Housing%20Impact%20Fee%20(HIF)%20FY27.pdf
City of Sacramento, Park Development Impact Fee notice, FY 2026/2027 (PDF, City fee database)
https://services5.arcgis.com/54falWtcpty3V47Z/arcgis/rest/services/Fees_And_Charges/FeatureServer/1/19/attachments/18
City of Sacramento, Transportation Development Impact Fee rate schedule as of July 1, 2024 (PDF, City fee database)
https://services5.arcgis.com/54falWtcpty3V47Z/arcgis/rest/services/Fees_And_Charges/FeatureServer/1/38/attachments/37
City of Sacramento, School District Impact Fees, Form CDD-0226, revised September 9, 2026 (PDF, City fee database)
https://services5.arcgis.com/54falWtcpty3V47Z/arcgis/rest/services/Fees_And_Charges/FeatureServer/1/8/attachments/7
City of Sacramento, Residential New Building fees by project
https://www.cityofsacramento.gov/community-development/building/building-fees/fees-by-project/residential-new-building
City of Sacramento, Department of Utilities residential fee schedule
https://www.cityofsacramento.gov/utilities/development-standards/residential-fee-schedule
City of Sacramento, Department of Utilities development impact fees
https://www.cityofsacramento.gov/utilities/development-standards/development-impact-fees
City of Sacramento, Reduction of Development Impact Fees for Affordable Housing
https://www.cityofsacramento.gov/community-development/planning/housing/reduction-of-development-impact-fees-for-new-adus
Government Code 66311.5 (ADU impact fees)
https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=66311.5
VanPlex newsletter

Get new guides by email

New VanPlex guides and articles on multiplex rules, building costs and permits, sent to your inbox.

General information, not legal advice. California housing law changes every year, and each city adds its own rules on top of state law. Confirm current requirements with the city or county planning department, and with a California-licensed attorney or architect, before you buy land or file plans.

Planning a multiplex in Sacramento?

VanPlex builds multiplexes in British Columbia, Canada. For a lot in Sacramento, our team makes a custom proforma by hand and emails it to you in 24 to 48 hours.

Get a proforma for your address