Setbacks are the required gaps between a building and the property lines. Together with height, lot coverage and parking, they decide how much building fits on a lot. Sacramento dropped its parking minimums in 2024, and its missing middle ordinance set new setbacks for R-1 to R-2. This page gives those numbers, the tree and levee rules that go with them, and the older base zone figures. The Sacramento overview has a short summary.

Parking, setbacks and height in six facts

Parking: No Minimums Since 2024

The 2040 General Plan ended required parking. Policy LUP-4.14, "Elimination of Vehicle Parking Minimums," says: "The City shall not require new or existing development to provide off-street vehicle parking spaces." The City's missing middle FAQ gives the date: "As of March 28, 2024, General Plan Policy LUP-4.14 (Elimination of Vehicle Parking Minimums) is in effect." It adds that parking "could certainly still be provided" and that the decision is now made "on a project-by-project basis."

The City's Missing Middle Housing page words it more carefully: "With few exceptions, no onsite parking is required by the City code." The page does not list the exceptions. The Parking Revisions page points to two parking rules still in force: vehicle parking maximums for residential development in the Central Business District and the Arts and Entertainment District, and "minimum bicycle parking requirements that are applied to new development that includes most land uses." Both sit in City Code Chapter 17.608.

A change is in progress. An ordinance "Relating to Off-Street Bicycle and Vehicle Parking Requirements" (record M26-005) went to the Planning and Design Commission in 2026, and the Commission reports of March 26 and April 23, 2026 recommended continuing it to later meetings. The Parking Revisions page says the City is considering three parking districts (Central City, Transit-Oriented and Traditional), more bicycle parking, and vehicle parking maximums "in the Central City and within ½ mile of existing high-frequency transit citywide."

If you do build parking, the size rules apply. The City's SB 9 and SB 684 applications ask that each space be at least 10 feet by 20 feet and meet the paving rules of City Code Section 17.612.020, and that driveways meet the width and location standards of Chapter 17.508. For missing middle housing, Section 3.C of Ordinance 2024-0027 turns off "Section 17.612.020, subsections A and C (paving requirements)." The common open space a missing middle project needs "cannot include any part of a driveway or other area dedicated to vehicle parking."

Height and Lot Coverage

For missing middle housing in R-1, R-1A, R-1B and R-2, "The maximum height is 35 feet," and "There is no maximum lot coverage." Lot coverage is the share of the lot that buildings cover. Without a cap, a missing middle project may cover as much of the lot as the setbacks and the required open space leave free. For three or more homes, the building must also fit the base building envelope, which rises 16 feet at the side lot lines and then slopes inward at 45 degrees up to 35 feet. The three or more homes page explains the envelope.

The base zones carry their own heights. The City's September 2020 summary in the Housing Element lists 35 feet for RE through R-3A and for RO, 45 feet for R-4 and RMX, 75 feet for R-4A and 240 feet for R-5. The SB 9 application sets 35 feet for SB 9 projects. Under SB 684, a project must meet the zone's height limit, "unless that requirement physically precludes a housing development proposed to be built to the density of 30 dwelling units per acre."

The zoning update would tie height to the General Plan floor area ratio. The August 10, 2026 rezoning slides list draft limits of 35 feet where the maximum ratio is 1.0 and 45 feet where it is 2.0 in the RE, N-1, N-2, N-3 and RMX zones. The August 3, 2026 missing middle slides say height would be measured to the plate line, where the roof meets the wall, and that a pitched roof could rise 20 percent above the limit if the plate line stays within it. These are drafts.

Missing Middle Setbacks

Section 6.F of Ordinance 2024-0027 sets the setbacks for missing middle housing. Many depend on whether the General Plan gives the lot a maximum floor area ratio below 2 or of 2 or more. The City's March 2026 workshop report ties the 2.0 ratio to lots within a half mile of transit.

Setback Maximum floor area ratio under 2 Maximum floor area ratio of 2 or more
Front (two or more buildings on the block face) Equal to either of the two nearest buildings or in between Same, or 12.5 ft if less (8 ft in the Central City)
Front (one building on the block face) The setback of that building That building's setback or 12.5 ft, whichever is less
Front (no other building on the block face) 12.5 ft (8 ft in the Central City) 12.5 ft (8 ft in the Central City)
Interior side None; 5 ft next to a detached single-unit dwelling (3 ft on interior lots under 52 ft wide or corner lots under 62 ft) Same
Street side 12.5 ft (3 ft in the Central City) 5 ft (3 ft in the Central City)
Rear 15 ft; 4 ft on lots under 2,900 sq ft or on a public alley 10 ft; 4 ft on lots under 2,900 sq ft or on a public alley
Levee 20 ft from the landside toe (50 ft for 5 acres or more) Same

Source: City of Sacramento, Ordinance 2024-0027, Section 6.F. "Central City" means the Central City Special Planning District. The 4-foot rear setback for small or alley lots applies "regardless of the FAR established by the general plan."

The front setback follows the street. With two other buildings on the same block face, the new building may line up with either of the two nearest buildings or sit between them. The SB 684 form asks applicants for "Accurate dimensions of front setbacks for the nearest two adjacent buildings." The interior side setback is the most generous rule in the ordinance: "no interior side-yard setback is required" unless the side line abuts a lot with a detached single-unit dwelling. Then it is 5 feet, or 3 feet on an interior lot under 52 feet wide or a corner lot under 62 feet wide. Townhouse rows can therefore share side walls.

Porches earn extra room at the front. The first and second floors may project into the front setback, and the street side setback of a corner lot, "up to 40% of the required depth of the setback or 5 feet, whichever is greater," if the building has a front porch with a clear area at least 6 feet deep and 8 feet wide. The projection must have a roof, at least one window or door per floor on each street-facing wall, no garage or carport, and a width of no more than half the façade. Upper-floor private open space, such as a balcony, may not sit within 10 feet of an interior side lot line unless that line abuts a nonresidential use or a private street.

Trees and Levees

Sacramento ties its missing middle rules to its tree canopy. Section 6.G requires "At least one 15-gallon tree" in the front-yard setback, plus one in the street side setback on a corner lot. A new or existing tree for every 40 feet of frontage in the street planter, or an existing private protected tree in those setbacks, may count if the City approves. The City reviews the species and location during design review. The rule does not apply when the site is reached only from an alley, when the project keeps a protected tree elsewhere on the lot as a design element, or when an existing City street tree already shades the sidewalk and street.

Keeping trees can buy space. If a private protected tree will be preserved, the decision-maker may let the building go up to 5 feet into the rear, front or street side setback, and up to 10 feet for a tree "with a 32-inch or greater diameter at standard height." Planting a large shade tree in the front or street side yard can allow 5 feet into the rear setback for a species with a mature canopy of 40 feet or more, and 10 feet for 45 feet or more. "No private protected tree ... may be removed without first obtaining a tree-removal permit under Sacramento City Code section 12.56.050." The SB 684 and ADU forms add that tree removal may not be authorized "unless such tree(s) physically preclude the construction of up to two dwelling units of at least 800 square feet."

Sacramento sits behind levees, and the ordinance keeps buildings back from them. "A minimum 20-foot setback from the landside toe of any flood control levee is required for development less than five acres in size," and 50 feet for five acres or more. The landside toe is where the levee slope meets the ground on the dry side. "No primary or accessory structures may encroach into the levee setback." The SB 9 form repeats the 20 and 50 foot rule, and the ADU code says an ADU "may not project into the required setback from the landside toe of a levee."

Base Zone Setbacks and Coverage (2020 Summary)

Projects outside the missing middle ordinance, such as a single home on a large R-1 lot or an apartment building in R-3, use the base zone standards in Title 17. The most complete City summary VanPlex could read is Table H 5-2 of the 2021-2029 Housing Element, dated September 2020. Confirm any figure with the Planning Division, since Title 17 has been amended since then.

Zone Front Rear Interior side Maximum lot coverage
R-1 20 ft (1) 15 ft (2) 3 or 5 ft 40% or 2,500 sq ft
R-1A 20 ft (1) 5 ft 0 ft (3) 50%
R-1B 20 ft (1) 15 ft (2) 3 or 5 ft 60%
R-2 20 ft (1) 15 ft (2) 0 ft (3) Printed as "40% or 25,00 square feet"
R-2A, R-2B, R-3 10 ft 15 ft (2) 0 ft (3) 50%
R-3A, R-4 3 or 5 ft 15 ft (2) 0 ft (3) 60%

Source: City of Sacramento, Housing Element 2021-2029, Table H 5-2. Notes from the table: (1) "10- to 25-feet; average of two nearest buildings"; (2) "5 feet if abuts alley"; (3) none unless the side line abuts a lot in an R-1 or R-1B zone or a lot with a single-unit dwelling, then 5 feet. The street side setback is 12.5 feet in R-1 to R-2 and 10 feet in R-2A to R-3.

Read the R-2 coverage cell with care. The R-1 row says "40% or 2,500 square feet," and the R-2 row prints "40% or 25,00 square feet," with the comma in the wrong place. VanPlex has not seen the current Title 17 text that would settle it, so ask the Planning Division. For missing middle projects in R-2 the question does not arise, because Ordinance 2024-0027 sets no lot coverage limit.

ADUs have their own exemption. Under City Code Section 17.228.105, ADUs that "occupy less than 800 square feet total in lot coverage are exempt from maximum lot coverage and minimum open-space requirements." The ADUs and SB 9 page gives the ADU setbacks, and the SB 9 setbacks of 4 feet at the side and rear.

Best For

  • ✓ Narrow infill lots, where no interior side setback is required unless a detached house is next door.
  • ✓ Lots under 2,900 square feet or on an alley, where the rear setback is 4 feet.
  • ✓ Projects that skip on-site parking and use the space for homes or open space.

Usually Fails When

  • ✕ The plan needs a building taller than 35 feet in R-1 to R-2 before the zoning update is adopted.
  • ✕ A protected tree must be removed and the tree permit rules are not met.
  • ✕ Any structure reaches into the 20-foot levee setback.

What To Verify Before Spending Money

  • → Front setbacks of the two nearest buildings on the same block face.
  • → Your lot's maximum floor area ratio, which changes the front, street side and rear setbacks.
  • → Whether the 2026 parking ordinance has been adopted and what bicycle parking it requires.

Where to Go Next

Related on VanPlex: the Sacramento overview, California energy code and property tax and insurance.

Frequently Asked Questions

Do I need to provide parking for new homes in Sacramento? +
No. Sacramento General Plan Policy LUP-4.14 says the City "shall not require new or existing development to provide off-street vehicle parking spaces." The City's Missing Middle Housing FAQ says the policy has been in effect since March 28, 2024 and that parking decisions are made "on a project-by-project basis." Bicycle parking rules in City Code Chapter 17.608 still apply, and parking that is built must meet the City's size and paving standards.
What size must a parking space be in Sacramento if I provide one? +
Sacramento's SB 9 and SB 684 applications ask that each vehicle parking space, when provided, be at least 10 feet by 20 feet and meet the paving rules in City Code Section 17.612.020. Driveways must meet the objective standards in Chapter 17.508, including width and location. For missing middle housing, Ordinance 2024-0027 turns off subsections A and C of Section 17.612.020, the paving requirements.
Is Sacramento changing its parking rules in 2026? +
Yes, an ordinance on bicycle and vehicle parking (record M26-005) was before Sacramento's Planning and Design Commission in 2026. Commission reports dated March 26 and April 23, 2026 recommended continuing it, the second to May 14, 2026. The City's Parking Revisions page says the City is considering new parking districts, more bicycle parking, and vehicle parking maximums in the Central City and within a half mile of high-frequency transit.
How tall can a missing middle building be in Sacramento? +
Thirty-five feet. Section 6.B of Sacramento Ordinance 2024-0027 says, "The maximum height is 35 feet," for missing middle housing in R-1, R-1A, R-1B and R-2. For three or more homes, the building must also fit the base building envelope, which slopes in at 45 degrees from 16 feet at the side lot lines, unless the block face has no single-unit or duplex dwellings.
What front setback applies to missing middle housing in Sacramento? +
It follows the neighbors. Under Sacramento Ordinance 2024-0027, Section 6.F.1, when two other buildings on the same block face have front setbacks, the new setback equals either nearest building's setback or falls in between. Where the lot's maximum floor area ratio is 2 or more, the setback is capped at 12.5 feet, or 8 feet in the Central City. With no neighbors, it is 12.5 feet.
Can a porch extend into the front setback in Sacramento? +
Yes, for missing middle housing. Sacramento Ordinance 2024-0027 lets the first and second floors project into the front setback by 40 percent of its depth or 5 feet, whichever is greater, if the building has a front porch with a clear area at least 6 feet deep and 8 feet wide. The projection must have a roof and a window or door on each floor, no garage, and no more than half the façade width.
Can I build closer to the property line to save a tree in Sacramento? +
Yes. Sacramento Ordinance 2024-0027 lets the decision-maker allow a missing middle building up to 5 feet into the rear, front or street side setback to preserve a private protected tree, or up to 10 feet for a tree of 32 inches or more in diameter. Planting a large shade tree with a mature canopy of 40 feet, or 45 feet, in the front yard can earn 5 or 10 feet into the rear setback.
Does a Sacramento missing middle project have to plant a tree? +
Usually yes. Section 6.G of Sacramento Ordinance 2024-0027 requires at least one 15-gallon tree in the front-yard setback, and another in the street side setback on a corner lot. A City-approved street tree in the adjacent planter or an existing private protected tree in those setbacks may count. The rule does not apply to a site reached only from an alley, or where the City finds the street already shaded.
What lot coverage applies in Sacramento's R-1 zone? +
For missing middle projects in R-1, none. Sacramento Ordinance 2024-0027 says, "There is no maximum lot coverage." The City's SB 9 application applies the same rule to SB 9 projects in R-1. For other projects, the City's September 2020 summary in Housing Element Table H 5-2 lists R-1 coverage as "40% or 2,500 square feet," R-1A at 50 percent and R-1B at 60 percent.
How far must a Sacramento home stay from a levee? +
Twenty feet from the landside toe of any flood control levee for development of less than five acres, and 50 feet for five acres or more, under Section 6.F.6 of Sacramento Ordinance 2024-0027. "No primary or accessory structures may encroach into the levee setback." Sacramento's SB 9 application applies the same 20 and 50 foot rule, and the ADU code says an ADU may not project into it.

Official sources (checked October 2026)

City of Sacramento, Ordinance 2024-0027, Missing Middle Housing Interim Ordinance (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/Housing/Missing-Middle-Housing/O2024-0027%20An%20Interim%20Ordinance%20Broadening%20the%20Range%20of%20Housing%20Types%20Permitted%20by%20Right.pdf
City of Sacramento, Missing Middle Housing Interim Ordinance FAQ, updated January 6, 2025 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/Housing/Missing-Middle-Housing/MMHOrdinance_FAQs_01.06.25.pdf
City of Sacramento, 2040 General Plan, Land Use and Placemaking Element (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/Long-Range/general-plan-2040/2040%20GP_2-03_Land%20Use%20and%20Placemaking_Amended_20251118.pdf
City of Sacramento, Parking Revisions page
https://www.cityofsacramento.gov/community-development/planning/housing/parking-revisions
City of Sacramento, SB 9 application, Form CDD-0436 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/planning-forms/CDD-0436-SB-9-Ministerial-Approval-of-Two-Dwellings-and-Urban-Lot-Splits.pdf
City of Sacramento, SB 684 application, Form CDD-0684 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/planning-forms/CDD-0684-SB-684-Planning-Approval-Form.pdf
City of Sacramento, Housing Element 2021-2029, Appendix H-5, Constraints (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/Long-Range/Housing-Element/H5_Sac-HE_Amended_Final_Constraints_Dec142021.pdf
City of Sacramento, New Zones and Rezoning webinar slides, August 10, 2026 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/Major-Projects/2040-gp-zoning-consistency/2026-08.10_T17U_Webinar%204%20Rezoning.pdf
City of Sacramento, Missing Middle Housing webinar slides, August 3, 2026 (PDF)
https://www.cityofsacramento.gov/content/dam/portal/cdd/Planning/Major-Projects/2040-gp-zoning-consistency/2026_08.03_T17U_MMH%20Webinar-final.pdf
VanPlex newsletter

Get new guides by email

New VanPlex guides and articles on multiplex rules, building costs and permits, sent to your inbox.

General information, not legal advice. California housing law changes every year, and each city adds its own rules on top of state law. Confirm current requirements with the city or county planning department, and with a California-licensed attorney or architect, before you buy land or file plans.

Planning a multiplex in Sacramento?

VanPlex builds multiplexes in British Columbia, Canada. For a lot in Sacramento, our team makes a custom proforma by hand and emails it to you in 24 to 48 hours.

Get a proforma for your address